A swim spa of this size does not arrive like a carton of chairs. The Outdoor Swim Spa WS-130CⅢ is an 11830 × 3000 × 1430 mm shell with pumps, jets, lighting and a control system built around it, so the order has to be planned as freight, site works and commissioning — not just as a product purchase. The checklist below follows that order from quotation to handover.
Start With the Configuration Sheet, Not the Model Number
The same model code can cover different equipment sets, and the equipment set decides what ships, how it is packed and what the site must supply. For WS-130CⅢ the catalogue lists a control system (1 set), swim training system (1 set), water pump (1 pc), filter pump (1 pc), 20 jets in total, 7 LED lights and a total power figure of 10.85 kW, with water jets, LED lighting, ozone and the swim training system shown as features.
Optional items listed for the range — control systems, UV sterilization, water pumps, heat pumps, sand filtration, insulation and steps — change both the packing list and the electrical load. Availability and compatibility vary by model, so treat the option list as a discussion to close before production, not after.
| Item on the sheet | Why it changes the delivery plan |
|---|---|
| Total power (10.85 kW as catalogued) | Sets the supply capacity, cable sizing and protection your electrician must install before the spa can be commissioned. |
| Heat pump / insulation options | Adds equipment to the shipment and affects running costs in the local climate. |
| UV sterilization and sand filtration | Extra treatment equipment with its own space, plumbing and maintenance access needs. |
| Steps and access items | Influence site layout, surrounding deck height and how users enter the shell. |
| Dimensions 11830 × 3000 × 1430 mm | Determines the lifting route, opening widths, crane or forklift access and final footprint. |
Confirm Site Conditions Before Production Begins
Delivery problems usually trace back to site information that arrived after the order. Collect these before production starts:
- Slab and structure. The finished deck must carry a full water volume plus users. Hand the exact footprint and point loads to the local structural engineer rather than assuming an existing patio will do.
- Electrical supply. Match the supply, protection and earthing arrangement to the confirmed equipment set and to your local wiring rules, which are written by the country of installation, not by the factory.
- Drainage and overflow. Plan drainage for backwash, drainage during maintenance and any overflow route.
- Access route. Check gates, corridors, overhead beams and turning space against the packed dimensions, since an 11.8 m shell cannot be shortened on site.
- Operating environment. For exposed terraces and gardens, insulation and cover options are worth pricing at quotation stage rather than as a later add-on.
Choose the Incoterm and Read the Packing List Together
Freight for an item of this size normally moves by sea, with air or rail considered when timing matters more than cost. Our furniture logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery, including commercial invoices, packing lists, certificates of origin and import permits.
Before booking, ask for two documents and compare them line by line:
- The configuration sheet — every pump, jet set, light, control unit and optional accessory named, with quantities.
- The packing list — number of packages, dimensions, weights and how the shell is separated from plant and accessories.
A mismatch between the two is the earliest warning you will get. Decide at the same time who books the vessel, who acts as importer of record, who pays duty and taxes, where risk transfers, and whether cargo insurance is included or arranged locally. If delivery runs to the villa gate but not into the garden position, that gap belongs in the written scope.
Plan the Delivery Day as a Sequence
- Receive. Inspect packaging against the packing list while the carrier is still present, and photograph any damage on the outer crates before signing.
- Unpack and inventory. Check pumps, jets, lights, control system and small accessories against the configuration sheet. Report shortages immediately — replacement parts crossing a border take far longer than replacing them from a local supplier.
- Set and level. Position and level the shell on the prepared base before any finishing works close in around it.
- Connect. Electrical connection, plumbing and any treatment equipment by licensed local trades, to the confirmed configuration.
- Commission. Fill, run the pumps and jets, check the control system and lighting, and confirm water treatment before handover.
Our furniture installation and after-sales support service covers on-site installation, inspection and snags, warranty coverage, spare parts and replacement, and ongoing maintenance. For a swim spa the practical question is who does what: which stages our team handles, which belong to local trades, and which items are covered by warranty versus normal wear. Get that split in writing with the order.
Ordering With the Rest of the Project
A spa ordered alone arrives as a single crate with no one on site to receive it. Ordered with the rest of the outdoor area, it travels with outdoor furniture for villas and resorts — loungers, dining sets, pergolas — under one shipping schedule and one site visit. Where the spa has to fit a particular garden line or terrace shape, the customizable shape outdoor spa in the same range is worth reviewing at design stage rather than after the deck is built.
Documents to Have Ready Before the Vessel Departs
- Commercial invoice with values agreed for customs, matching the packing list quantities.
- Packing list covering shell, plant and accessories as separate line items.
- Bill of lading with the correct consignee and delivery address.
- Certificate of origin and any import permit your broker requires.
- Configuration sheet, wiring requirements and commissioning notes for the receiving team.
A Simple Timeline to Work Back From
Fix the site-ready date first, then count backwards: commissioning and snag time, installation by local trades, sea transit plus customs clearance, production of the confirmed configuration, and finally the quotation period spent closing option choices. Every week saved on the option list is a week you can spend on site preparation instead.