An open-plan kitchen is rarely the last decision on a project drawing set, yet it is usually the first thing a buyer, guest or resident notices when they walk in. Cabinetry that reads as one continuous surface with the living area has to be planned long before any wall is closed up: services have to be routed, sightlines fixed, storage programmed and finishes matched to everything else in the room. The installation plan for open plan kitchen cabinetry is therefore not a set of fixing details alone. It is the document that carries every coordination decision from design into production, delivery and site fitting.

Below is what we ask project teams to put into that plan when we manufacture custom cabinetry for hotel suites, serviced apartments and residential open kitchens, based on how our own workshop, logistics and installation process works.

1. Measured base conditions, not design-model dimensions

Custom cabinetry is made to the millimetre, so the plan should start from a survey of the space as it actually is or as the structural and finishes drawings show it will be. Record overall length and height of each run, floor levels across the room, the position of columns, beams and skirting, and the location of every existing riser or duct. Where wall surfaces will be tiled, paneled or clad in stone, note the build-up thickness, because that is what changes a reveal by 20 mm or more once the cabinets arrive.

For hotel and apartment repeats, the plan should state which units are identical and where the tolerance sits. A typical guest-room kitchenette repeated across floors only works if one dimension set is fixed as the reference and every deviation is called out unit by unit.

2. The layout decision: what stays open and what gets closed

An open-plan run has no wall to hide behind, so storage has to be programmed deliberately. Our open concept kitchen cabinets are built on the same principle: the layout is drawn around how the space will be used, with tall units for dry goods and small appliances, deep base drawers for pots, and open shelving or niches reserved for pieces that are meant to be seen. Decide in the plan which sections are open shelves, which are glass-front display cabinets and which are closed doors, because each choice affects panel thickness, shelf load and edge detailing.

The plan should also fix where appliances sit — oven, hob, extractor, dishwasher, refrigerator, wine cabinet — with the model or at least the cut-out envelope agreed before panels are cut. Appliance positions drive ventilation gaps, door swing direction and the position of sockets, so changing them after production starts is the most expensive revision in the whole job.

3. First-fix services mapped onto the elevation

Water, waste, power, data and lighting all have to be shown on the same drawings as the cabinetry elevations, with dimensions from a common datum line. In an open-plan kitchen this matters more than in a closed one because worktops, islands and breakfast bars are visible from the living area: no one can tolerate a socket that lands in the middle of a glass splashback zone or a waste pipe that forces a plinth to be built out.

  • Cold and hot water outlets, waste positions and any boiling or filtered water tap provision
  • Socket outlets for worktop appliances, built-in appliances and internal cabinet power, with their heights marked on the elevation
  • Lighting circuits for under-cabinet, in-shelf and toe-kick lighting, including where the driver or transformer will be accessible for maintenance
  • Extractor routing, whether ducted to outside or recirculating, and the ceiling route it will take through the open space
  • Island services: floor boxes, cable runs and how they are reached after the floor finish is laid

4. Materials, finishes and hardware schedule

The plan should name every material the buyer will receive: panel substrate, door style, surface finish, colour reference, edge treatment, worktop material and the full ironmongery set. Our custom built-in kitchen cabinets are supplied with matching hinges, drawer slide rails, support legs and connecting brackets, so the hardware schedule is part of the manufacturing record rather than something the site team improvises. For open-plan work we normally specify soft-close fittings throughout, since door and drawer noise carries straight into the living area.

Finish selection also needs a maintenance line in the plan. Surfaces in an open kitchen are touched constantly and are visible from across the room, so we use wear-resistant, waterproof panels that wipe clean, and we state the recommended cleaning method for each finish. Where a project specifies matte lacquer, acrylic, melamine, veneer or laminate, record which is used on which elevation — matching tones under different lighting conditions should be approved from physical samples before order.

5. Interface details with the rest of the open space

Because the kitchen shares a room with the lounge and dining area, the installation plan has to close out every junction where cabinetry meets another trade. Left unresolved, these are the joints that spoil the look of an otherwise clean run.

InterfaceWhat the plan must fix
Floor and plinthFinished floor level, whether cabinets sit on an adjustable plinth or a built-out recess, and how the plinth is detailed at the open end of a run
Ceiling and tall unitsClear ceiling height, scribe or filler to ceiling, and whether tall units are integrated into a full-height paneling wall
Worktop and splashbackWorktop material and thickness, upstand detail, cut-outs for sink and hob, and the joint to tiled or stone splashback
Island or peninsulaEnd panel returns, overhang for seating, integrated lighting and how services are accessed from below
Adjacent joineryTonal match between kitchen doors and wardrobes, media walls or pantry units supplied by the same package

6. Production, packaging and delivery sequence

Once drawings are signed off, the plan moves to the factory: panel cutting, edge banding, finishing, assembly checks and hardware packing. For project orders this stage should show unit numbers on every crate so that what arrives on site can be matched directly to the room schedule rather than sorted by hand.

Delivery planning belongs in the same document. State the shipping mode, the port or site address, who handles customs clearance, and how the consignment is staged. Where a project has several identical kitchenettes, crates should be labelled so each unit can go straight to its floor and apartment. Panels, worktops and glass are the fragile items in any cabinet consignment, so packing method and container loading order should be agreed with the freight forwarder rather than left to the last week.

7. Site preparation and installation sequence

The section most often missing from a cabinetry installation plan is the condition the site must reach before cabinets are unpacked. In practice we need: wet trades finished and floors level, wall finishes complete to the recorded datum, first-fix services tested and pressure-tested, lighting circuits proven, dust down, and safe storage on site for large panels. Installing into a room still being painted or tiled is how scratched panels and blocked waste connections happen.

The installation sequence itself should be written out: carcass and tall units first, then base runs levelled to the floor, worktops templated or fitted, appliances set and connected, doors hung and adjusted, hardware and internal fittings installed, lighting commissioned, then a snag inspection with the site team. Our furniture installation and after-sales support covers on-site fitting, inspection with a snag list, spare parts replacement and ongoing maintenance, so the plan should record who signs off each stage.

8. Approvals, responsibilities and handover records

A workable installation plan names the decision-maker for every open item: who approves the finish samples, who confirms appliance cut-outs, who signs off first-fix positions, and who receives the completed units. It should carry a revision log with dates, because cabinetry drawings change hands between designer, contractor and factory many times during a project.

Handover closes the loop. The plan should list what the client receives at completion: as-built elevations, the material and hardware schedule, care and cleaning instructions for each surface, spare hinge and runner sets, and the contact route for warranty claims and replacements. For a hotel or apartment operator running dozens of identical kitchenettes, that record is what keeps maintenance consistent years later.

How this fits into a one-stop project package

Kitchens are rarely ordered alone. When cabinetry is procured through one-stop furniture and building materials project procurement, the same team coordinates the flooring, wall panels, doors, lighting and bathroom fixtures around the kitchen elevations, which removes most of the interface conflicts described above. Our cooperation steps run from project brief and design proposal through quotation and detail confirmation to production, shipment and follow-up; under custom furniture design and prototyping we can tailor layout, dimensions, door styles, materials and finishes to the drawing set you already have.

Before sending drawings for quotation, have three things ready: a measured survey or dimensioned base plan, the appliance list with cut-out sizes, and the finish direction confirmed by sample. Those three inputs decide whether the installation plan can be executed as drawn or has to be redrawn after production starts.

Send us your kitchen elevations, room dimensions and project location, and we will return a cabinetry proposal with layout, material schedule, hardware list, delivery plan and installation sequence for review. Contact SANTERSON to start the detail confirmation stage for your hotel, apartment or villa project.