A swim spa on a villa terrace or a resort deck looks straightforward on a mood board: a shell of water, some jets, lighting, done. In procurement it is one of the few line items that combines structure, plumbing, high electrical load and daily wet-area maintenance in a single delivery package. That is exactly why approval should not happen at quotation stage. The Outdoor Swim Spa WS-SP600 is a configurable model, and two units with the same name can arrive with different equipment and different power requirements.

The checklist below is written for the people who actually sign the purchase order: project managers, procurement leads, M&E consultants and client representatives on villa, resort and hospitality fit-outs.

1. Confirm which configuration you are approving

Model codes in this range carry suffixes that change what is supplied. The WS-SP600 and the WS-SP600-MS share the same catalog shell dimensions, but their captured specification sheets differ: the standard listing shows 6 jets and a total power figure of 9.35 kW, while the -MS listing shows 29 jets, an additional water pump and 11.55 kW.

Specification (as listed in catalog)WS-SP600WS-SP600-MS
Catalog dimensions5900 × 2500 × 1600 mm5900 × 2500 × 1600 mm
Jet total6 pcs29 pcs
Water pumpNot listed in the captured spec sheet1 pc
Filter pump1 pc1 pc
Control system1 set1 set
Swim training system1 set1 set
LED lights44
Total power9.35 kW11.55 kW

Practical consequence: the jet count is what a client feels in the water, and the power figure is what your electrical engineer has to serve. Do not let either one be decided by whoever fills in the proforma invoice. Ask for the specification sheet of the exact model code on the quotation, and attach that sheet to the purchase order as a controlled document.

2. Confirm the site condition before the shell is manufactured

A 5900 × 2500 × 1600 mm unit full of water is a heavy point load, and once it is on a slab it cannot be moved for structural reasons. Before approval, close out these items with the local structural engineer:

  • Slab or deck load capacity for a filled spa plus occupants, checked against the finished dimensions rather than the shipping dimensions.
  • Whether the unit sits on a prepared plinth, a raised timber or composite deck, or a terrace with waterproofing that must not be penetrated.
  • Access and drainage around the cabinet, because filters, pumps and the control system need reach for routine service.
  • Clearance for steps and any optional cover, which are catalog options rather than standard inclusions.

Where the spa is part of a wider terrace design, coordinate it in the same drawing set as the outdoor furniture for villas and resorts, such as loungers, daybeds and storage, so levels, drainage falls and traffic routes are resolved once instead of twice.

3. Confirm the electrical scope in writing

Total power on a spec sheet is not an electrical design. Before approval, obtain from the supplier and confirm with your M&E consultant:

  • Supply voltage, phase and frequency assumed by the quoted configuration, compared with what is available on site.
  • Cable size, protection and dedicated circuit requirements for the confirmed total power figure of the selected model.
  • Earthing, RCD/residual current protection and bonding requirements as specified for the installation location by your local regulations; these must be signed off locally, not assumed from factory practice.
  • Which items in the quotation are optional additions that change the load: heat pumps and additional water pumps both alter the electrical demand.

If a heat pump is added after the order is placed, the electrical design usually has to be revisited. Decide at approval stage.

4. Confirm what is included and what is optional

Catalog-listed options for this range include control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps. Availability and compatibility vary by model. Write an inclusions/exclusions table into the purchase order, because disputes at handover almost always come from items both parties assumed were standard.

A useful rule: if an item is not on the attached specification sheet with a quantity against it, treat it as not supplied. That includes steps, covers, insulation and any water or heat pump.

5. Confirm who operates and maintains it after handover

The maintenance question decides several specification choices, so it belongs at approval rather than at handover:

  • Ozone is shown as a feature on this model; UV sterilisation is listed as an option. Decide which water-sanitisation approach the operator can actually maintain.
  • Insulation matters for year-round use and for energy demand, so it should be priced before approval if the spa runs outside warm months.
  • Filter access and spare-parts supply set the service routine for a hotel or resort operator with no tolerance for downtime.

For hospitality projects, this is also where the swim spa stops being a single product line and becomes part of a wider package. When the same supplier handles cabinetry, bathroom fixtures, lighting and outdoor furniture under turnkey interior project solutions, one coordination team can align the spa delivery with deck works, electrical first fix and the rest of the outdoor package.

6. Confirm the logistics and installation sequence

  • Freight mode and packaging for a spa shell, by sea, air or rail, with customs paperwork prepared alongside the commercial invoice and packing list.
  • Site delivery route: gate widths, turning areas, crane or forklift needs, and whether the deck is complete before the unit lands.
  • Who connects and commissions the unit on site, and who witnesses the first fill and function test.
  • Snag list and defect responsibility at handover, recorded in writing with the as-built configuration attached.

For projects outside the factory's country, furniture logistics and door-to-door delivery and installation and after-sales support are separate service scopes. Confirm which of them are included in your quotation, since a spa that arrives without a commissioning plan still leaves you with an untested product.

Approval checklist before signing

  • Exact model code on the quotation matches the attached specification sheet, including jet count and total power.
  • Structural sign-off for the filled unit at the confirmed position.
  • Electrical design based on the selected configuration, including any heat pump or extra pump.
  • Written inclusions/exclusions list covering pumps, steps, covers, insulation and sterilisation.
  • Maintenance plan with named operator, spare-parts route and filter access confirmed.
  • Delivery route, commissioning responsibility and snag process agreed before order placement.

Send the model code and your site conditions to our project team, and we will return a configuration sheet with equipment list, power requirement and delivery scope for that specific installation, so what you approve is what gets built and shipped.