Wall panels look simple on a drawing. A sheet goes on a wall, the elevation looks clean, and the schedule gives them one line. On site they turn into something else entirely: substrate questions, finish samples that never come back signed, joint details that three trades interpret differently, and a delivery date held hostage by a single unapproved sample. If your project has wall panels and wall cladding anywhere in the scope, approvals are the work that decides whether the package lands on time.

This guide sets out a practical approval route for project teams, contractors, interior designers and procurement leads. It covers who signs what, which documents remove guesswork, how to sequence samples, and what to confirm before an order is released. Everything we manufacture is made to measure, so the paperwork stage is where your dimensions and finish choices get locked in.

Why Wall Panel Approvals Slip

Paneling sits at the junction of several packages, and every package has its own approver. The designer wants the joint line and the surface texture right. The builder wants to know what is behind the panel and how it fixes. The client wants to see the colour before anything arrives. The procurement lead wants a fixed price against a fixed quantity. When those four people approve different things, or approve at different times, the order cannot be released.

The second cause of slippage is specification drift. A project starts with a decorative feature panel in a lobby, then the same look gets extended into a corridor, then into guest rooms. Each extension changes quantities, panel sizes and sometimes the material itself. If the approval record does not follow that growth, you end up with panels made to an earlier version of the design.

The third cause is treating all panels as one line item. A Santerson Acoustic Panels schedule, a Santerson Partition Sliding Systems opening and a fixed Wall Panel Systems wall all need different confirmations. Acoustic panels raise questions about the build-up behind them. Sliding systems raise questions about track, hardware and clear opening dimensions. Fixed paneling raises questions about substrate flatness and edge details. Bundling them into one approval is how projects lose weeks.

Who Approves What

Write the approval map down at the start of the package. One name per decision, one date per decision. In practice you usually need five signatures, and they do not all sign the same document.

DecisionPrimary approverConsultedEvidence that closes it
Panel material, colour and surface textureInterior designer or design leadClient / owner representativeSigned physical sample with reference number
Layout, joint positions and set-out dimensionsArchitectural designer or detailerSite builder, manufacturer technical teamApproved dimensioned drawing, signed and dated
Substrate preparation and fixing methodMain contractor / site engineerManufacturer installation teamMethod statement plus on-site mock-up sign-off
Quantities, unit rates and delivery sequenceProcurement or commercial managerSite plannerCountersigned order confirmation and packing schedule
Budget release and any variation to itClient / owner representativeCommercial managerVariation note referencing the approved sample and drawing

The point of the table is not bureaucracy. It means that when a decision stalls, you know exactly whose desk it is on and what document will unblock it.

The Four Documents That End Most Arguments

1. A dimensioned set-out drawing per wall

Not one general elevation for the whole floor. One drawing per wall run, with finished dimensions, panel widths, joint locations, and how the run resolves at ceilings, floors, door reveals and internal corners. Made-to-measure paneling is cut from these numbers. If a dimension on the drawing does not match what the builder actually built, the panel will not fit, and that becomes a variation.

2. A physical finish sample with a reference number

Screens lie about colour and texture, particularly for wood grain, stone look and matte lacquer surfaces. Approve the actual surface on a physical sample, then keep that sample in the project file with the same reference used on the order. When a delivery arrives, the sample is how you check it. A signed sample also protects the client: they can see the sheen level and the grain scale before panels are produced.

3. A joint and edge detail

Most on-site disappointment comes from joints, not panels. Draw how two panels meet, how a panel meets plaster or stone, how an inside corner is formed, and whether trims are used or the joint is shadow-gap. Aluminium and stainless steel decorative profiles exist for exactly these conditions, and choosing them late changes both cost and lead time.

4. A site mock-up

For hospitality and multi-unit residential work, build one small area at real quality before the main order is released. Two square metres on a real wall, with the real substrate, the real fixing method and the real joint detail. The mock-up settles arguments that drawings cannot: how the surface reads under the actual lighting, whether the joint line is acceptable at close range, and how long installation actually takes per person.

Sequencing Approvals Around a Made-to-Measure Order

Paneling that is manufactured to project dimensions cannot start until dimensions are confirmed. That single fact drives the whole programme, so work backwards from it.

  • Early design stage: confirm the panel families you need and which walls they apply to. Material direction, not final colour.
  • Technical design stage: issue set-out drawings and joint details for approval. Request finish samples against those drawings, not out of a catalogue in isolation.
  • Pre-order stage: sample signed off, drawing signed off, substrate method agreed with the builder. Only then measure on site.
  • Order release: quantities and dimensions countersigned, delivery sequence agreed against the site programme.
  • Pre-installation: mock-up inspected and accepted before panels come out of packaging in volume.

Where a project carries several wall systems, run the approvals in parallel rather than in series. Sliding panel hardware, acoustic build-ups and decorative feature walls can each be sampled at the same time, as long as one person owns the register that tracks them.

Approval Checkpoints Before You Release an Order

Walk this list with the client and the builder in the same room. Anything left blank is a variation waiting to happen.

  • Wall-by-wall set-out drawings signed and dated, with finished dimensions taken from the built condition, not the tender drawing.
  • Physical finish sample approved, referenced on the order, and retained in the project file.
  • Joint, edge and trim details agreed, including how panels meet ceilings, floors and door reveals.
  • Substrate flatness and preparation responsibility assigned to a named trade, with a date.
  • For sliding or operable systems: track type, hardware finish, panel weight allowance and clear opening dimensions confirmed in writing.
  • For acoustic walls: the build-up behind the panel face confirmed by the party responsible for performance.
  • Quantities reconciled against the approved drawings, with a stated allowance for cuts and replacements.
  • Delivery sequence agreed per floor or per zone, so panels do not arrive before the substrate is ready.
  • Storage conditions on site confirmed for moisture-sensitive panel materials.
  • One named approver for each item above, with a target date against the programme.

What to Confirm With the Manufacturer Before Order Release

Our configurable wall products are specified per project rather than ordered off a stock list. For Wood Panel Partitions, Custom Niche Paneling and Integrated Door & Paneling, the same three confirmations apply: the layout, the material and finish selection, and the measured dimensions. For a run that includes an integrated door, the door opening and the panel module have to be drawn together, or the reveal will not line up.

For exterior and high-traffic cladding, the conversation shifts. Aluminum Honeycomb Panel for Building Exterior & Interior Wall Cladding raises questions about panel size, flatness tolerance, fixing system and how the facade detailing handles movement joints. For curved walls, arches and renovation work where a rigid board cannot bend to the surface, flexible sheets such as Flexible Wood Grain Cement Wall Panel change both the approval sample and the installation method, because they are cut, drilled and formed on site. Confirm performance expectations against the actual product data sheet for each project, since requirements differ by location and use.

Where decorative effect rather than cladding is the goal, Decorative Wall Panel for Interior Home Decoration and Modern Decorative Wall Panel for Interior Decoration are approved on texture, panel size and pattern scale. These read very differently at three metres than they do in a hand sample, which is exactly why a mock-up belongs in the approval route.

Keeping One Approver Across Furniture and Finishes

Wall paneling rarely travels alone. It meets cabinetry, doors, flooring, lighting and joinery, and those packages share the same junctions. A media wall is a good example: Santerson Integrated TV Panels involve paneling, the recess for the screen, cable routes and sometimes Santerson Backlit Feature Walls lighting behind the surface. If the panel approver and the lighting approver are different people working from different drawings, the recess gets built to one set of numbers and the panel to another.

For villa and hospitality projects, turnkey interior project solutions put those approvals under one coordination path, with a single team handling design, material selection, production, logistics and site coordination. That matters most on multi-unit work, where the same detail repeats across floors and one unresolved approval delays every repetition of it.

Common Failure Modes and How to Close Them

The sample was approved but the drawing was not. Production starts from an unapproved layout. Fix: no order release until both carry a signature and a date, with the same reference number on each.

Dimensions came from drawings rather than the built condition. Panels arrive for a wall that no longer exists in that form. Fix: site measurement after substrate completion, signed by the person who will install.

Approvals spread across many emails. Nobody can say what is currently approved. Fix: one register listing every wall, its approver, its status and its date, reviewed weekly on programme.

Substrate responsibility left vague. Panels get fixed to an unprepared wall and the finish telegraphs through. Fix: method statement naming the trade responsible for flatness, with a tolerance stated.

Deliveries ahead of readiness. Panels sit on site, get damaged, then get blamed on the material. Fix: sequence deliveries by zone against the site programme and confirm storage before dispatch.

Ready to Move Your Panel Package Through Approval

Send us your drawings and we will tell you what is still open

Share your elevations, the wall locations and the finishes you are considering. We return a dimensioned set-out for review, finish samples to approve against it, and a list of any details that need a decision before production can be scheduled. As a manufacturer handling furniture and building materials in one package, we coordinate paneling with cabinetry, doors and joinery so junctions are agreed once rather than re-argued on site.

Contact PHILLIP to start a specification review for your villa, hotel or office project: https://www.santerson.com/contact/

All panel dimensions, materials, finishes and installation methods are confirmed per project. Please verify product data sheets and local requirements for your specific application before ordering.