A swim spa of this size is not a line item you can approve from a brochure page. It arrives as a delivered shell, needs power and a prepared base before the crane or forklift leaves the site, and then has to be commissioned by someone who knows the equipment inside it. The checks below are the ones project teams most often leave too late on a swim spa order, and each one has a document you can ask for before the purchase order is signed.

Start With the Footprint, Not the Water

The catalog figure for this model is 11830 x 3000 x 1430 mm. Treat that as a starting dimension to verify against the drawing issued with your quotation, because the shell you receive has to clear more than its own outline. A spa just under twelve metres long needs an access route that can take it intact: gate widths, turning radii at corners, overhead clearance under power lines or tree canopy, and a hard surface for the delivery vehicle. On villa sites this is where projects fail first. The unit reaches the property on a truck, and if the drive narrows to three metres at the boundary wall, the whole delivery has to be re-planned around a heavier lift.

Ask your supplier for a dimensioned drawing that shows the shell, the plant compartment, the access hatch positions and the lifting points. Then walk the route on site with a tape measure before you approve anything. This costs an afternoon; re-routing a delivery after production has started does not.

Confirm the Base and Drainage Before Production

A filled spa of this length is heavy, and the slab or pad under it must be designed for that load with the finished level already decided. Two things need to be settled while the spa is still in manufacture:

  • The finished top level of the base, so the coping and any surrounding decking, steps or seating tie into it correctly rather than being built to guesswork.
  • Where overflow, drain-down and any plant-room discharge actually go, including the route of those pipes and whether they fall far enough to work without a pump.

If the spa sits on a terrace or upper level rather than at grade, the structural engineer has to sign off the loading before the shell is ordered. That single dependency should sit on your programme with a date, because nothing else in the wet area can be released until it is closed.

Get the Power Supply Agreed in Writing

The catalog entry for this model lists a total power figure of 10.85 kW, with one control system, one water pump, one filter pump and twenty jets. That number is a specification reference, not an electrical design. The load you actually install depends on the configuration chosen: whether a heat pump is included, what insulation package is specified, whether any optional accessory adds a circuit, and which supply voltage and phase arrangement the site can provide. Note that closely related variants in this range carry different jet counts, pump counts and power figures at the same shell size, so the figure you hand to the electrician must be the one for your exact model code.

Before the order is placed, ask for the electrical schedule for your exact configuration: total connected load, supply voltage and phase, recommended breaker rating, cable sizing guidance, and the location of the isolator. Hand that schedule to the local electrician, not to a general contractor working from the product page.

Local wiring is normally carried out by a licensed electrician on site under the rules that apply where the building stands. A supplier shipping units internationally does not design or certify that installation for you. Confirm in writing which side of the interface each party owns, and put the isolator and control access somewhere a maintenance technician can reach without moving furniture or draining water.

Decide Which Model Variant You Are Actually Buying

This range carries closely related model codes, and the differences are in the equipment list rather than the shell size. The catalog entry for WS-130CIII lists a swim training system among its features, while the matching -U variant of the same shell size lists water jets, LED lighting and ozone without that item, and shows a different pump count, jet count and power figure. Both are described at 11830 x 3000 x 1430 mm.

That is precisely the kind of overlap that causes disputes at handover. If the client's brief says "lap swimming", the swim training unit has to appear on the packing list and in the commissioning sheet, not only in a marketing paragraph. Match every line of the quotation against the specification table on the product page you are buying from, and have the supplier confirm the final configuration as a dated document before production starts.

Reference catalog figures for this model

ItemCatalog entry
ModelWS-130CIII
Dimensions11830 x 3000 x 1430 mm
Control system1 set
Swim training system1 set
Water pump / filter pump1 pc / 1 pc
Jets20 pcs
LED lights7 pcs
Total power (reference)10.85 kW

Verify these against the drawing and specification issued for your order. Catalog pages describe a range; your contract should describe one specific build.

Settle the Optional Equipment Early

Options listed across this range include control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps. Each of them changes something else on site:

  • A heat pump adds a circuit and an outdoor position with its own clearance and noise considerations.
  • Insulation affects running cost in cooler climates and is far easier to specify now than to add later.
  • Sand filtration needs a location, access for backwashing and somewhere for the waste water to go.
  • Steps and seating need to be coordinated with the deck level you have already set.

Late additions to a unit already in production usually mean either a change order with its own lead time or a field workaround. Freeze the option list at the same meeting where you sign off dimensions.

Plan the Delivery Sequence and Who Unloads

For an oversized shell, agree in writing how the unit arrives, what it arrives on, and what lifts it off. Confirm whether a crane, forklift or manual carry is required at your site address, who books that equipment, and who pays for it if the access you described on paper does not match what the driver finds. Also confirm packaging, container loading and the shipping documents for import, since paperwork errors delay clearance far more often than freight does.

Once the shell is in position, resist connecting it before inspection. Check the acrylic shell for transit damage, count the delivered items against the packing list, and photograph everything before the packaging goes out of the site. That record is what makes a claim straightforward if something arrived damaged.

Agree Commissioning and After-Sales Terms

Before approval, get clear answers on four points:

  • Who commissions the unit and what is tested at handover — jets, filtration cycle, ozone, lighting, controls and the swim training system if fitted.
  • What warranty applies, to which components, for how long, and what voids it. Water treatment chemistry is a common exclusion, so ask specifically.
  • How spare parts are supplied and how quickly, given that the unit was manufactured offshore.
  • What water-treatment regime the manufacturer recommends for ongoing operation, since poor chemistry is the usual cause of early equipment failure.

If your project also needs decking, outdoor furniture, pergolas or shade structures around the spa, sourcing those from the same supplier as the wet area simplifies coordination of levels and finishes. The swimming pool and swim spa range sits alongside outdoor furniture collections in the same catalogue, which is useful when one team has to reconcile drawings across several trades.


A Pre-Approval Checklist

  • Dimensioned drawing received, with lifting points and plant access marked
  • Site access route measured and signed off by the person organising the lift
  • Structural sign-off for the base obtained where the spa is not at grade
  • Finished base level, drainage routes and overflow connection fixed on drawing
  • Electrical schedule for the exact configuration issued to the local electrician
  • Model code and equipment list matched line by line against the quotation
  • Options frozen: heat pump, insulation, UV, sand filtration, steps
  • Delivery method, unloading plant and import documents confirmed in writing
  • Commissioning scope, warranty terms and spare-parts route agreed before order

Every item above is a document you can request from the supplier before the purchase order is signed. If any of them cannot be produced, that is the point at which to resolve it — not after the shell is on site.

Send us your site conditions and we will confirm what fits

Share the plan for your wet area, the access route and the intended configuration. As a China-based manufacturer of swim spas and outdoor leisure products, we work through dimensions, equipment lists, options and delivery logistics with project teams before production starts — including villa and hospitality projects across the region. Contact SANTERSON to start that conversation.