A set of aluminum frame cabinets with solid panel doors looks simple on a drawing. It is a box, a door, some hinges. That simplicity is exactly why kitchens built to this detail go wrong on site: the tolerance that the frame leaves for the panel, the way the run meets an out-of-square wall, and the order in which services, carcasses and doors arrive all have to be settled before production starts, not after the cabinets land.
This article sets out what a working installation plan for Aluminum Frame with Solid Panel cabinetry should contain, from the survey sheet through to handover. It is written for contractors, project managers and procurement teams who order made-to-measure cabinetry from a factory and have it assembled by a local crew.
Why this detail needs its own plan
Aluminum frame kitchen cabinets are supplied as a collection in which the frame, the panel insert, the finish and the layout are all specified per project. Our Aluminum Frame with Solid Panel line is made to measure, with material and finish options and a layout tailored to each space, so the drawings you send back are what get manufactured. There is no standard carcass width to fall back on.
Two consequences follow. First, an error in the survey does not become a trim problem on site; it becomes a re-made component and a delayed handover. Second, a solid panel door behaves differently in the run from a glazed one. Within this collection we also supply Glass Front Aluminum Frame Cabinets and Smoked Glass Aluminum Cabinets, where the frame carries a glazed infill. Swapping to a solid panel changes what sits in that same frame, so hinge specification, door-to-door clearance and the reveal around the opening need confirming for the doors you have chosen rather than assumed from another variant. Those decisions belong on paper in the plan.
1. A survey record, not a floor plan
The installation plan starts with measured site data taken after the wet trades have finished and the final wall finish is in place. At minimum it records:
- Run lengths along each wall, measured at three heights, not one.
- Plumb and square checks at every internal and external corner in the run.
- Finished floor level and finished ceiling or soffit level, with the tolerance band.
- The depth of any skirting, tile upstand or cornice that the carcass has to scribe to.
- Position and height of every waste, soil stack, water outlet, spur and extract duct that falls inside a cabinet zone.
- Window reveal and door opening heights where base or tall units pass alongside them.
Where a wall is out of plumb, the plan should say which end takes the scribe and what the maximum filler width is. A plan that only shows nominal run dimensions pushes the problem onto the installer with no agreed solution.
2. Confirmed frame, panel and finish schedule
Because sizing, material and finish are specified per project, the plan needs a schedule that locks each of them down unit by unit before the order is released. The table below shows the form we find works best for this collection.
| Item | What the plan must state | Why it matters on site |
|---|---|---|
| Frame profile | Color and finish of the aluminum frame; whether the profile is the same on wall units, base units and tall units | Mixed profiles in one run read as a mistake even when each unit is correct |
| Panel insert | Panelling material, surface finish and color reference for solid panel doors | Finish samples under site lighting differ from catalogue images |
| Door layout | Opening direction, hinge side, door-to-door gap, handle or handleless edge | Determines the cut of every adjacent carcass |
| Unit dimensions | Finished width, height and depth of each unit as built, including scribes and fillers | The installer packs to these numbers, not the drawing scale |
| Internal fitments | Shelf positions, drawer stacks, pull-out trays, appliance housings | Drilled once; changing them after delivery means a re-made component |
Where a project mixes finishes on purpose, say so in the schedule. A run that pairs solid panel doors with Two Tone Aluminum Frame Cabinets or a Minimalist Black Aluminum Frame Cabinets accent needs the break point marked on the elevation, with the transition detail drawn.
3. Services coordination and first-fix sign-off
Cabinetry is the last thing to arrive and the first thing everything else has to fit around. The plan should carry a services drawing showing electrical outlets, switched spurs, water and waste points, and extract routes, each dimensioned from a fixed corner of the run rather than from the cabinet itself.
Then it needs one line that is usually missing: a named date on which first-fix positions are signed off as built. Any outlet moved after that date changes the panel cut, and a cut made in an aluminum frame with a solid infill cannot be corrected by shifting a shelf or trimming a filler.
4. Sequence, access and delivery
Made-to-measure cabinetry arriving from overseas has to be received properly or the schedule is lost. The plan should cover:
- Pack list matched against unit numbers on the elevations, checked at the point of delivery.
- A dry, secure storage area large enough for the full run, with doors stored flat and framed panels upright.
- Route from the delivery vehicle to the kitchen: door widths, lift dimensions, corridor turns, and whether any unit has to be assembled in place because it cannot be carried in one piece.
- A sequence that puts carcasses, then worktops, then doors and trims, then hardware adjustment, with each stage signed off before the next begins.
For projects where the cabinetry travels with other interior fixtures, it is worth ordering them together. Our Custom Built-in Kitchen Cabinets are supplied as interior fixtures for hotel, apartment and residential renovation work with matching hinges, drawer slide rails, support legs and connecting brackets, so one delivery window covers the cabinetry and its ironmongery instead of two.
5. Installation method statements the installer can follow
Rather than a single general note, the plan should carry short method statements for the details that decide the outcome:
- Levelling and fixing. How base units are levelled across an uneven slab, what the fixing substrate is at each wall, and whether the run is joined as one line or broken at a corner.
- Scribing. Maximum filler width, scribe direction, and how scribes are finished so the frame edge stays continuous.
- Hanging wall units. Rail or cleat type and fixing centres for the wall substrate, agreed with the site engineer before drilling.
- Door adjustment. Who sets hinge alignment, and at what point in the sequence - after worktops and trims, not before.
- Worktop junctions. Whether the worktop sits on the carcasses or is scribed to the wall first, and how the frame meets the upstand.
The product page for this collection states that dimensions and selected specifications are to be confirmed for each project. The installation plan is where that confirmation happens; a plan carrying only nominal sizes from a design drawing is not yet ready for production.
6. Snag list and handover
Close the plan with the record it leaves behind: door alignment and gap tolerances checked run by run, drawer and hinge operation, worktop seals at wet zones, a note of any panel or door replaced after delivery, and as-built dimensions for any unit that had to be re-made. This is what makes a follow-up order for a second phase straightforward instead of another full survey.
A short checklist
- Site survey taken after final finishes, with plumb and square recorded.
- Frame, panel material, finish reference and unit dimensions confirmed per unit.
- Services drawing with a signed first-fix date.
- Delivery route, storage area and pack-list check agreed.
- Method statements for levelling, scribing, hanging, worktops and door adjustment.
- Snag list format and as-built record defined before the crew arrives.
Can an aluminum frame with solid panel be ordered to the same sizes as a standard carcass kitchen?
No. This collection is made to measure, with layout, sizing and finish specified for each space, so the dimensions come from your survey rather than a catalogue module range.
Should solid panel doors be specified together with glazed doors in the same run?
They can appear in the same project, but a glazed infill and a solid panel are different products within the collection. Keep the change of infill at a defined break point, mark it on the elevation, and confirm the door specification for each variant separately.
Who should hold the installation plan?
Both the party ordering the cabinetry and the crew fitting it should work from the same revision. Where we supply the run, our service covers project design coordination, including drawings, production coordination and on-site guidance, so your survey can be checked against the unit schedule before manufacture.
If you are putting a kitchen or apartment package together and want elevations checked before the order is released, send us the survey and finish selection for the Aluminum Frame with Solid Panel run and we will confirm the unit schedule against it.