In a villa or resort project the swim spa usually arrives as a factory-assembled, pre-tested unit and only then connects to power, drainage and paving on site. That is why a buying checklist for the Outdoor Swim Spa WS-S04B needs to cover more than the shell: it has to close out equipment, services and site readiness before production starts. Below is the checklist we work through with project buyers on this model.

1. Confirm the footprint against the prepared slab

The catalog dimensions for WS-S04B are 3900 x 2200 x 1450 mm. Treat those numbers as the starting point for setting-out, not as the final clearance. Before you order, confirm on drawings:

  • The clear rectangular pad, plus working space on at least one long side for pump and control access.
  • Whether the unit is fully recessed, partially recessed or sitting above finished floor level — this changes the retaining structure and the step arrangement.
  • Rim height relative to the surrounding deck, paving levels and any pool coping detail.
  • Route for removal or replacement later, including gate widths and crane or forklift access if the spa is delivered into an enclosed courtyard.

2. Verify the equipment list line by line

Specification sheets in a catalogue are usually written at model level, while the configuration you buy is fixed in the order confirmation. For WS-S04B the site lists the following as shown features and counts; each line should be confirmed as included, optional or substituted:

ItemShown on the product pageWhat to confirm in writing
Control system1 setController type, display location, whether it is wired indoors or at the unit
Water pumps3 pcsDuty of each pump and which jet circuit it serves
Filter pump1 pcFiltration cycle, run-time control, filter element size and spare availability
Jets31 pcs total; 6 water columnsJet layout drawing, seat and lounger positions each jet serves
Lighting2 pcs LED lights; 28 small LED lightsColour options, controller, fitting access for servicing
Total power10.35 kWSupply voltage and phase, circuit size, isolation location
Water treatmentOzone shownWhether UV sterilisation is added, and dosing arrangements
Swim training systemNot listed for this modelIf you want a swim current, ask explicitly whether it can be added to this shell

The product page also notes that availability and compatibility of options vary by model. Anything not written into the confirmed specification should be treated as not included.

3. Decide the options before production, not after

Catalogue-listed extras for this range include control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps. Two of these drive the whole running cost profile:

  • Heat pump. Determines whether the spa is used year-round or only in warm months, and how the electrical board is sized.
  • Insulation. Matters most for exposed terraces and rooftop positions with wind exposure; it also affects where plant can be located.

Steps and access detail should be resolved together with the paving design, because retro-fitting steps usually means re-laying the surrounding deck.

4. Fix the electrical and drainage scope on site

The spa itself arrives wired; what fails most often in handover is the interface work. Assign these clearly between the pool supplier, the main contractor and the services engineer:

  • Dedicated supply with correct phase and protection, plus local isolation within sight of the plant.
  • Plant room or cabinet location, with drainage for filter backwash and overflow.
  • Structural loading for a filled shell on a suspended slab or terrace — this needs engineer sign-off before the spa is ordered.
  • Control cabling routes agreed before paving is laid.

5. Match the spa to the rest of the outdoor package

A swim spa is rarely bought alone. In villa and resort work it sits inside a wider poolside scheme — loungers, dining sets, pergolas and screens — and finishes, timber tones and hardware are easier to keep consistent when everything is specified from one supplier. You can review the wider range under Swimming Pools and Swim Spas, and coordinate it with Outdoor Furniture for Villas and Resorts. If the site geometry is irregular, our Customizable Shape Outdoor Spa covers square, round, oval and curved shells instead of a fixed catalogue model.

6. Close out delivery, installation and after-sales terms

Before the order is signed, get written confirmation of:

  • Freight mode, packaging and container loading plan, and who handles customs clearance at destination.
  • Delivery window and site readiness date, so the shell does not arrive before the slab is cured.
  • Scope of on-site installation and inspection, and how snags are recorded at handover.
  • Warranty terms, spare-parts availability for pumps, jets, lights and controllers, and who supplies them after year one.

SANTERSON handles this as one package from design coordination through production, logistics and door-to-door delivery, and installation and after-sales support, so the swim spa does not become a separate procurement line with its own gaps.

Ready to price your configuration?

Send us the drawings, the equipment list you want confirmed and the site's electrical details, and we will quote WS-S04B as a complete, buildable specification rather than a catalogue sheet. Contact SANTERSON to start the specification review.