A stacked laundry unit looks simple on a drawing: washer below or beside, dryer above, a cabinet enclosure around them. The problems appear later, when the appliance schedule arrives after the cabinetry has been produced and the enclosure no longer fits the machines actually purchased. This article covers what to count and what to coordinate so stacked laundry units arrive ready to install.

Start with the unit count, not the room plan

Quantity planning for stacked laundry units is driven by three inputs that usually reach the buyer at different times: the number of dwellings or rooms in the project, the appliance schedule, and the wall and floor finishes. Take them in that order.

  • Dwellings and rooms. Count every location where laundry is provided — one unit per dwelling in most villa and apartment work, plus any shared or staff laundry in hospitality and multi-unit projects.
  • Appliance schedule. Record the make, model and installation dimensions of each washer and dryer before you order any enclosure. Stacked configurations depend on the specific pair, so an unconfirmed schedule stops the joinery enquiry.
  • Finishes. Wall tiling, skirting, floor levels and door openings change the finished opening you need to allow. Note whether dimensions are required in structural or finished state.

Our Laundry Integration pieces, including WasherDryer Cabinets, are made to measure for each project, so the enclosure is built around the appliances and openings you confirm — not the other way round.

What to include in the quantity list

A bill of quantities that names only "laundry cabinet, 1 no." will come back with a price you cannot compare. Split each location into line items so substitutions are visible:

Line itemWhat to record per unit
Stacked enclosure / tall cabinetFinished width, height and depth; whether the unit is recessed or surface mounted; door or panel type.
Appliance housingAppliance make, model and dimensions; stacking order; access to rear services.
Worktop or folding lidPresence, material, size, and whether it must clear the open appliance door.
Storage additionsShelves, Pull Out Laundry Hampers, ironing or hanging provision.
Finishes and hardwareMaterial, colour or veneer, handles or handleless profile, hinges and runners.
Services accessTaps, waste, power points and isolation valves, with their positions on the drawing.

Where a floor plan repeats, list the quantity per typical floor and confirm how many identical floors there are. Repeat locations are exactly where an unrecorded variation — a mirrored layout or a different appliance model in a duplex wing — turns into a batch of units that do not fit.

Coordinating the laundry zone with adjacent products

Laundry zones rarely stand alone. In villas and apartments they sit next to bathrooms, kitchens or utility corridors, so the finishes and fixtures around them should be specified in the same pass.

  • Bathrooms sharing a wall. Basins, toilets and showers on the partition that carries the laundry enclosure affect where services can run. Group these items with the Compact Laundry Solutions enquiry so one drawing governs both sides.
  • Kitchen and utility cabinetry. Matching material, colour and door profile across kitchen and laundry keeps the joinery consistent. Specify finishes once and reference them on both schedules.
  • Storage that has nowhere else to go. Cleaning products, linen and bulk supplies need a home. Laundry & Storage Combo and Multi Function Tall Cabinets absorb that load in the same run of joinery.
  • Flooring and doors. Threshold details, door swing clearance and floor levels decide whether a stacked unit can be serviced with its door open.

One coordination point matters more than the rest: a single person should hold the appliance schedule, the joinery drawings and the services drawing. When those three sit with different parties, the mismatch is discovered on site, when only replacement can fix it.

Ordering sequence for a project batch

Move through the steps in this order and each one feeds the next; out of sequence, production starts against information that is still open.

  1. Fix the appliance models and issue their installation dimensions to the joinery team in writing.
  2. Confirm finished dimensions for every location, including floor and wall build-up, and mark any mirrored or varied layout.
  3. select material and finish across the whole joinery package, so laundry, kitchen and bathroom units match.
  4. Approve shop drawings against the appliance schedule — check access to taps, waste and power before sign-off.
  5. Release production per location or per floor, so a variation on one level does not hold up the rest.
  6. Group the shipment with related fixtures where practical, and label crates by room so installation follows the drawing sequence.

Confirm dimensions and selected specifications for each project before production. Our product pages state made-to-measure sizing, material and finish options, and layout tailored to the project; they do not promise fixed sizes or fixed lead times.

Common quantity errors and how to avoid them

  • Ordering to structural dimensions. Tiles, waterproofing and plasterboard consume centimetres. Always state whether a dimension is structural or finished.
  • Assuming one appliance model across the project. Substitutions happen at procurement stage. Ask for an enclosure that can be re-sized against a revised schedule before production starts.
  • Forgetting service access. Hoses, filters and rear clearances need working space; a tight enclosure blocks maintenance and voids appliance warranties.
  • No spare allowance. Repeat projects should carry a small number of spare panels or doors for future replacement — agree the percentage with the client rather than assuming one.
  • Ventilation left to site. Dryer venting and any required air circulation must appear on the joinery drawing, not be resolved during installation.

Getting an accurate quotation

Send these four items with your enquiry

A room-by-room schedule of locations with quantities; the appliance list with installation dimensions; the finish specification for the joinery package; and the current architectural drawings showing levels and openings. With those, we can price stacked laundry units as part of a wider fit-out that covers bathroom fixtures, kitchen cabinetry, doors and flooring from one supplier, with production coordination and door-to-door delivery arranged around your site programme.

What we confirm back

Made-to-measure proposals for each location, finish options matched to the rest of the joinery package, and a breakdown that shows which line items belong to which floor or dwelling, so substitutions are visible before production rather than after.