Integrated TV panels sit at an awkward point in a hospitality schedule. They are joinery, they are wall finish, and they carry electrical work — yet on most project programmes they are treated as a late decorative decision. That is exactly why the packages arrive short of openings, the screen size changes after the panel is cut, or the wall finishes do not match the cabinetry elsewhere in the same room. This guide walks through how to procure Santerson Integrated TV Panels for a hotel, serviced apartment or resort project: what information the manufacturer needs from you, which decisions have to be locked before drawings are issued, and how the wall integrates with the rest of the fit-out so one supplier carries the whole scope.
What an integrated TV panel actually is in a hospitality fit-out
An integrated TV panel is a factory-built wall section in which the screen, its mounting structure, the storage below or beside it and the surrounding finish are designed as one unit rather than assembled on site from separate trades. The Integrated TV Panels range sits inside our Media & TV Walls collection, alongside Full Height Media Walls, Backlit Feature Walls and Sliding Panel TV Systems. Finish, layout and dimensions are specified per project, so the same elevation can be reproduced across a guest-room tower with different screen sizes or different storage arrangements in each room type.
The procurement value is consolidation. In a typical guest room the media wall touches the joinery package, the painting or wall-covering package, the electrical contractor, and AV or network cabling. Handled as four separate scopes it becomes four sets of drawings, four variations and four chances for somebody to be wrong. Handled as one manufactured unit, the recess, the cable route, the mounting substrate and the visible finish are resolved in the factory, and the site crew fixes a completed element to a prepared wall.
Where these panels belong in a hospitality project
Integrated TV walls earn their keep wherever a screen has to look like part of the architecture rather than an object hung on it:
- Guest rooms and suites. A panel sized to the bed wall, with the screen recessed or flush-mounted and concealed storage for the minibar, safe and luggage rack beneath.
- Serviced apartments and build-to-rent units. Media walls double as living-room storage, so the layout has to serve daily use, not just viewing.
- Lounge, lobby and club levels. Feature-scale elevations, sometimes with backlit panels or sliding screens that hide the display when the space is used for events.
- Villas and private-residence wings of a resort. The same detailing language as the wardrobes and cabinetry, so the media wall does not read as imported furniture.
The decisions that must be locked before drawings are issued
Most cost overruns on media walls trace back to a small number of items being decided too late. Work through them in this order.
1. Screen size, mounting method and viewing height
Fix the screen diagonal, the brand or at least the mounting pattern, and whether the screen sits flush inside a rebate or on an articulated arm that pulls out from the wall. Flush mounting gives the cleanest elevation but demands precise recess dimensions and adequate clearance behind the panel for the bracket and cable bundle. An arm gives serviceability and angle adjustment but needs a deeper carcass and a stronger substrate.
2. Cable, power and network routing
Confirm what has to reach the screen: mains, HDMI or fibre, network point, aerial if the property still distributes broadcast signals, plus low-voltage feeds for any integrated lighting. State whether those runs are concealed inside the panel, in the wall behind it, or in the floor. Where backlit or accent lighting is specified, agree the driver location — a driver buried behind a sealed panel is a maintenance problem you will meet again on site.
3. Storage layout and room-service practicalities
Decide what the unit actually stores: glassware, linen, a minibar fridge, luggage, a working desk surface. Doors, drawers or open niches each change the carcass build, and housekeeping needs to open and close them hundreds of times over the asset life.
4. Finish continuity with the rest of the joinery
Specify the veneer, lacquer, laminate, glass or stone panel against the sample already approved for the wardrobes and vanity units. Where the media wall is part of a wider wall panelling and cladding elevation, request that the same batch and grain direction be used so joints across the room read as one surface.
5. Fixing method and wall substrate
Tell us what the finished wall is — masonry, stud partition with lining, timber battening or an existing framed surface — and the room's clear height and floor level. Full-height panels need a prepared substrate and a defined set-out line; the manufacturer cannot design the support detail if the wall build-up is still open.
What to send your supplier, and what to expect back
A single enquiry covering the items below usually converts into a firm quotation in one round instead of three. As a hospitality furniture and fit-out supplier, we work from project drawings rather than catalogue selections.
| What you provide | Why it matters |
|---|---|
| Room type list with quantities per floor or block | Sets the production batch and lets identical elevations be repeated across a tower |
| Elevation drawings, scaled, with clear heights and finished floor levels | Drives panel height, set-out and fixing detail |
| Screen schedule: diagonal, model or mounting pattern, flush or articulating | Determines recess size, substrate strength and clearance behind the panel |
| Services schedule for each screen location: power, data, AV, lighting drivers | Fixes concealed routing and keeps drivers accessible for maintenance |
| Finish references already approved for joinery and wall finishes | Prevents visible mismatch between media wall, wardrobes and skirting |
| Wall build-up and fixing substrate at each location | Determines the support frame and installation method |
| Delivery destination, access constraints and installation window | Shapes packaging, container loading and the site programme |
In return you should receive shop drawings for sign-off before production starts, a specification of materials and hardware, confirmation of what is pre-assembled versus assembled on site, and an installation sequence that matches your trade order. Anything left ambiguous on the drawing becomes a variation on site.
Packaging, freight and the site sequence
Media walls are large, flat and unforgiving of rough handling, so packaging and loading plans matter more than for loose furniture. We handle freight forwarding by sea, air and rail with the associated customs paperwork, packaging and container loading planned around the panel sizes rather than the other way round — see logistics and door-to-door delivery. Confirm import terms, duties and insurance for your destination case by case; we do not quote a transit time as a guarantee.
On site, keep the sequence honest: substrate prepared and signed off, first-fix services complete and tested, wall finishes around the opening resolved, then panels installed last so they are not damaged by later trades. Where your programme allows it, install one sample room end to end — screen mounted, cables dressed, doors aligned — and have the client or design team sign that room before the remaining units ship.
Procurement checklist for media walls
- Screen model, size and mounting method confirmed in writing before drawings are issued
- Every cable type and its route specified, with lighting drivers left accessible
- Storage layout agreed with the operator, not just the designer
- Finish matched to approved joinery samples, with batch and grain direction noted
- Wall substrate, clear height and finished floor level supplied for each location
- Quantities grouped by room type so identical elevations repeat correctly
- Sample room built and signed off before the production batch is released
- Installation window agreed with the site programme; panels installed after wet trades
- Spare hardware and a documented fixing detail retained for future maintenance
A note on scope. Media walls are configurable systems, not fixed catalogue items. Dimensions, materials, hardware, glass and electrical options are confirmed per project, and we will ask for the technical requirements at each screen location rather than assume them from a reference image.
Bringing media walls into one procurement package
The clearest saving on a hospitality programme is not the unit price of the panel but the number of suppliers you have to coordinate. When media walls, wardrobes, vanity units, cabinetry and wall panelling come from one manufacturer under a single design-coordination process, finishes match by default, drawings are issued once, and one party answers for the whole joinery scope. That is how we work on villa, hotel and office projects: design consultation and space planning, material selection and product specification, manufacturing with quality control, project management and site coordination, then installation and handover — turnkey project delivery rather than a crate of unrelated boxes.
If you have a guest-room or lounge elevation that needs a screen resolved into the architecture, send the drawings and services schedule and we will return shop drawings for review.