A swim spa in a hotel, resort or serviced-apartment project is not a single line item on a purchase order. It is a piece of plant equipment with structural, electrical, waterproofing and maintenance consequences that reach well past the wellness area. If your hospitality project is specifying Outdoor Swim Spa WS-115AⅢ-U, this guide walks through the procurement sequence in the order a project team actually has to make decisions, and flags the items that most often slip when a spa is treated as furniture rather than equipment.
Why a swim spa belongs in the MEP conversation, not the FF&E schedule
Loose furniture can be swapped late in a programme. A swim spa cannot. The shell dimensions set the footprint of the slab or plinth, the wet zone and the access route for delivery. The pump and jet package sets the electrical load and the distribution board it lands on. The filtration and sanitation choices determine pipework, plant-room space and the daily maintenance routine your engineering team inherits at handover.
For that reason we recommend bringing the swim spa into the mechanical, electrical and plumbing coordination package at concept design, alongside pool plant and bathroom fixtures. Projects that leave it to the FF&E stage usually end up either re-routing services or accepting a smaller unit than the amenity brief asked for.
Reading the WS-115AⅢ-U specification as a project team
The catalogue entry for this model records an external envelope of 3880 × 2200 × 1250 mm, one control system, four water pumps, one filter pump, a total of 23 jets, one LED light and a total power figure of 11.85 kW, with water jets, LED lighting and ozone shown as the featured equipment. Treat these as catalogue figures for the standard configuration, and confirm the exact numbers on your signed specification before any service design is frozen.
| Specification item | Catalogue value | What your team must confirm |
|---|---|---|
| External dimensions | 3880 × 2200 × 1250 mm | Clearance for access, maintenance hatches and drainage falls around the shell |
| Total power | 11.85 kW | Whether a heat pump is added, which changes the connected load materially |
| Water pumps / jets | 4 water pumps, 23 jets | Jet layout and seating positions against your wellness concept |
| Filtration | 1 filter pump | Whether sand filtration is added and where the plant sits |
| Sanitation | Ozone shown | Local requirements for water treatment, dosing and testing regime |
| Swim training system | Not listed for this model | If lap swimming is part of the amenity brief, confirm the option before ordering |
That last row matters. The WS-115A family includes configurations that carry a swim training system and configurations that do not, and pump counts and jet totals differ between them. If your amenity brief promises lap swimming for fitness-focused guests, the difference between a hydrotherapy-only unit and a counter-current swimming unit is a design decision, not an accessory you can add after installation.
Options that change scope, not just price
The range lists control systems, UV sterilisation, additional water pumps, heat pumps, sand filtration, insulation and steps as options. In a hospitality setting, four of them carry scope consequences:
- Heat pump. This is the single largest change to connected load and to operating cost. A heated spa used by guests year-round needs an electrical supply sized for it from day one; retrofitting a supply in an occupied building is disruptive and expensive.
- Insulation. Insulation around the shell and pipework determines how much energy the heat pump works against overnight, which matters when the unit sits outdoors in a cooler climate or runs on metered tariffs.
- Sand filtration. Adding filtration moves pipework and plant out of the spa itself. It needs space, drainage and a maintenance access that guests never cross.
- UV sterilisation and ozone. Sanitation is a compliance-sensitive area for commercial water features. Confirm what the unit supplies, what your local authority expects on top, and how dosing and testing will be logged during operation.
Site conditions to resolve before the shell arrives
- Structure. A water-filled shell of this size is a heavy point load. Confirm the slab, plinth or deck loading with your structural engineer, including the drained weight for maintenance and the saturated zone around it.
- Delivery route. Measure the path from the delivery vehicle to the final position: gate widths, turning radii, overhead services, and whether a crane or lifting plan is needed for a terrace or rooftop location.
- Drainage and overflow. Plan drainage falls, an overflow route and an emergency drain before the shell is set. This is far cheaper at groundworks stage than after tiling.
- Electrical segregation. The control system, pumps and any heat pump need a dedicated supply with appropriate protection. Keep the distribution board inside the required distance from the wet zone.
- Acoustics. Pumps and jets run on a schedule guests will complain about if the unit sits under guest windows. Check separation distances at design stage, not at handover.
Building a realistic procurement timeline
A swim spa should be ordered against a signed specification, and that specification depends on decisions made by several different consultants. A practical sequence looks like this:
- Concept. Amenity brief defines whether the unit is hydrotherapy, lap swimming or both; approximate footprint reserved in the layout.
- Design development. Model and configuration selected; electrical load, plant location and drainage fixed; structural loading confirmed.
- Specification sign-off. Equipment list, options and finishes agreed with the manufacturer, with a written confirmation of included items.
- Order and production. Purchase order raised against the signed specification; production slot booked so the shell lands after groundworks are ready, not before.
- Delivery and setting. Access route verified, unit set on prepared base, services connected by qualified trades.
- Commissioning and handover. Jets, control system, lighting and sanitation tested; maintenance routine, spares and consumables handed to the operations team with a written schedule.
The most common failure is ordering the shell before the base, drainage and supply are ready, which leaves a large piece of equipment sitting on site while civil works catch up. Sequence the order against your civil programme rather than against your furniture programme.
What to require in a quotation
When you compare offers for this or any comparable unit, ask each supplier to state, in writing: the exact model and configuration; a complete included-equipment list against the catalogue options; confirmed dimensions and connection points; the electrical supply requirement including any heat pump; warranty scope and what voids it; the delivery terms and who handles unloading and setting; spare-parts availability for pumps, jets and controls; and the maintenance consumables the unit needs in its first two years of commercial use. A quotation that only lists a model number and a price is not comparable with one that answers those questions.
Sourcing it as part of a wider project package
Most hospitality projects do not buy a swim spa on its own. It arrives alongside outdoor lounge furniture, poolside loungers, bathroom ceramics, lighting and finishes for the same wellness area. Coordinating those items with one supplier reduces interface risk: one set of drawings to reconcile, one freight consolidation, one installation window and one point of accountability for snags. SANTERSON works as a one-stop furniture and building materials manufacturer for villa, hospitality and office projects, covering design consultation, custom and OEM production, door-to-door logistics and installation support across the fit-out package.
If the wellness area also needs adjacent products from the same range, our swim spa and swimming pool collection covers alternative dimensions and configurations, which is useful when a layout revision changes the space available for the shell.
Checklist before you sign the purchase order
- Amenity brief confirmed: hydrotherapy, swimming or both, and the guest profile it serves
- Configuration signed off with a written included-equipment list, including whether a swim training system is supplied
- Electrical supply sized for the full configuration including heat pump, with segregation from the wet zone
- Structural loading, drainage falls and overflow route approved by the relevant engineers
- Delivery route measured, with lifting plan if the final position is elevated
- Water treatment responsibilities defined: what the unit supplies versus what local requirements add
- Maintenance schedule, spares and consumables agreed and handed to operations at commissioning
Send us your wellness area drawings, the amenity brief and your target configuration, and we will confirm equipment scope, supply requirement and lead time for a project-specific quotation.