A wall cabinet that measures correctly on a drawing can still fail on site. Load-bearing fixing points, the sequence of wet trades, container handling and the availability of an installing crew all sit outside the shop drawing. The following sequence covers how project teams align those items before production starts, so wall mounted cabinets arrive when the wall is ready for them and go up without rework.

Why Wall Mounted Cabinets Expose Scheduling Gaps Early

Unlike a freestanding unit, a wall cabinet depends entirely on the structure behind it. Its weight, once loaded with glassware, linen or bathroom supplies, transfers to the substrate through the fixings. That dependency means three separate trades have to be finished before installation can begin: the framing or masonry that carries the load, the first-fix plumbing and electrics routed behind the cabinet zone, and the finishes that determine the revealed dimension of the wall face.

Because those trades sit at different points in the programme, a cabinet ordered to a nominal dimension can arrive to find the finished wall line has moved. On imported consignments the gap becomes more expensive: the unit is on site, the substrate is not ready, and storage, insurance and crew standby costs accumulate while the correction is arranged.

Step 1: Lock the Wall Build Before the Cabinet Dimensions

Fix the wall construction type in writing before any cabinet dimension is signed off. Record whether the substrate is masonry, stud framing with noggin blocking, or an existing plastered surface, and confirm who is responsible for adding reinforcement where a heavy upper unit hangs.

  • Mark the finished wall face on the drawing, not the structural face, so tolerances and finishes are already included in the dimension.
  • Note every service that runs through the cabinet zone: water feeds, waste outlets, switch plates, socket boxes and extractor ducting.
  • Record obstructions such as beams, skirting returns, window reveals and door heads that change a run's effective length.
  • Confirm which units sit on a floor-supported base and which hang clear, because the two need different support details.

Practical rule: no made-to-measure wall unit should be released for production from an as-built survey that has not been signed by the site lead. The signature is what stops a revised wall line reaching the factory after cutting has started.

Step 2: Specify Made-to-Measure Units Against the As-Built Condition

Project-specified cabinetry gives you the latitude to match a run to an awkward wall, but only if the specification is issued late enough to reflect reality. Santerson Wall Mounted Cabinets are made to measure with material and finish options and a layout tailored to the space, which means the dimension sheet is part of the order rather than an adjustment made after delivery.

The same logic applies across related built-in items. A floating vanity shares the wall zone with basin waste and tall units, so its hanging height should be set against the finished floor level rather than the slab. Where a display run is involved, wall mounted display cabinets need their lighting and shelf loads resolved at specification stage, because concealed wiring has to be chased before the finishes go on.

What the dimension sheet should carry

  • Finished floor to finished ceiling levels for each wall, with the tolerance band stated.
  • The hanging line and the clear height beneath each unit, agreed with the designer.
  • Aperture sizes where a unit returns into a reveal or wraps a corner.
  • Finish references for doors, carcass and internal surfaces, matched to the sample already approved.
  • The substrate note for each fixing line, so the installer arrives with compatible fixings.

Step 3: Sequence Production Against Site Readiness

Production lead time and site readiness have to be plotted on one programme, not two. A common error is releasing the joinery order as soon as the design is approved, then discovering that tiling, waterproofing or floor screed has slipped by several weeks.

MilestoneSite condition requiredCoordination action
Survey releasedWall build and first fix complete on the relevant zoneSite lead signs off levels and service routes
Production startApproved finish samples on fileConfirm finish references in writing with the supplier
Packing and loadingDelivery address and access confirmedAgree crate labelling by room and elevation reference
Arrival at port or siteClear storage area, dry and coveredBook handling equipment for the crate weights
Installation windowWet trades cured, finishes protectedCrew booked with fixings matched to each substrate

Step 4: Plan Handling and Storage Before the Container Lands

Wall units are long, flat and easily damaged at the corners, which makes them poor candidates for double handling. Confirm before shipment that the delivery point can take the crate size through lifts, stairwells or narrow doors, and identify a dry storage location where crates can stand upright and be reached without moving other trades' materials.

  • Ask for each crate to carry the room name and elevation reference used on the drawings, so installers do not open everything at once.
  • List heavy upper units separately in the packing list so two people are assigned to them.
  • Inspect door and carcass faces against damage at unload, while the carrier is still present.
  • Keep spare panels and hardware in original packaging until the run is complete.

SANTERSON's stated logistics scope covers freight forwarding by sea, air and rail, customs documentation, packaging and container loading, shipment tracking and door-to-door delivery. Those services matter most at this stage because they determine who to query when a consignment is delayed: the forwarder named on the paperwork, not the factory floor. Import terms, duties and transit arrangements should still be settled per project, since each destination applies its own requirements.

Step 5: Set the Installation Window and Its Prerequisites

Fix the installation date only when these conditions are met. If any one of them is open, the crew will arrive and leave a partial run on site.

Site readiness checklist

  • Tiling, waterproofing and paint or wallpaper behind and around the unit are complete and cured.
  • Finished floor levels are laid and protected where a unit hangs above them.
  • Plumbing and electrical outlets are in their final positions and tested.
  • The substrate type at each fixing line is confirmed, including any blocking added late.
  • Adjacent units and worktops are set, so the run can be scribed to them.
  • Fixings suitable for each substrate are on site in the correct lengths.

Sequencing inside a bathroom or kitchen zone

Where a wall cabinet shares a wall with a vanity, mirror cabinet or tall unit, install from the structural constraint outward: units that must align to a waste outlet or a flue go first, then free-standing runs fill the remaining length. Hanging units should be set before worktops are templated where the top of the carcass affects the template line. Doors and drawers are adjusted last, after the carcass has been loaded once to settle the fixings.

Step 6: Hand Over With Snag Items Assigned

Close out the installation with a joint inspection against the dimension sheet. Check that each unit is level, that doors are aligned, and that no fixing has been driven into a service run.

  • Record door alignment adjustments and any scribed fillers on one snag list, with an owner and a date for each item.
  • Photograph the finished run before the site is handed to the client or operator.
  • Keep the specification sheet with the approved finish references; it is what you need if a replacement panel is ordered later.
  • Note spare hardware left over, and store it with the project documentation rather than on site.

SANTERSON lists installation support alongside after-sales service, inspection of snags, spare parts and maintenance as part of its one-stop scope for villa, hospitality and office projects. For a specific programme, confirm what on-site attendance is available at the destination and which items fall under warranty, since those arrangements vary by project.

Common Failure Points and What Prevents Them

  • The wall line moved after the survey. Only release dimensions from a signed as-built, and re-check levels before production if any wet trade has run since the survey.
  • Cabinet fixed to the wrong substrate. Record the substrate at each fixing line on the drawing; installers bring fixings accordingly.
  • Unit arrives during a wet-trade window. Plot arrival against the finish programme, not the production date, and hold shipment if the zone is not ready.
  • Corners damaged in handling. Confirm access routes and crate sizes before loading, and inspect at unload.
  • Doors out of alignment at handover. Leave adjustment time in the installation window rather than treating hanging as a single-day task.

Frequently Asked Questions

How far before the installation date should wall cabinets be ordered?

Order against a signed as-built survey rather than a fixed number of weeks. Work backwards from your installation window: production, then freight and clearance, then on-site storage, then the wet-trade completion that must precede hanging.

Should wall cabinets be installed before or after flooring?

Hanging units go in after the finished floor level is set, because their clear height is measured from that surface. Floor-supported runs can follow once adjacent finishes are protected.

What documentation should travel with a made-to-measure order?

The dimension sheet with finished levels and tolerances, the approved finish references, the substrate note for each fixing line, and crate labelling that matches room and elevation references on the drawings.

Bringing Delivery and Installation Into One Plan

Wall cabinets fail on site for reasons that are visible on paper months in advance: an unsigned survey, an unplanned substrate change, a container landing during tiling, or a crew booked before the wet trades cure. Treating production, freight and installation as one sequence with named prerequisites keeps each handover explicit. As part of SANTERSON furniture and building materials supply for villa, hospitality and office projects, wall cabinets are specified to the space, packed to the site's access conditions and installed against a readiness checklist agreed with the project team.