On most villa and hospitality jobs the doors are the item everyone specifies last. Wall finishes, joinery, wardrobes and tiling all move through the drawing set with detailed schedules, while interior doors arrive as a late line item on a separate purchase order. That is exactly where Integrated Door & Paneling changes the conversation: it stops being a door purchase and becomes part of the wall package you are already procuring.
This article looks at how concealed doors that sit inside a panelled wall system can be bundled into one coordinated fit-out package: what has to be decided before production starts, who signs off on what, and how a single supplier covering cabinetry, panelling, doors and matching finishes reduces the coordination load on site.
Why Doors And Wall Panels Are Usually Bought Separately
A conventional bill of quantities treats an internal door as a standard component: pick a leaf size, pick a finish from a sample card, place the order. It works well for a painted hollow-core leaf in a standard reveal. It stops working when the design intent is a seamless wall — timber-veneer panelling running continuously across a bedroom or corridor with the doorway almost invisible.
In that situation three separate trades each control one piece of a single visual result:
- The joinery or paneling supplier sets the substrate, joint pattern and finish.
- The door supplier provides the leaf, frame and hardware.
- The site builder builds the opening, sets the frame level and lines, then makes good around it.
Each party is responsible for their own element and nobody owns the junction. The visible outcome — a flush reveal, matched grain, consistent sheen across leaf and wall — depends on all three interpreting the same detail the same way. When they do not, the correction happens on site, at the worst possible moment in the programme.
What Integrated Door & Paneling Actually Means
Integrated door and paneling means the concealed leaf and the surrounding wall cladding are designed, manufactured and delivered as one assembly. The panel layout is drawn around the opening rather than the opening being cut into a finished panel run. Finish, substrate and joint detailing carry through from wall to leaf.
SANTERSON's version sits in the Custom Partitions & Paneling collection. The catalogue record for Integrated Door & Paneling describes made-to-measure sizing, material and finish options, and a layout tailored to the project — which is the practical definition of the product: nothing about it is standard, everything about it is specified per opening.
Related items in the same family are usually specified together with it, and they share that made-to-measure approach:
- Wall Panel Systems — the continuous cladding the door disappears into.
- Wood Panel Partitions — timber-faced partitioning where a doorway is set into a new wall build-up.
- Custom Niche Paneling — recessed display niches that must align with the same joint grid as the door leaf.
- Handleless Concealed Doors and Decorative Concealed Doors — concealed-leaf options for projects where the requirement reads as a door first rather than a wall.
Which of these you specify depends on whether the design driver is the wall appearance or the door operation. Both routes need the same early decisions, described below.
The Decisions That Have To Precede Production
A coordinated package only holds together if the following are settled before anything goes into manufacturing. Each one is cheap to change on paper and expensive to change on site.
| Decision | What needs confirming | Typical failure if left late |
|---|---|---|
| Opening set-out | Leaf size, hinge side, opening direction and reveal position for every opening, taken from coordinated drawings rather than site measurement after the panels are made. | Panels arrive cut to a grid that no longer matches the built opening. |
| Wall build-up and frame type | Which concealed frame and substrate the leaf sits in, and how that build-up relates to the finished floor level and ceiling line. | Frame is set out of plumb or at the wrong height; the leaf rubs once flooring is laid. |
| Finish and grain direction | Species or decorative surface, sheen level, and whether grain runs vertically or horizontally across the whole wall including the leaf. | Leaf matches in colour but not in grain or sheen under raking light. |
| Joint grid | Where panel joints fall relative to the door edge, and how niches and reveals align to that same grid. | An off-grid joint cuts visually through the doorway. |
| Hardware interface | Handleless or concealed hardware, swing clearance, and what the leaf butts against at floor level. | Threshold or skirting blocks the swing after installation. |
The reason these belong in one package is simple: once the panel grid and the door opening are drawn by different people, no single drawing controls the junction. Bundling does not remove the decisions — it puts them under one set of shop drawings.
How A Single-Supplier Package Reduces Coordination Load
SANTERSON is a China-based furniture and building materials manufacturer positioned as a one-stop supplier for project customers, with services spanning design coordination, custom and OEM production, door-to-door logistics, installation support and after-sales. For fit-out packages that matters because the same factory can produce the joinery, the panelling and the integrated leaf against one set of dimensions.
In practice a bundled scope for the same rooms typically covers:
- Flush Interior Doors and integrated door and paneling for bedrooms, corridors and bathrooms.
- Wardrobes and built-in storage in the same decorative surface, so bedroom joinery and wall cladding are ordered together.
- Kitchen cabinetry, vanities and tall storage where the finish continues into adjacent panelling.
- Wall finishes, decorative screens and acoustic or sliding panel systems for the shared areas of the same project.
The practical benefit is not fewer suppliers for its own sake. It is that one shop-drawing set governs openings, panel grids and finishes; one production run keeps decorative surfaces from the same batch; and one packing list and shipment schedule delivers the package to site together rather than in three separate consignments arriving on different weeks.
Sequencing The Package Into The Programme
Integrated doors and panelling are long-lead, made-to-measure items. They sit in the middle of the programme, not at the end of it. A workable sequence looks like this:
1. Design freeze on openings
Every opening that will be concealed must be fixed on coordinated drawings before anything is released for manufacture. At this stage also confirm which doors are integrated into panelling and which are ordinary flush leaves, because they carry different site requirements.
2. Shop drawings and sign-off
Panel grids, reveal details, frame build-ups and finish samples are issued for approval. This is the point where the client or designer signs off on grain direction and sheen — not at delivery.
3. Production and pre-shipment check
Once drawings are signed, production starts. Confirm dimensions and selected specifications for each project against the approved drawings before goods ship; the catalogue record for these products states that explicitly, and it is worth treating as a required step rather than a formality.
4. Site preparation before delivery
Openings must be built to the approved setting-out, finished floor levels established, and services inside the wall build-up completed. Made-to-measure panelling has very little tolerance for an opening that shifted on site.
5. Installation and snagging
Frames are set first, panels follow, and the leaf is hung last so it can be adjusted to the finished wall. Snag list covers swing, reveal consistency, and finish continuity under the room's actual lighting.
A Practical Checklist For Specifiers And Buyers
- Issue an opening schedule listing every concealed and integrated door with size, hinge side and swing direction.
- Name the finish once, across doors, panelling and joinery, rather than describing it separately in three scopes.
- Require a joint grid drawing that shows panel joints relative to each door reveal.
- Confirm substrate, frame type and threshold detail before release for manufacture.
- Order doors, panels and matching joinery on one purchase order with one delivery window.
- Verify finished floor levels and opening set-out before the panels ship.
- Keep one named contact responsible for both door and paneling submittals.
If your project also needs the surrounding scope — cabinetry, wardrobes, vanities, wall finishes — specifying them as one turnkey fit-out package keeps those submittals under a single coordination process instead of several parallel ones.
Frequently Asked Questions
Can integrated doors be supplied for existing buildings as well as new builds?
They can, provided the opening and wall build-up are rebuilt to the approved setting-out. In renovation work the wall lining is usually reconstructed anyway, which is where concealed frames integrate cleanly.
Do integrated doors have to be handleless?
No. Concealed and handleless details are the common choice because they preserve the wall surface, but the collection also includes decorative concealed options where a visible hardware detail is acceptable.
What information should a buyer provide with an enquiry?
Coordinated drawings showing each opening, the intended finished floor levels, the required decorative surface, and the panel layout intent. With those four items, shop drawings can be developed without re-opening design decisions later.
Is the door supplied already finished?
The leaf is specified with the same decorative surface as the surrounding panels, which is the reason for ordering them together. The catalogue lists material and finish options rather than one fixed face, so samples should be approved before production release.
Specify doors and wall panelling as one package
Send your opening schedule and drawings, and the team can develop shop drawings for integrated door and paneling alongside the matching joinery, vanities and wall finishes for the same project.