A floating vanity looks simple on a rendering: a wall-hung box, a stone top, a mirror above it. On site it is one of the least forgiving items in a bathroom fit-out, because everything about it has to be resolved before the tiles go on. Wall supports, waste and supply positions, countertop thickness, mirror alignment and door swing all depend on a unit that does not exist yet as a physical sample. If you are specifying the Santerson Floating Vanity for a villa or hotel bathroom, the approval stage is where the expensive mistakes get removed. Below is the checklist our project team asks buyers and consultants to sign off before an order is released.

1. Confirm the wall build before you confirm the unit

A wall-hung vanity carries its own weight plus the countertop, basin and the load of daily use, all cantilevered off one surface. Before drawings are frozen, agree with the main contractor what the substrate actually is: framed stud partition with reinforcing ply or steel backing, solid masonry, or a cavity wall with a proprietary frame. The fixing detail and the required timber or steel blocking must appear on the wall layout drawing, not be decided by the installer on the day.

  • Finished floor-to-finished-floor height, and where the vanity sits relative to it.
  • Clearance for the door or drawer fronts when fully open, measured against the WC, shower screen and room door.
  • Whether services run inside the wall the unit will be fixed to, and whether they can be relocated before closing up.

2. Lock the made-to-measure dimensions on a coordinated drawing

The Santerson Floating Vanity is supplied to project-specific sizes rather than a fixed catalogue width, and the same applies to the Single Vanity and the wider vanities range. That flexibility is useful, but it moves responsibility onto the drawing set. The dimensioned elevation we work from should show finished wall faces, not structural ones; drawer and door reveals; handle or integrated pull detail; and the exact relationship between the carcass and the countertop edge.

Where a longer run is needed across one wall, tell us whether you want a single wide carcass or two units with a shadow gap. That decision changes the support detail, the stone joint and how the mirror is cut.

3. Match basin, countertop and taps as one assembly

Vanity, top and basin are approved separately in many specification packages and arrive on site as three unrelated purchases. Confirm them together: the tap hole pattern and spout reach relative to the basin bowl, the overflow provision, the countertop material and thickness, and the exposed edge profile. If a seamless look matters, look at the Santerson Integrated Countertop Vanity, where the top and basin are configured as one piece instead of assembled on site.

  • Tapware brand, model and mounting centres, confirmed against the stone drawing.
  • Basin type: undermount, drop-in or integrated.
  • Waste and trap set, and whether it is supplied with the unit or by the plumber.

4. Resolve waste, supply and access before the wall closes

Wall-hung units usually conceal the trap, so the position of the waste outlet has to sit inside the carcass envelope while still falling correctly to the soil stack. Supply outlets need to be reachable after the unit is hung, and isolation valves should not end up behind a fixed panel. Confirm all of this on the services drawing and photograph the open wall before it is boarded or tiled.

Practical rule: if the trap cannot be reached with the drawer baskets removed, change the layout now. Rework after tiling means lifting finished surfaces.

5. Specify the finish and substrate for a wet room

Bathrooms are humid, splashed and cleaned aggressively. Tell us the environment honestly — guest bathroom, master ensuite, hotel room or shared poolside facility — and we will match the board and surface system to it rather than assume one finish suits every project. Confirm the substrate, edge sealing method, hardware finish and the cleaning products the client intends to use, and record all of it on the approval sheet so the same specification survives across phases.

6. Coordinate mirror, lighting and electrics with the vanity elevation

A floating vanity reads badly when the mirror is off-centre to the basin or the light lands on the top of a guest's head rather than their face. Decide the mirror type early: a Santerson LED Mirror Cabinet needs a supply point and a switching position, while a framed mirror with separate Vanity Lighting needs the fitting centred on the basin, not the carcass. Set-out dimensions for both should sit on the same elevation drawing as the vanity.

7. Order against a schedule, not a rendering

For multi-bathroom villas and hotel room types, put every unit in one bathroom schedule: type code, room reference, width, height, depth, carcass finish, countertop material, basin, tapware, mirror, and the wall build it attaches to. Repeat identical configurations across identical room types so production runs as one batch, and keep a single revision-controlled version of that schedule. Most on-site delays we see trace back to two versions of a bathroom schedule circulating at once.

8. Plan packaging, delivery sequence and installation

Countertops and mirrors are the fragile items in the shipment; carcasses are the bulky ones. Confirm how each is crated, the container or consignment sequence, and which units arrive first so wet trades finish before joinery goes in. SANTERSON handles freight, customs paperwork and door-to-door delivery as part of its Turnkey Interior Project Solutions, and installation, snag inspection and after-sales support follow the same package. Agree on-site storage and who signs for each consignment before dispatch.

What to have signed off before you release the order

Item to confirmWho confirms itWhere it appears
Wall substrate and blocking for fixingsMain contractor + our project teamWall layout / setting-out drawing
Made-to-measure width, height, depthBuyer / designer + our project teamDimensioned vanity elevation
Countertop material, thickness, edge profileDesigner + stone supplierStone shop drawing
Basin type, tapware model and hole patternM&E consultant / buyerBathroom schedule
Waste and supply positions, trap accessPlumbing contractorServices drawing + site photo record
Mirror type, lighting position, electrical pointM&E consultantSame elevation as the vanity
Finish system and cleaning regimeClient / operatorApproval sheet, per room type
Packaging, delivery sequence, storage planBuyer + our logistics coordinatorDelivery schedule

Send us the bathroom schedule and the vanity elevation and we will check them against production requirements before anything enters manufacturing — including whether a floating unit is genuinely the right choice for that wall, or whether a floor-standing Santerson Double Vanity or integrated countertop option serves the room better. As a one-stop furniture and building materials supplier, we can also group vanities with basins, toilets, shower systems, mirror cabinets, lighting and cabinetry in one procurement package, which removes most of the coordination burden between separate suppliers.