A set of minimalist black aluminum frame cabinets looks simple on a rendering: thin black profiles, flat panels, clean lines. On site it is one of the least forgiving products to get wrong, because every millimetre of an aluminium carcass is fixed before the container leaves the factory. When the order also has to cross an ocean, the delivery plan matters as much as the design. Below is the sequence we follow on project orders, and the decisions your team needs to lock down at each stage.

Why aluminium frame cabinetry punishes late changes

Timber carcasses can be trimmed on site. Aluminium extrusions cannot. A black minimalist cabinet run is cut, machined and assembled to the dimensions on the approved shop drawing, and the glass, panels and hardware are matched to those same numbers. Once the profiles are cut there is no practical way to shorten a run by 60 mm in another country.

That single fact drives everything else in the delivery plan: measurement method, drawing approval, packaging sequence, container loading order and the installation brief. Treat the delivery as an extension of production, not as a separate shipping step.

Stage 1 — Confirm what is actually being shipped

Before any freight discussion, the order specification has to be closed out. For our aluminium frame kitchen collection each project is made to measure, with the finish, layout and dimensions specified to suit the space, so the following items are confirmed in writing and signed off against the drawings:

  • Overall run lengths, heights and depths for every wall, island and tall unit, taken from a site survey rather than architectural drawings alone.
  • Frame finish and profile style — black anodised or powder-coated profiles, and whether the infill is a solid panel or glass. Our aluminum frame with solid panel and glass front aluminum frame cabinets are built to the same dimensional discipline but pack differently.
  • Appliance cut-outs, sink positions, services and ventilation routes, checked against the plumbing and electrical drawings.
  • Interior configuration: drawer stacks, shelf heights, internal fittings and any integrated lighting.
  • Which items ship with the cabinets — worktops, splashbacks, handles, and whether locally sourced stone is being matched to our carcass dimensions.
Confirm dimensions and selected specifications for each project before production starts. A dimension corrected after production begins usually means remanufacture, and remanufacture resets the whole delivery date.

Stage 2 — Drawings and approval: the real deadline

On an international project order the critical path is almost never the factory. It is the approval loop. Our design coordination step produces detailed drawings for your review, and production is released only after you approve them. Build enough time into the programme for that round trip, especially when the site team, the designer and the client are three different parties in different time zones.

What we ask project teams to do at this stage:

  • Have the on-site builder or installer verify the survey against the finished floor levels and finished wall lines. Cabinet heights depend on the floor build-up, not the slab.
  • Return mark-ups with a single, named authority for decisions. Two reviewers producing two sets of comments is the most common cause of a lost week.
  • Sign off finishes and glass type — clear, frosted, bronze or smoked — at the same time as dimensions, so glazing is not ordered against an unconfirmed drawing.
  • Freeze the appliance schedule. A different oven model changes the cut-out and the surrounding carcass.

Stage 3 — Production and packing for the voyage

Cabinetry that survives a sea leg arrives packed deliberately, not just padded. For aluminium frame work the practical measures are:

  • Knock-down or semi-assembled crates where possible, so a damaged corner is a replaceable panel rather than a written-off unit.
  • Edge and profile protection on every black-finished extrusion; scratches on a visible frame face are the complaint we see most often after unloading.
  • Glazing separated from carcasses, individually crated and clearly marked as fragile and "this side up".
  • Hardware, hinges, runners and handles boxed separately and labelled against the crate they belong to.
  • Each crate marked with the room, wall and unit reference that matches the shop drawing, so the site team never has to guess.

We handle packaging and container loading as part of the shipment preparation, and we share the loading plan and packing list with you before the container is sealed. That document is what your site team should be holding on delivery day.

Stage 4 — Choosing the freight mode and the terms

Our logistics service covers freight forwarding by sea, air and rail, with customs paperwork handled on our side. For cabinetry the choice is usually straightforward:

ModeWhen it makes sense for cabinets
Sea, full container (FCL)The default for a whole kitchen or a multi-unit apartment order. Fewer handling steps than groupage, and the crates stay together in one box.
Sea, shared container (LCL)Used when the order is small or is being consolidated with other materials from us — flooring, wall panels, lighting or bathroom items going to the same site. More handling, so packing must be heavier.
AirReserved for replacements, sample units or a small set of profile sections needed to unblock an installation. Cost per kilogram is high relative to the volume of cabinetry.
RailAn option on land-linked routes where the project can accept a transit time between sea and air.

Then fix the commercial terms. Decide who is importer of record, which Incoterms apply, whether cargo insurance is taken out and by whom, and who clears customs at destination. We prepare commercial invoices, packing lists and certificates of origin as part of the shipment; import permits and destination-country requirements are confirmed for your specific country and order before dispatch. Ask us for the paperwork list early — a missing certificate of origin can hold a container at the port long after the cabinets have arrived.

Stage 5 — Sequencing the delivery against the site programme

Cabinets arrive in the middle of the fit-out, not at the end. The order that actually works on site is:

  • First fix complete — plumbing, electrical, ventilation tested and signed off.
  • Walls plastered and floor build-up finished to the levels shown on the drawings.
  • Wet trades in that room finished, so nothing is being painted or tiled around new units.
  • Cabinets delivered to a dry, secure storage area — not dropped on an open pavement for a week.

Tell us the site-ready date, not just the desired delivery date. We plan production and dispatch around it, and shipment tracking lets you watch the container while the builders finish their work. If the site slips, say so as soon as you know; storage arrangements are far easier to solve before the vessel sails.

Stage 6 — Receiving, checking and installing

The receiving check is where most avoidable disputes are settled. Assign one person to do it on the day:

  • Count crates against the packing list before the truck leaves.
  • Photograph any damaged or wet packaging at the point of unloading, before opening.
  • Open a representative crate and inspect profile faces and glass.
  • Report shortages or damage immediately with crate numbers and photos, matched to the packing list.

Installation follows the drawing references on each crate. Our service includes on-site installation support and a snag inspection after fitting; where your own crew fits the units, we provide the assembly sequence and technical guidance so the frame alignment and door adjustment are done to specification. Any replacement part that comes out of that inspection is produced and shipped against the same reference numbers, which is why the crate labelling matters long after unloading.

A short checklist for the buyer

  • Site survey verified by the installer, not taken from drawings alone.
  • One named approver; one consolidated set of drawing comments.
  • Finishes, glass type and appliance schedule frozen at drawing approval.
  • Incoterms, importer of record and insurance agreed before production release.
  • Paperwork list confirmed for the destination country early.
  • Site-ready date communicated; storage area prepared.
  • Receiving check done on the day with photos.

Send us your drawings and site-ready date

Share the floor plan, the survey and the target installation window, and we will come back with a production and delivery plan for your minimalist black aluminum frame cabinets — including packing, freight mode and the paperwork your port agent will need.