Built-in wardrobes arrive on site in the same window as flooring, doors and joinery. When the wardrobe sequence is out of step with the rest of the fit-out, panels sit in a corridor while trades wait, and the fixing details that should have been agreed on paper get settled on site. This guide walks through how we plan delivery and installation for Wood Grain Melamine Wardrobes on villa and apartment projects, stage by stage.

Why Built-in Wardrobes Are Scheduled Differently from Loose Furniture

Loose furniture can be unloaded into a clean room at almost any point in the programme. A fitted wardrobe is different: it is measured against the finished wall, and its panels must pass through rooms that are already decorated. That single fact sets the whole order of work.

Three conditions have to be met before a made-to-measure wardrobe can be fixed:

  • walls, ceiling and floor finishes in the bedroom or dressing room are complete, level and dry;
  • the opening sizes on site match the dimensions confirmed at order stage;
  • electrical points, lighting drivers and any integrated mirror or glass components have been positioned to the drawings.

If any one of these is still open when the crates land, the wardrobes cannot be installed. They are stored, protected and re-handled later, which costs labour and raises the risk of chipped edges on a decorative surface. Planning the delivery date around those three conditions, rather than around the container schedule alone, is where most of the savings are made.

Step 1: Confirm Site Dimensions Before Production Is Released

Our Wood Grain Melamine Wardrobes are made to measure, with the layout, finish and dimensions specified for each space. That flexibility is an advantage in design but a risk in delivery if the numbers are taken too early.

For wardrobe orders we ask for a second dimension check once the wet trades have finished in that area. Floor levels in particular shift after screed and the final floor covering are laid, and a difference of a few millimetres changes whether a wardrobe can be scribed to the ceiling or needs an adjusted pelmet. The dimension sheet we confirm back lists:

  • width, height and depth at three points across each opening;
  • position of skirting, architraves and any protruding door stops;
  • out-of-plumb and out-of-level readings for the fixing wall;
  • location of sockets, switches and light outlets relative to the carcass.

Production is released only after that sheet is signed off. Where a project timeline does not allow a second survey, we produce to the design drawings and record the deviation as an item for site adjustment instead of guessing at the difference.

Step 2: Match the Finish Schedule to the Room Sequence

Wood grain melamine surfaces are chosen for their warm, consistent look across a run of doors, and that consistency is what you want checked before crates leave. For each project we confirm the door and panel finishes against the approved sample, including grain direction and which face of the board the decorative layer is applied to. Sliding-door fronts, hinged fronts and open shelving in the same room are grouped so their tones read as one set.

The same logic applies where wardrobes sit next to other cabinetry from our range. If a bedroom wardrobe is meant to align with Wood Grain Melamine Cabinets in an adjoining dressing area or utility space, the two orders are produced in one batch so the surface texture and grain match. Ordering them separately, weeks apart, is a common cause of visible mismatch.

Where a project also uses matching Two Tone Melamine Wardrobes in children's rooms or guest rooms, we group those units into the same shipment and the same installation visit. One crew on site handles all wardrobe types at once, which keeps the room sequence intact.

Step 3: Group Shipments by Trade Window, Not by Order Date

Our Furniture Logistics and Door-to-door Delivery service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and delivery to the project address. For wardrobe packages we plan the consolidation around when the bedroom area becomes available, which is usually later than when a client places the order.

In practice this means:

  • Cabinets and door fronts ship together. Loose hardware does not travel separately from the panels it belongs to; each set is packed as one installable group.
  • Panel orientation is protected for road transport as well as ocean freight. Decorative faces are separated and edged, because the last movement a crate makes, from warehouse to bedroom door, causes most edge damage.
  • Delivery windows are booked with the site foreman, not only with the consignee. A wardrobe delivery needs trolleys, a clear route and someone to receive it; those are site resources, not shipping ones.
  • Documents travel with the cargo. Commercial invoices, packing lists and certificates of origin are prepared for the specific import, and the packing list is labelled by room so unloading follows the installation order.

Freight mode is chosen against the programme rather than cost alone. A villa fit-out with a fixed handover date may take rail or air for the wardrobe run while the remainder travels by sea; we plan that split at order stage so it does not become an emergency later.

Step 4: Prepare the Room Before the Crew Arrives

A short site-readiness check avoids most installation delays. We send this checklist with the delivery notice:

Item to checkWhy it matters
Paint, plaster and floor covering complete and dryPanels are fixed against finished surfaces; wet trades afterwards mark the melamine faces.
Clear route from lift or entrance to the roomFull-height door fronts and side panels will not pass around tight internal corners.
Power available for tools, and lighting in the room workingScribing and aligning doors needs light in the room itself, not just a work lamp.
Skirting removed or scribed where the carcass meets the wallDecided on site if it is not agreed beforehand, which slows every unit in the run.
Confirmation that ceiling height matches the order sheetCut-to-height adjustments on a decorative panel are difficult to hide.

Step 5: Installation Sequence and Handover

Our Furniture Installation and After-sales Support team handles on-site installation, inspection with the client's representative, snag items, spare parts and replacement. For a run of wardrobes the crew works in a fixed order:

  • carcasses levelled and fixed to the wall, with adjustment recorded for each unit;
  • shelves, drawers and internal fittings set out per room;
  • door fronts hung and aligned as a group, so gaps between doors read evenly across the run;
  • integrated lighting, mirrors or glass fronts connected after the joinery is fixed;
  • a final walk-through with the site contact, with any snags written into one list.

The snag list is where wardrobe projects are usually finished properly. Door alignment shifts slightly once a building moves after occupation, and adjustable hinges let that be corrected without replacing a panel. Spare door fronts and hardware for the specific finish are ordered with the original batch when a project has multiple room types, so a later replacement matches rather than stands out.

Common Coordination Problems and How We Avoid Them

Wardrobes delivered before the bedroom is finished

The fix is scheduling, not storage. We hold finished panels in the warehouse until the site confirms the room sequence, which is why the second dimension check and the delivery window are agreed together.

Site dimensions differ from the order sheet

Small differences are handled on site with scribing and adjustable components. Larger differences go back to the drawings before anything is cut, with the client's designer copied on the change so the appearance is not altered without agreement.

Two wardrobe finishes that should match do not

Prevented by batch production and one approved sample per project. Where a design calls for wood grain melamine alongside solid colour or textured fronts, the combination is confirmed on one sheet before either order enters production.

Planning Your Wardrobe Package

If your project includes fitted wardrobes in more than one room, send us the room list, the finish schedule and the current site programme. We will map each order to a production slot, a shipment group and an installation visit, and tell you which dates need a second survey before they are locked. As part of our Custom Furniture Manufacturer service, layout, material and finish choices for each wardrobe are specified to the space rather than taken from a fixed catalogue size.

Send your drawings, room list and target handover date, and we will return a delivery and installation plan for your wardrobe package, including which items should ship together and what the site must have ready before our crew arrives.