Open wardrobes arrive on site as frames, panels, rails, shelves and hardware. If the packaging does not match how those parts travel and get handled, the first thing your team meets in the container is a chipped edge, a bent upright or a missing bracket. For Metal Frame Open Wardrobes, packaging is not a formality at the end of an order — it is part of the specification you should settle before production starts.

Why Packaging Deserves Its Own Line in the Purchase Order

A metal frame open wardrobe is a mixed shipment. The structural frame is metal; the carcass, shelves and drawer fronts are board-based; the rails, hinges, brackets and fixings are small metal parts that shift easily. Metal edges can abrade adjacent finishes, and board panels crack at corners long before the middle gives way. Packaging therefore has to answer three separate questions: what protects the finish, what keeps the parts separated, and what lets the receiving team identify each bundle without opening everything.

This matters most on multi-room projects. When one container carries wardrobes for several bedrooms or units, an unlabelled bundle becomes a schedule problem at installation, not just a cosmetic one. Confirming packaging in writing is cheaper than re-manufacturing a panel after it lands.

1. Packaging Method: Knocked Down or Built Up

Ask how the units travel and get that method stated on the order.

  • Fully assembled: fewer parts on site and faster installation, but the units occupy more volume and the finished faces carry the handling risk all the way to the room.
  • Flat packed / knocked down: better cube efficiency and easier replacement of a single damaged panel, but every joint, cam and dowel must be labelled so assembly follows the shop drawings.
  • Hybrid: frames assembled with panels packed separately. Common for metal frame systems, since the frame stays square and the boards stay protected.

Whichever method is agreed, request photographs of the actual packed cartons before loading. A photo of corner protection and edge banding condition tells you more than a sentence in a proforma invoice.

2. Protective Materials by Component

  • Metal frames: corner protectors and interleaving between profiles, so powder-coated or plated surfaces do not rub during sea transit.
  • Board panels and shelves: edge protection plus surface interleaving; specify the face that must stay unmarked if one side is a high-gloss or lacquer finish.
  • Glass or mirrored inserts (if your specification includes them): glazed in crates with individual separators, and confirm they ship separately from heavy board bundles.
  • Hardware: bagged and labelled per unit, with a written contents list matched to the assembly drawing. Loose hardware in one shared box is where installation delays start.

3. Cartons, Crates and Palletisation

Confirm the carton grade and whether bundles are palletised or loose-loaded. For longer journeys with transhipment, palletised or crated bundles reduce forklift damage at intermediate terminals. Ask for:

  • carton dimensions, gross weight and net weight per bundle;
  • total carton count and total volume against the quoted figure;
  • the stacking limit printed on each carton, and whether mixed stacking is allowed;
  • moisture barriers for board components travelling by sea.

These numbers feed your own receiving plan: labour needed at the dock, storage space, lift or trolley requirements, and how many units can be opened per day without blocking the site.

4. Marking That Supports Your Site Team

Ask for bundle labels that carry the project reference, room or unit code, item code from the shop drawing, and carton number in a sequence such as 3 of 12. A wardrobe packed for a bedroom on level two should be identifiable without opening it. Also confirm that handling marks — this way up, keep dry, fragile — appear where they will actually be visible after container loading.

5. Loading Plan and Documentation

Request the packing list before the container is sealed, and match it to the commercial invoice and your own purchase order. The Furniture Logistics and Door-to-door Delivery service described on the SANTERSON service pages covers freight forwarding by sea, air and rail together with customs paperwork such as commercial invoices, packing lists and certificates of origin, plus container loading and shipment tracking. Terms, duties, insurance and transit arrangements are agreed project by project, so treat the paperwork you receive as the record to check against your order rather than a standard promise.

If several product lines ship together — wardrobes alongside Minimalist Open Wardrobes, Wall Mounted Open Wardrobes or other fit-out items — ask which bundles load first and where the wardrobes sit in the container. Furniture should not be crushed under heavier building materials.

6. Custom Dimensions and Branding

Made-to-measure units mean non-standard carton sizes, so confirm that oversized panels get their own protection and a clear place in the loading sequence rather than being wedged between standard cartons. Where private labelling or branding is part of the order — engraving, embossing, logos or custom packaging under the SANTERSON Custom Furniture Manufacturer service — agree in writing which parts carry that marking and how the outer cartons are labelled, since retail-facing packaging has different handling expectations than project cargo.

A Short Checklist to Send Before Production

  • Packaging method confirmed: assembled, flat packed or hybrid.
  • Protective materials specified per component: frames, panels, glass, hardware.
  • Carton size, weight, count and volume matched to the quotation.
  • Labels carry project reference, room code, item code and carton sequence.
  • Packing list approved before container sealing; loading position agreed.
  • Inspection point at delivery agreed: what is checked, photographed and reported, and to whom.

Damage claims depend on evidence. Photograph cartons before opening, keep damaged packaging until the count is complete, and record discrepancies against the packing list on the delivery note the same day.

SANTERSON manufactures furniture and building materials in China for villa, hospitality and office projects, with custom sizing, finish selection and door-to-door logistics coordinated by a dedicated project contact. Send us your wardrobe drawings, destination and delivery sequence, and we will confirm the packaging method, carton schedule and loading plan with the quotation so nothing is decided after production has started.