Open wardrobes look simple on a drawing. That is exactly where procurement problems start. When a bedroom joinery item has no doors, nothing hides the differences between what was specified and what arrives: shelf positions, exposed edges, hanging rails, wall fixings and the finish of every visible surface all sit in plain sight. The following documentation checklist is written for buyers, contractors and project managers specifying Minimalist Open Wardrobes for apartments, villas and hotel guest rooms.

Why an open wardrobe needs a fuller spec than a closed one

A hinged or sliding-door wardrobe can absorb tolerance issues behind a panel. An open system cannot. Every dimension is measured by the eye, every edge band is a design feature, and internal storage layout becomes part of the interior appearance rather than a hidden function. In practice this shifts risk to three places: the shop drawing, the material schedule, and the site condition record. If any one of them is thin, variations appear at handover instead of at approval.

SANTERSON's Open Wardrobes collection is supplied on a made-to-measure basis, with finish, layout and dimensions specified per project. That flexibility is useful, but it also means the buyer has to state what "as agreed" actually means before production starts. The sections below set out what to put in writing.

1. Dimension and setting record

Record the wardrobe envelope as a set of site-verified dimensions, not a nominal module size. For each unit, document:

  • Overall width, height and depth taken from finished wall and finished floor levels, including where tiling, skirting or screed changes the datum.
  • Out-of-plumb and out-of-square readings on the host wall, plus the agreed packing or scribing allowance.
  • Ceiling condition above the unit: exposed slab, gypsum bulkhead, curtain box, sprinkler head, air diffuser or lighting track that the top section must clear.
  • Adjacent items in the same run — bed headboard, bedside table, door swing, curtain line, switch and socket positions — with the clearance each one needs.

Where a unit is fixed to the wall rather than standing on a base, note the wall substrate and the fixing method agreed with the manufacturer. A wall-mounted open wardrobe transfers load into the wall build-up, so the substrate type and the fixing detail belong in the record before the wall is closed up.

2. Storage layout drawing per unit

Ask for a dimensioned internal layout for each wardrobe, not one generic elevation reused across room types. The drawing should show:

  • Hanging zones with single or double rail heights, stated in clear opening height rather than carcass height.
  • Shelf spans with thickness and support method; long unsupported spans sag, and an open unit shows it.
  • Drawer banks, tray counts and pull-out clearance, including anything that must clear a bed or an adjacent return.
  • Open display niches versus closed storage boxes, and which compartments are meant to hold luggage or seasonal items.
  • Integrated lighting: fitting type, cable route, driver location and the access point for maintenance or replacement.

Where a project mixes open and closed storage, keep one drawing per room type and label it with the room code used on site. A modular wardrobe run that combines open bays with closed modules should show which modules are open on every elevation, because the price and the finishing detail differ.

3. Material and finish schedule

In an open wardrobe the carcass interior is a visible surface. A material schedule that only names the exterior panel will not hold up at inspection. Specify, for each surface:

SurfaceWhat to record
Carcass and shelf boardsBoard type, thickness, colour or decor reference, and the supplier's reference code rather than a colour name alone.
Exposed edgesEdge band material, thickness, colour match and whether joints are mitred or butted at visible corners.
Frame elementsProfile type and finish — for example an aluminium frame in a stated colour — plus the glazing or panel infill where the design uses one. See Metal Frame Open Wardrobes for this family of designs.
Rails, brackets and runnersLoad rating as stated by the supplier, finish, and brand or model reference where a specific fitting is required.
Back panelsThickness, fixity and whether the back panel is finished on the visible face.

Keep approved physical samples with the schedule and record their batch or reference numbers. Colour names travel badly between factories and shipping containers; a signed sample does not.

4. Tolerance, interface and site-condition notes

Document the interfaces before order placement, because this is where open joinery most often fails on site:

  • Floor covering at the wardrobe line: carpet, timber, tile or vinyl, with its build-up height and whether the unit sits on the finished floor or a recessed rebate.
  • Wall finish tolerance and who is responsible for making good around the unit after installation.
  • Expansion gaps where a run crosses a movement joint or wraps an external wall.
  • Weather and moisture exposure if the bedroom faces a pool, terrace or unglazed loggia; state the exposure and ask the manufacturer to confirm the board and edge specification for it.

5. Commercial and delivery record

For imported joinery the paperwork carries as much risk as the drawing. For each wardrobe package, keep:

  • The purchase order with the layout drawing number and revision attached, so production cannot be signed off against an outdated version.
  • Pack list keyed to room codes and unit numbers, with each carton marked accordingly — installers sort by label, not by memory.
  • Shipping method and Incoterms as agreed, plus the packing standard for panels and glass or framed components.
  • A receiving inspection note recording panel damage, missing edge banding and short-delivered items on the day of unpacking, with photographs.
A practical rule: if a detail is not on a drawing, in the material schedule or in the site-condition record, it has not been bought. Open wardrobes make that rule visible at handover, so write the detail before production rather than negotiating it after installation.

6. Approval and handover trail

Close out each wardrobe type with a short sign-off pack: approved shop drawing revision, approved sample reference, agreed site conditions, and the inspection record from delivery and installation. For multi-unit residential and hospitality projects this pack is what turns a snag list into a defensible handover document, and it protects the buyer when variations are claimed later.

Where the same project also needs closed storage, bedroom doors or built-in cabinetry in matching finishes, coordinating those items with one furniture and building materials supplier keeps the material references consistent. Custom minimalist bedroom wardrobes and other interior fixtures are listed on the SANTERSON site alongside the open wardrobe collection, and project enquiries can be raised through the contact page.

Note: dimensions, material options, load ratings and fixing details are confirmed per project with the manufacturer's technical team. Nothing in this article should replace the approved shop drawings for a specific job.