A set of raised panel wardrobes looks straightforward on a drawing: a carcass, a run of doors with a profiled centre panel, some internal fittings. On site it is one of the most coordination-sensitive items in a bedroom fit-out, because the door profile has to clear skirting, handles and adjacent walls, and made-to-measure sizes only work if the opening was recorded correctly before production started. An installation plan is what turns a good shop drawing into a clean handover.

Below is the documentation and sequence we ask project teams to settle before a paneled wardrobe order is released, based on how our built-in furniture is made and delivered.

1. Survey record of the actual opening, not the drawing opening

Raised panel wardrobes are made to measure, so the survey sheet is the first deliverable in the plan. Record it after flooring, skirting, plaster and ceiling finishes are in place, or state clearly on the sheet which finishes are still outstanding and by how much they will change each dimension.

  • Width, height and depth at three points along each wall - left, centre, right - not one average figure.
  • Floor level difference across the run, since a long wardrobe on an unlevel slab needs scribing or an adjustable plinth.
  • Position of skirting boards, architraves, door reveals and radiator positions that the carcass has to scribe around.
  • Ceiling condition: flat plaster, cornice, exposed services, or a bulkhead the wardrobe abuts.
  • Electrical outlets, switches, thermostat heads and wall lights that fall inside the wardrobe footprint, with their heights.

Where the wardrobe returns into a corner or wraps past a door opening, add an internal corner dimension and note which leg is built first. A single missing return measurement is a common reason a paneled run arrives on site and stops fitting.

2. Door swing and clearance check

Paneled hinged doors sit deeper in the reveal than flat fronts, and the raised profile reads best when the door can open fully. Put a simple plan sketch in the installation pack showing every door arc against:

  • The bed, bedside table and any chest placed within the swing zone.
  • The bedroom door and any en-suite door that crosses the same wall.
  • Curtains, headboards or wall-mounted lighting fixed to the shared wall.

If a clearance fails, decide it on paper before production: switch that bay to a sliding front from our sliding door wardrobes range, shorten the run, or move the furniture layout. It is a drawing decision at this stage and a demolition problem later.

3. Confirmed specification sheet

The plan should carry one signed specification page that matches the order. For our Classic Paneled collection this covers:

ItemWhat to confirm before release
Door styleRaised panel profile, and whether the same profile continues on recessed panel wardrobes or matching doors elsewhere in the project
Material and finishBoard material, surface finish and colour reference, with a physical sample approved rather than a screen proof
DimensionsFinal made-to-measure sizes per bay, taken from the survey sheet above
Internal layoutHanging zones, shelf stacks, drawer banks and any mirror or trouser rail, drawn to scale with heights
Handles and hardwareHandle type and fixing centres, hinge type, soft-close specification, drawer runners
Plinth and scribingPlinth height and finish, scribe fills to out-of-square walls, skirting treatment
LightingInternal door-triggered or motion lighting, cable routes and where the transformer sits for access

The product range is specified per project - finish, layout and dimensions are all set to suit each space, so treat the specification sheet as a live document until it is signed. Confirm every dimension and selected specification again at sign-off; nothing in a made-to-measure order should be inferred from a previous bay.

4. Interface responsibilities with other trades

Built-in wardrobes sit between several trades, so the plan names who does what and in which order:

  • Electrical first fix: relocating sockets and switches outside the carcass zone, running cables for internal lighting to an accessible point.
  • Wet areas: if the wardrobe shares a wall with an en-suite, confirm the waterproofing and tile line before the carcass is fixed.
  • Flooring: whether the wardrobe sits on finished floor or on a cut-out, and who replaces flooring under the plinth after installation.
  • Decoration: who carries out final touch-in of scribe fills, cornices and the wall-to-carcass joint after fixing.

A short responsibility table with names and dates prevents the common end-of-project argument about who owns a visible gap at the wall line.

5. Delivery, access and storage on site

Wardrobe panels are long, and doors with a raised profile mark easily. The plan should record the delivery window, the lift or stair route to the bedroom floor, and a dry, flat storage area where panels can stand against a wall with protection between them. Where we handle logistics and door-to-door delivery, the delivery note, carton list and room-by-room labelling should reach the site contact before the truck arrives, so the right carton goes to the right bedroom on the day.

6. Installation sequence and fixing method

State the intended order of work in the plan so the site team can prepare the wall:

  • Confirm the survey one final time against the delivered cartons before anything is unpacked.
  • Level and fix the carcass or base run, then scribe to out-of-square walls.
  • Install internal fittings while the carcass is still open and accessible.
  • Hang doors, set the reveal on every panel, then adjust until the raised profiles align across the run.
  • Fix handles, connect internal lighting, and only then close up the plinth and scribe fills.
  • Touch-in decoration, protect the fronts, and hand over with doors closed and adjusted.

Wall fixing method depends on the substrate. Note in the plan whether the wall is masonry, stud partition or plasterboard, because that determines bracket type and whether a top fix, back fix or both are used. Where the wall cannot take a load, say so before production so the carcass can be specified as a freestanding unit.

7. Snag list and handover

Close the plan with the inspection step: door alignment across the run, drawer runners and soft-close action, no marks on panel faces, internal lighting working, and all fixings concealed. Our installation and after-sales support covers on-site installation, inspection and snags, spare parts and ongoing maintenance. Warranty terms and response arrangements differ by project, so confirm them in writing with our team before handover instead of assuming them from a brochure.

Practical rule: if the survey sheet, the signed specification page and the door-swing sketch all agree, the wardrobe installs. If any one of the three is missing, expect adjustment on site.

Working from drawings to a fitted run

For projects that need survey, shop drawings and production handled together, our interior design services include space layout planning, furniture layouts with 3D renderings, and project design coordination covering drawings, production coordination and on-site guidance. Our custom and OEM service covers bespoke finishes and sizes where a standard profile has to match existing joinery on site.

Send us the bedroom elevations, the finish reference and the intended furniture layout, and we will return a wardrobe specification together with the survey points that still need confirming on site. That is the quickest route to an installation plan your site team can actually build from.

Dimensions, finishes and hardware are specified per project; confirm all measurements and selected specifications before production release.