A smoked glass wardrobe door looks simple on a rendering. It is the ordering behind that door where projects go wrong: one opening measured twice, one leaf short of the clearance it needs, or tinted glass specified in one room and mirror in another with nobody to reconcile them. This guide covers how to set quantities for smoked glass wardrobes and how to coordinate the adjacent products so a bedroom fit-out arrives as one consistent package rather than several separate purchases.
Start from openings, not from a wardrobe count
The unit number is the least useful figure in a wardrobe schedule. Two bedrooms with identical floor areas can need three doors or five, depending on ceiling height, door swing and whether the run turns a corner. Build the quantity sheet around each opening and record four values for it:
- Floor-to-ceiling height at both ends of the run, plus the finished floor level if screed or flooring is still to be laid.
- The clear width available after skirting, architraves and any recess are accounted for.
- The operating zone in front of the opening: a hinged door needs its own swing arc, while a sliding leaf needs track depth and an overlap allowance rather than floor clearance.
- What sits inside the carcass for that room: hanging lengths, drawer banks, shelving bays, lighting or a mirror panel.
Santerson wardrobes in this range are made to measure, with layout, finish and dimensions specified per project, so there is no standard module to round your numbers up to. That flexibility is the reason the schedule has to be right before production starts: a made-to-measure panel that misses the opening by 20 mm cannot be trimmed on site the way a stock unit can.
Set quantities at leaf level, not unit level
Order in doors and carcass sections. A run of 2,400 mm might resolve as three sliding leaves or four hinged ones, and those two answers carry different hardware, different track lengths and different installation labour. The same opening can also take a frameless glass door or an aluminium-framed one, which changes the profile allowance again. For each room, list:
| Line item | What to record | Why it matters downstream |
|---|---|---|
| Carcass sections | Width, height, depth of each section and the order they assemble in | Determines the joint detail where two sections meet and whether a corner post is needed |
| Glass leaves | Count per opening, tint, thickness option, edge treatment, handle or profile side | Tint and edge work are specified leaf by leaf, so mixing counts across rooms risks tone differences that only appear once installed |
| Framed alternatives in the same room | Whether any opening uses an aluminium-framed glass door instead of a frameless one | Framed and frameless doors sit differently on the same wall and need separate track or hinge allowances |
| Interior fittings | Drawer banks, hanging rails, shelves, mirror panels, integrated lighting | Fittings fix the internal layout before the door size is finalised |
| Spare leaves and hardware | A small contingency for glass leaves and moving hardware on multi-unit jobs | Glass in transit and replacement rollers are the two most common mid-job gaps |
The contingency line is worth pricing deliberately. On a villa or apartment handover, a chipped leaf discovered after installation cannot be replaced from shelf stock; it goes back into production with its own lead time, and the room stays incomplete while it does.
Keep the tint family consistent across rooms
Smoked glass reads differently against different wall colours and light levels, which is exactly why buyers like it. It also means an inconsistency shows. Where a project uses smoked glass in more than one space, decide once whether each opening takes a frameless glass door or a smoked glass aluminium frame wardrobe, and record that choice per room on the schedule. The two families solve different problems: a slim metal frame gives a crisp shadow line and a rigid edge for tall leaves, while a frameless door lets the tint carry the whole elevation.
Then hold three variables constant across the rooms that are visible to each other:
- Tint depth. Smoked, bronze and frosted glass in this catalogue are separate products, and a bedroom specified in smoked glass next to a dressing room specified in bronze will not read as one design intent.
- Furniture style. If the same project also uses smoked veneer wardrobes as a solid-panel counterpart, specify the carcass and frame tones together with the glass edge detail rather than treating them as unrelated items.
- Handle and profile finish. Frame finishes travel visually across the joinery; mismatched metals are noticed long before a slightly off dimension is.
Where a project needs smoked glass in kitchen display cabinets as well as bedroom doors, keep the tint reference on one document. Smoked glass aluminium cabinets and smoked glass wardrobe doors are separate product lines with their own detail drawings, and a shared finish reference is the only thing that keeps them looking related once installed.
Coordinate the products that touch the wardrobe
Wardrobe orders stall far more often on an interface than on the wardrobe itself. Work through these dependencies before you release the order:
- Floors and skirting. Engineered flooring laid after the carcass sits proud of the base; laid before it changes the floor-to-ceiling height the doors were cut to. Fix the sequence in the programme, not on site.
- Wall finishes and architraves. These consume millimetres at the reveal and change where a sliding track can be fixed.
- Doors and partitions nearby. A room door that swings into the wardrobe wall reduces the usable leaf count on that run; where the same wall also carries glass sliding doors or a glass sliding door wardrobe, share the track detailing and metal finish across them.
- Lighting. Integrated cabinet lighting needs its driver position, cable route and switching decided before the carcass is closed up, not after.
- Vanity and bathroom joinery on the same floor. Where a fit-out also includes vanities or mirror cabinets, matching metals and panel tones are easier to specify from one schedule than reconciled later.
This is where a single supplier for built-in furniture and the surrounding finishes saves coordination cost. Santerson supplies wardrobes and built-in joinery alongside kitchen cabinetry, interior doors, wall panels, vanities, lighting and engineered flooring, so interfaces that would otherwise sit between several vendors get resolved on one drawing set with one production sequence.
Sequence the order for a multi-unit job
For apartment blocks, serviced units or villa portfolios, split the release into batches rather than ordering everything at once:
- Confirm one prototype room end to end: carcass, glass tint, frame finish, internal layout and door operation. Sign it off physically before repeating it.
- Release the first floor or building block only after that sign-off, so any change is made once rather than across every unit.
- Schedule site survey of the remaining openings against the actual finished floor levels achieved on the completed units, since as-built heights drift from drawing heights.
- Group deliveries by installation crew and sequence, and keep glass leaves packed so they can be carried to floor without passing through other trades' work.
What to send with your enquiry
A complete enquiry shortens the round trip considerably. Include:
- A room-by-room schedule with opening widths, heights and depths taken from finished dimensions.
- The leaf count you expect per opening, or the drawing if one exists, plus which openings are hinged and which are sliding.
- Tint, frame profile and metal finish references, held consistently across rooms.
- Internal layout per room: hanging lengths, drawer banks, shelves, mirror panels, lighting.
- The interface conditions that affect installation: floor sequence, wall build-up, ceiling type, and where the delivery can be received.
Send those items with your drawings and the quotation covers the actual job instead of an assumption about it. As a China-based manufacturer of furniture and building materials serving villa, hospitality and apartment projects, SANTERSON works from made-to-measure specifications with custom and OEM options, door-to-door logistics and installation support, so the quality of that first schedule directly determines how smoothly production and delivery follow.
Product dimensions, glass thickness options, finishes and hardware availability are confirmed per project during specification. Site conditions, local building requirements and installation arrangements should be verified with your design team and contractor before ordering.