A glass partition order rarely travels alone. Panels, tracks, hardware and fixings have to arrive together, undamaged, and in the right sequence for the site crew. Because our partitions are made to measure rather than stocked, a delivery plan is really a production plan seen from the other end. The steps below follow the order we work in — design and specification, production, packing, freight, customs, delivery and after-sales — so you can see where each decision belongs.

Start With the Survey, Not the Freight Quote

Made-to-measure partitions only fit the opening they were measured for. Before any shipping discussion begins, we close out three items on the specification sheet:

  • Final opening dimensions and floor levels, confirmed by a survey or by drawings signed off on site — not by an early concept layout.
  • Glass type and finish for every panel, together with the safety requirement you need the glazing to meet. Our product pages list glass type and safety requirements as project-specific items to confirm, so we record them in writing rather than assume them.
  • Track, hardware and fixing details, including how each panel is opened and what it is fixed to.

Our glass partitions sit in the Custom Partitions & Paneling collection, where size, material and finish are specified per project. The same is true for the related systems we supply on the same shipment: glass sliding panels, partition sliding systems and wood panel partitions. If a project mixes glass with timber cladding, we group them on one production schedule so they arrive together.

Agree the Delivery Terms Before Production Starts

Delivery responsibility changes what you need from us. Door-to-door delivery means we handle freight and the final leg to site; port or warehouse delivery means your forwarder takes over earlier. We state which applies in the proforma, along with who arranges cargo insurance.

Delivery arrangementWho books the main legWho clears customsWhat you still need on your side
Door-to-door, arranged by usSANTERSONYou, as importer of recordImport licence or permit if required, duty and tax payment, site access for the truck
Port or warehouse deliveryYour freight forwarderYou or your brokerForwarder booking in advance, inland transport to site, unloading gear
Mixed shipment with other fit-out goodsAgreed per consignmentYouOne consolidated packing list, and a named lead for receiving

We arrange sea, air and rail freight, prepare the shipping documents and manage container loading on our side. Your importer of record handles duty, tax and any permit questions in your country, because those rules are set locally and we do not want to guess them for you.

Pack for the Panel Size, Not the Carton Standard

Glass fails at the edges and on the corners, so packing follows panel size and how the panels sit in the container. For each order we settle:

  • Plywood crates with edge protection for glass, and vertical racking inside the container so panels are not stacked flat under load.
  • Hardware, tracks and fixings packed separately and marked to the panel or zone they belong to, so nothing is lost in a shared container.
  • A packing list that names each crate by room or level — "Level 2, treatment rooms, panels 1–4" reads far better on site than "carton 7 of 12".
  • Container loading plan agreed before the van arrives at our factory, so heavy items go on the floor and glass goes last.

If you are also ordering other joinery from us in the same consignment, tell us early. We consolidate where it saves cost and separate where a mixed crate would slow the install down.

Sequence the Shipment With Site Works

Glass partitions go in after wet trades, ceilings and floors are finished, but before loose furniture and final cleaning. We schedule production against your programme so panels land when the openings are ready, not months earlier sitting in a warehouse. For staged projects we split the order by zone and ship in install order, which keeps one crew working through a building instead of waiting.

Two practical points we confirm in writing before shipment: the earliest date your site can receive glass, and the latest date your programme can absorb a delay. Those two dates bracket our production slot.

Clear Customs With Documents That Match the Goods

Most delivery problems we see are document problems. Our logistics team prepares commercial invoices, packing lists and certificates of origin, and supports import permits where they apply. The check that saves the most time is simple: the description, quantity and value on every document match the crates actually in the container. Where your broker wants a specific wording for glazing or joinery, send it to us before the documents are drafted.

Receive, Inspect and Report on Arrival

  • Count crates against the packing list before the truck leaves site, and photograph any damaged crate from outside before it is opened.
  • Open one crate per panel type, check edge condition and hardware contents, then re-seal. Full inspection happens at install.
  • Send us photos and the crate number the same day if anything is chipped or missing. Replacement panels are made to measure, so a report on day one beats a report in week three.

Warranty terms, spare parts and maintenance support are listed under our installation and after-sales service; we confirm the applicable terms for your order rather than quoting a general promise.

Handover: What We Need From Your Site Team

  • A confirmed opening schedule with finished floor levels, so made-to-measure panels match what was actually built.
  • Track and fixing approval before we ship, once you know the substrate.
  • One named person on site who signs for deliveries and can answer a measurement query within a day or two.
A short rule of thumb: anything fixed to the building — glass, tracks, frames — should be specified after the wet trades are settled. Anything replaceable — blinds, hardware covers, mirrors — can follow later and travel separately if that helps your cash flow.

Ordering Through One Supplier Keeps the Delivery Simple

When partitions, wall panelling, doors and joinery come from several factories, each shipment has its own documents, its own delays and its own gaps. As a one-stop furniture and building materials supplier, we put glass partitions on the same production schedule as the cabinetry, wall panels and doors around them, so the project clears customs once and lands on one delivery plan.

If you have drawings or an opening schedule, send them over with your target site date. We will come back with a specification sheet, packing proposal and delivery option for your location.