When a swim spa moves from a mood board into a project budget, the drawing is only half of the job. The other half is agreement: what exactly is being bought, who supplies each part, and where the site contractor's responsibility ends. This article uses Outdoor Swim Spa WS-S38 as a worked example, so designers and buyers can see which items usually cause change orders when they are left open.
Start with the footprint, not the brochure image
The catalog lists WS-S38 at 3760 × 2080 × 1110 mm. Those three numbers describe the shell, and they are what a designer should test against the plan before anything else is discussed. Two checks matter early:
- Clear opening versus finished surround. The spa sits inside a deck, terrace or garden platform. Agree who builds that structure, what tolerance it allows, and how the unit reaches its position — crane, forklift or manual carry along a defined route.
- Coping level versus finished deck. At 1110 mm overall height, the relationship between the coping, the finished deck finish and the access steps changes how the installation reads. Fix that section on paper before the paving order is placed.
Read the specification as a scope list, then close the gaps
The published figures for this model are a starting point for coordination rather than a final purchase document:
| Catalog item | Value shown | What both sides must confirm |
|---|---|---|
| Overall dimensions | 3760 × 2080 × 1110 mm | Set-out drawing, access route, surround detail |
| Water pump / filter pump | 3 pcs / 1 pc | Which units are in the quoted package for the chosen configuration |
| Jets | 51 pcs total, including 6 water columns | Jet layout and count as configured, not as catalog maximum |
| Lighting | 4 pcs plus 12 small LED lights | Fitting positions, control method, spare allocation |
| Total power | 14.05 kW | Supply capacity, dedicated circuit, protection device, electrician's scope |
| Control system | 1 set | Location of the control point and who runs the cable to it |
| Swim training system | Not listed in the catalog record | Whether a swim current is required at all, and if so what is offered |
The last two rows are where misunderstandings cost the most. A project that assumes a counter-current swim station is included, when the model record does not list one, will discover it on site. Equally, a 14.05 kW connected load needs an electrical engineer's sign-off before the spa is committed: the supplier confirms the equipment, the local engineer confirms the supply.
Catalog-listed options for this range include control systems, UV sterilization, water pumps, heat pumps, sand filtration, insulation and steps. Availability and compatibility vary by model, so price the option list item by item in writing before order confirmation rather than carrying it as an assumption.
Split the scope into three columns on one page
Every swim spa procurement works better when a single table states who does what. For a villa or hospitality installation of this type, that usually breaks down as:
- Supplier side: the spa shell and configured equipment package, packaging and container loading, freight and shipping documents, delivery to site.
- Client or main contractor side: foundations or supporting platform, waterproofing of the surround, electrical supply and dedicated circuit, drainage, lifting equipment on arrival, and site access for the agreed delivery date.
- Agreed jointly: the set-out drawing, the priced option list, the inspection checklist at handover, and the spare-parts contact after commissioning.
Under its Turnkey Interior Project Solutions, SANTERSON covers design consultation and product specification, manufacturing and quality control, logistics through to door-to-door delivery, and installation support — so the supplier column can be widened or narrowed depending on how much the buyer wants to keep local. Either way the boundary is drawn once, in writing, before production starts.
Decide early whether a standard model or a customised unit fits
Where the space is irregular or the design intent drives a specific form, a shaped unit may serve better than a rectangular one. The Customizable Shape Outdoor Spa covers square, round, oval and curved layouts with an acrylic shell and structural reinforcement, which suits gardens, terraces and leisure areas where geometry leads the design. Compare that against a fixed-catalogue model such as WS-S38: the standard model is faster to specify and simpler to price, while a customised shape needs a longer agreement on dimensions, jet positions and services.
If the brief calls for hydrotherapy features across a longer water body, review the wider Swimming Pools and Swim Spas range before locking in a single model. Jet count, pump arrangement and total power differ from one model to another, and those differences drive both the electrical design and the running assumptions the client is quoted.
Questions that should be answered before the purchase order
Six items to close in writing
- Which equipment is included in this configuration, and which options are quoted separately?
- What is the confirmed connected load, and who provides the protection device and the cable to the unit?
- Who supplies and installs the access steps, and when do they arrive relative to handover?
- Which water treatment route applies — ozone as shown, plus UV sterilization if selected — and who maintains it after handover?
- What is inspected at delivery, and what document records acceptance on site?
- Which spares are held, by whom, and how are replacement requests raised after commissioning?
Send the drawings, get a scoped quotation
Share the plan, the section through the surround and the required option list for Outdoor Swim Spa WS-S38, and the specification can be confirmed item by item before production is scheduled — including packaging, freight documents and delivery to site. Send drawings through the project enquiry page.