A handleless concealed door looks simple on a drawing: one flush sheet, no visible frame, no hardware, no lining. That simplicity is exactly why quantity take-offs go wrong. The door itself is only one line in the schedule; the wall build-up, opening reinforcement, ceiling heights and finish continuity decide whether it installs cleanly or stalls on site. This guide sets out how to count Santerson Handleless Concealed Doors across a project, which related product families need to be scheduled alongside them, and what to confirm before an order is placed.

What You Are Actually Ordering

Santerson Handleless Concealed Doors sits in the Flush / Concealed Doors collection and is made to measure for each project. Finish, layout and dimensions are specified per space rather than chosen from a fixed size range, and material and finish options are selected at configuration stage. Two practical consequences follow.

  • Every opening is a unique item. Quantities cannot be reduced to one line for a whole door type unless the openings genuinely repeat with identical dimensions, wall thickness and swing direction.
  • The order closes only once dimensions and selected specifications are confirmed for that project. Until then, treat the number as provisional in your schedule.

Because sizing is made to measure, a quantity plan built on nominal blockwork dimensions will not match the finished opening. The dimension that matters is the completed opening after plaster, board or panel finishes are accounted for, measured and recorded per door position.

Step 1: Build a Door Schedule Before You Count Anything

Work from a door schedule, not a marked-up plan. For each position record the information that changes price, lead time or site readiness:

  • Position number and room, so each unit can be traced on site and in delivery paperwork.
  • Finished opening width and height, plus wall build-up thickness at that position.
  • Swing direction and whether the door is specified to sit flush with one face or both faces of the wall.
  • Finish intent: painted, matched to Wood Veneer Panels and adjacent joinery, or left for site decoration.
  • Above-head condition: full-height to ceiling, head to a soffit, or sharing a run with Flush Wall Aligned Doors.
  • Floor finish build-up at the threshold, which sets the clear opening height.

A schedule kept in this format is what allows a manufacturer to quote accurately and what lets you compare like-for-like between bidders. A quantity list without these fields invites variations later.

Step 2: Count the Positions, Then Group Them by Type

Grouping by type does not mean grouping by size. Group by the specification that has to be repeated: same finish family, same head condition, same wall build-up. Repeating types are what allow production runs and site details to be standardised; identical sizes across unrelated rooms rarely recur in villas and hospitality fit-outs.

Quantity lineHow it is countedWhy it belongs in the take-off
Handleless concealed doorsOne unit per confirmed opening, listed individually by position numberMade-to-measure units; each position carries its own dimensions and finish
Matching concealed or decorative concealed doors in the same wall runCounted separately but specified as one family with the primary doorKeeps reveals, shadow gaps and finishes consistent across a wall
Adjacent paneling and joinery runsMeasured as linear area of wall, not per doorPanel edges must resolve neatly against each door edge
Related hinged and sliding doors elsewhere in the projectCounted by collection and finish familyAvoids duplicated wall preparation work when openings are reworked late
Spare units held for maintenanceDecided per project, agreed before order closeLater matching of a made-to-measure finish is harder than ordering spares in the same run

Step 3: Coordinate the Wall Build-Up Around the Door

Concealed doors fail on site less often because of the leaf and more often because the surrounding wall was built without them in mind. Three coordination points decide the outcome.

Opening reinforcement and wall thickness

Confirm the wall build-up at each position before the schedule is frozen, since concealed door components sit inside that build-up. Where a partition is shared with a run of Integrated Door & Paneling, one party must own the detail: who sets out the opening, who reinforces it, and who closes the finishes.

Ceiling and head details

A full-height door meets the ceiling, so the ceiling set-out has to be resolved at the same time as the door schedule. Where a head is set below the slab, note the soffit height in the schedule rather than assuming it on site.

Floor levels and thresholds

Clear opening height depends on finished floor levels. Different floor build-ups across a threshold change clearance, so record them with the position rather than leaving them to be discovered during installation.

Step 4: Schedule the Related Door Families in One Pass

Projects rarely specify one door type throughout. Coordinating related families in the same pass prevents three separate rounds of wall preparation, and keeps finishes coherent between rooms.

Each of these is specified with made-to-measure sizing and material and finish options, so the same schedule discipline applies across the whole door set. Grouping them in one pass also means you review the full Windows and Doors range once, rather than re-opening the specification after walls are closed.

Step 5: Confirm Finishes Against the Surrounding Package

A concealed door only reads as a wall if its finish matches what surrounds it. Where doors sit inside panelled or veneered walls, decide early whether the door leaf is supplied ready for the same finish or prepared on site, and make sure the same material batch and grain direction are called up for both. This is also where Wall Panel Systems and built-in joinery should be cross-checked: a wardrobe, media wall or niche panel abutting a concealed door has to be dimensioned against the same opening record.

Where a product page lists both a collection name and an individual product title, pick one naming convention and use it consistently across the schedule, drawings and purchase order. Mixing collection references such as "Flush / Concealed Doors" with individual product titles in the same document is a common source of substitutions and re-orders.

Step 6: Sequence the Order With the Rest of the Fit-Out

Made-to-measure doors sit on the critical path between wall set-out and decoration. A practical sequence for a villa or hospitality package:

  • Freeze room set-out and finished floor levels, so opening dimensions are stable.
  • Issue the door schedule with position numbers, confirmed dimensions, wall build-ups and finish intent.
  • Confirm specifications and close the order; hold spares decision at this point, not after delivery.
  • Schedule deliveries against wall closure dates, so openings are ready when units arrive.
  • Book installation with a snag list per position, and record which positions were site-adjusted for future maintenance.

Santerson's project services cover design coordination, custom and OEM work, logistics and door-to-door delivery, and installation and after-sales support. For multi-unit projects, that means the door schedule can be issued as part of a wider package alongside cabinetry, paneling and other Interior Fixtures, which reduces the number of separate suppliers coordinating the same openings.

Common Quantity Mistakes to Avoid

  • Counting nominal openings. Take dimensions from finished openings, not blockwork or stud set-out.
  • Assuming repeat sizes. Made-to-measure units are per position; verify before grouping.
  • Omitting swing direction and face-flush intent. Both change the detail and cannot be corrected after walls close.
  • Scheduling doors without adjacent paneling. Panel edges and shadow gaps need one owner.
  • No spares decision before order close. Matching a made-to-measure finish years later is difficult.

Before You Place the Order

A complete submission for Santerson Handleless Concealed Doors carries a position-by-position schedule, confirmed finished opening dimensions and wall thicknesses, swing and flush details, finish intent matched to the surrounding package, head and threshold conditions, related door families grouped in the same pass, and an agreed spares quantity. Anything left out of that list tends to return as a variation once the walls are up.

Send your door schedule and drawings with position numbers and finished opening dimensions, and the specification can be confirmed against the Flush / Concealed Doors collection together with the related hinged, sliding and pocket door families in one pass.