An arched wardrobe looks simple on a rendering: a run of paneled doors with a curve along the top, matching the arch detailing elsewhere in the bedroom or corridor. That simplicity is exactly what makes it risky to order. Curves change how a door is built, how it meets the ceiling, and how much clearance the frame needs above the opening. This article sets out the items we ask procurement teams to record before an Arched Paneled Wardrobe is quoted, so drawings, prices and site conditions all say the same thing.

Working rule: if a detail is not written into the schedule and signed off on a shop drawing, it does not exist. Everything below belongs in one document, referenced by room and wardrobe code.

Start with the arch geometry, not the finish

Finish choices are easy to change at this stage; geometry is not. For every arched unit, record the shape and the numbers behind it.

  • Arch type and profile. State whether the top is a true semicircle, a shallow segmental arc or an elliptical curve, and give the rise over the span. Two drawings can both be labelled "arched" and produce completely different door panels.
  • Pitch line and ceiling condition. Note the finished floor level, the finished ceiling level, and whether the arch springs off a wall head that is out of level or sloped. Record which surface governs: for a full-height built-in, the site wall usually sets the line, so the drawing should show the measured high and low points.
  • Radii and break points. Give the radius at each curve and mark where straight runs begin. Curved transitions in niche paneling, arch heads and door panels need to share one set of radii, or the arches will read as mismatched once installed.
  • Cornice and skirting interface. State whether the wardrobe stops below an existing cornice, runs through it, or carries its own arched head trim. Decide who makes good the ceiling line above the unit.

Document the door build and how the arch sits in it

On a rectangular wardrobe, panel size is routine. On an arched one, the panel outline itself becomes project-specific, so specify it.

Item to documentWhy it matters at order stage
Door type: hinged or slidingHinged arched doors follow the curve of the panel; sliding arched doors need track clearance above the opening. The two options do not share head details.
Panel construction: framed with raised or recessed panel, or moulded one-piece frontFramed construction allows an arched rail with a shaped panel inside it. A moulded front is limited by the profile and radius available, so confirm what the collection actually offers.
Panel field and mould directionAn arch changes where the horizontal members fall. Note which members follow the curve and whether the mould runs with the door outline or stays square.
Mitred vs. butt corners at the springing pointAffects appearance, tolerance handling and how the unit absorbs a non-square wall head.
Handle or handleless edge, and hardware positionHardware on an arched door cannot always sit at the usual height. Mark the exact fixing point and the leaf type, including soft close where required.
Ventilation, if doors enclose an air-conditioned or damp zoneGrille or louvre detail in an arched panel needs to be drawn; it cannot be added on site without visible compromise.

Where the design language is classic rather than flat-fronted, cross-check the arched unit against its siblings in the same package. Our Decorative Moulded Paneled Wardrobes and Classic Wooden Hinged Wardrobes are commonly specified alongside arched doors in villa work, and the panel profile, stile width and finish have to match across all of them. If a bedroom also contains a full-height run with flat fronts, note explicitly which doors are arched and which are square so nothing is quoted on assumption.

Record the internal layout against real storage needs

The arch eats vertical space at the ends of the run. What matters for the buyer is what you lose and what you decide to do with it.

  • Hanging heights, by garment. Long-garment zones need a clear drop; short-garment zones can sit under a shelf. Mark both, and mark where the arch begins to cut into usable height.
  • Shelf and drawer stack. Give the number of drawers, their heights and whether any drawer sits beneath an arched head, which reduces depth at the top of the carcass.
  • Corner and end returns. Note L-shaped returns, angled ends and any mirrored or glass-front section, with the code for each. Our Glass Sliding Door Wardrobes are sometimes specified as a companion unit in apartments where hinged swing clearance is tight.
  • Integrated extras. Ironing station, lighting inside the carcass, glass shelves, trouser pull, safe box: list them and say which party supplies each one.
  • Access to services. Record any pipework, duct, switch or sensor behind the line of the wardrobe, with its offset from the wall face.

For projects where storage capacity matters more than mouldings, a flat-panel alternative is worth pricing side by side. A Custom Minimalist Bedroom Wardrobe uses the full height of the wall and avoids the curved head detail altogether, which often gives a usable comparison against the arched option.

Specify materials and finishes in words that survive translation

Colour names travel badly between offices. Specify by reference instead.

  • Substrate and surface system. State the board type for carcass and door, plus the surface treatment: paint, lacquer, veneer or laminate, with the make-up of each layer where it matters to performance.
  • Colour and sheen reference. Give a RAL or manufacturer code, and separately state the sheen level. "Beige, satin" is not an order; a code plus a signed sample is.
  • Veneer specification where used. Note species, cut, grain direction across doors, matching pattern across a run, and the acceptable range of colour variation between leaves.
  • Signed physical sample. Keep one approved door sample per wardrobe type on site. Arched doors are made to measure for each project, so the sample is the only reference once production starts.
  • Edge and touch-up policy. Say how cut edges, fixings and any site trimming should be finished, and who carries out touch-up work at handover.

Lock down measurement, tolerance and sequence

Most arched wardrobe problems are site problems that appear as production problems. Sequence and tolerance notes prevent them.

  • Who measures, and when. For built-in wardrobes, final dimensions should be taken after flooring, plastering and painting are complete, with floor level and wall plumb recorded for each unit code.
  • Tolerance allocation. State the maximum out-of-level and out-of-plumb the design absorbs, and who corrects anything beyond it. Arched heads against an uneven ceiling line are where this shows up first.
  • Trade dependencies. Note the dates for electrical first fix inside the wardrobe, skirting removal, air-conditioning grilles and any lighting that the unit has to receive.
  • Packaging, handling and access. Oversized arched doors need lift or stair routes checked in advance. Record the largest single piece by code, plus delivery dock hours.
  • Storage on site. Built-in joinery should stay sealed and off the floor until the room is dry; state this in the programme so other trades do not store wet materials against it.

If a project goes beyond standard made-to-measure wardrobes into arches carried through walls, niches and vanities, that work sits under arched niche and full-house custom wall cabinet projects, where the arch profile is coordinated across joinery, panelling and bathroom counters in one package. In those cases the wardrobe schedule should reference the same drawing set as the panelling, not a separate one.

What to attach to the enquiry

A complete arched-wardrobe enquiry is faster to price and far less likely to come back wrong. Send:

  • A room-by-room schedule: unit code, width, height, depth, arch type, rise and radius, door count and door type.
  • An internal layout drawing per unit, with hanging heights, shelves and drawers dimensioned.
  • A finish schedule with codes, sheen levels and veneer matching rules.
  • Site conditions: measured high and low points, ceiling height, wall material, and any services behind the line.
  • The interface list: cornice, skirting, flooring, lighting, electrical first fix, who does each.
  • Delivery address, access route, and required installation dates by phase.

Our wardrobe collections are made to measure, with material, finish and layout specified per project, so a schedule that carries these six attachments is what allows an arched unit to be quoted accurately the first time. As a built-in furniture range supplied alongside joinery, panelling and bathroom fixtures, these wardrobes are usually ordered as part of a wider package rather than as a standalone line item. Send your schedule through our custom furniture manufacturer service or the contact form, and we will confirm dimensions and selected specifications for each project before production.

Frequently asked questions

Can an arched wardrobe be fitted against a sloping ceiling?

Yes, but the drawing has to show the slope and say whether the arch follows the ceiling or stays level with a scribed filler above. Decide this at survey stage; it changes the door panel.

Are arched doors available as sliding as well as hinged?

Both door types exist in our wardrobe range, but the head detail and track clearance differ, and not every panel profile is offered in both. Confirm the combination for the specific collection before fixing the layout.

How early should the arch geometry be frozen?

Before doors are ordered, and after site measurement. Radii, rise and springing height should be on one approved drawing shared with the panelling and ceiling trades.

What is the most common cause of an arched wardrobe looking wrong on site?

Mismatched radii between the wardrobe head, adjacent niche paneling and arch skirting, or an uneven ceiling line that was never recorded at survey. Both are documentation failures, not manufacturing ones.