A quotation for matte melamine cabinets can look complete and still leave the site work undefined. Panels arrive, the wall is not square, the appliance schedule has changed, and the fitter starts improvising. An installation plan is what sits between the shop drawings and the finished kitchen: it records who measures, who signs off, what has to be ready on site, and how deviations are handled. Below is the checklist we work from on residential and apartment kitchens, whether the cabinetry is one villa kitchen or a repeated unit type across a building.
Why matte finishes reward more planning than most people expect
Melamine door panels in a matte finish are practical and easy to keep clean, but they behave differently from high gloss under site conditions. Gloss reflects light, so small flatness problems in a wall or a slight tilt in a run of wall units read as a highlight; matte diffuses light, which hides those highlights but makes gaps, shadow lines and uneven reveals along the doors far more visible. Handling also matters: finger pressure and adhesive from protective tape can leave marks on a dark matte surface that a gloss panel shrugs off.
That has two practical consequences for the plan. First, setting-out accuracy matters more, because there is nowhere for an uneven reveal to hide. Second, sequencing and protection matter more, because doors and drawer fronts are usually the last items handled and the first things a client inspects up close. Neither point is a fault in the material; it is simply how the finish should be specified and installed.
1. Verified site dimensions and a signed setting-out drawing
Made-to-measure cabinetry only works if the measurements are taken at the right moment and recorded properly. Before production is released, the plan should state:
- who takes the final site dimensions, and at which construction stage (after plaster, screed and waterproofing are complete and dry)
- the datum line used for heights, and how floor levels are recorded across the kitchen footprint, including door thresholds
- plumb and square checks on wall faces, plus measured out-of-plumb and out-of-square values rather than an assumed 90 degrees
- positions of waste, water supply, gas points, sockets and switches, marked and photographed against the datum
- ceiling level and the exact height available for tall units and overhead cabinets
The output is a setting-out drawing with those figures on it, signed by the client or contractor. It becomes the reference for every later decision, including any scribe or filler width that has to absorb a deviation.
2. Appliance schedule and services coordination
Appliance cut-outs are the most common cause of last-minute changes, because the model on the drawings is often not the model delivered. The plan should carry an appliance schedule with the model reference, recess dimensions, door-hinge side, ventilation requirement and connection type for each built-in item: oven, hob, extractor, dishwasher, fridge and washing machine. Where an appliance has not been chosen yet, the plan should record the reserved envelope and the date by which the selection must be confirmed.
Services follow from that schedule. Each item needs its power point, isolator and, where relevant, water inlet and waste located inside the correct carcass zone, with enough clearance for maintenance access. A short coordination note covering these points prevents the two most expensive fixes: a carcass that has to be re-made, or an appliance that cannot be serviced without removing a panel.
3. Storage layout and hardware specified before production
The interior layout is what the client actually lives with, so it belongs in the plan rather than in a conversation on site. The document should show drawer stacks against tall units and corner solutions such as pull-out or carousel fittings, together with hinge type and opening angle, drawer slide rating, soft-close provision, handle or handleless profile, and leg height where a plinth is used. Where matching hardware is supplied with the cabinetry, list hinges, slide rails, support legs and connecting brackets in the same specification so nothing arrives separately.
For projects that repeat a unit type across several apartments, this section is also the standard that keeps kitchens consistent from one floor to the next. If you are specifying a run of custom built-in kitchen cabinets for apartments or a hotel kitchen, the layout and hardware schedule is the part that should be frozen first and referenced by unit number.
4. Site readiness: what must be complete before delivery
Cabinetry should not arrive on a site that is still wet or dusty. The plan lists the prerequisites with a responsible party and a date against each one:
| Readiness item | Why it matters for matte melamine |
|---|---|
| Wet trades finished, screed and plaster fully dry | Melamine panels must not be stored or fitted against damp surfaces; moisture affects both the boards and the adhesives and fixings used on site |
| First fix services tested and pressure-tested | Any wall opening after fitting risks damaging panels and adjacent units |
| Floor levels, thresholds and screed heights confirmed | Determines leg height, plinth height and door drops; a late change alters every tall unit |
| Paint or wall finish schedule agreed for the cabinetry interface | Decides whether scribing is done before or after decoration, and who protects which edge |
| Clean, dry, covered storage with safe access to the kitchen | Packaged panels stacked in a wet or high-traffic area is the usual source of damaged goods claims |
| Other trades off the kitchen zone during fitting | Plasterers, electricians and painters working around fitted units cause most handling marks on matte doors |
5. Delivery route, unpacking and protection
For apartments and upper-floor villas the delivery route is part of the plan, not an afterthought: lift dimensions, stair widths, corridor turns and door clearances should be checked against the packed sizes of tall carcasses and long worktop blanks. The plan should state that panels are stored flat and dry, kept in original packaging until fitting, and that matte door and drawer panels are fitted with protective film left on until handover where the site is still busy.
Where cabinetry ships internationally, the plan also needs to record who handles customs clearance and who receives at the destination, how cartons are labelled against unit numbers or room codes, and how damage is documented on the day of receipt. Photographs of packaging before opening, taken against carton labels, turn a disputed claim into a simple replacement of specific panels.
6. Installation sequence and tolerance rules
A written sequence removes most arguments on site. A typical order for a matte melamine kitchen:
- Set the base run level using adjustable legs, checking against the recorded floor datum rather than the visible floor edge
- Level and fix wall units to solid fixing points, with a checked height line across the whole run
- Install tall units and end panels, then worktops, then scribes and filler panels cut to the actual wall
- Hang doors and drawer fronts last, then adjust reveals uniformly across the run
- Fit plinths, trims and internal accessories, then remove protective film and clean
The plan should also fix the tolerance rules in advance: the maximum scribe width allowed at a wall junction, how an out-of-plumb wall is resolved (scribe rather than pack-and-force), whether a filler panel or a rebated trim is used next to appliances, and what happens when a measured deviation exceeds what the shop drawing assumed. Where a deviation cannot be absorbed within those rules, work stops and the drawing is revised.
7. Inspection, snag list and handover
The final section of the plan defines how the installation is accepted. For this finish we check door alignment and reveal consistency under the room's own lighting, with the lights that will actually be used at night, because that is when uneven reveals become obvious on a matte surface. The snag list covers:
- door and drawer fronts aligned, with even gaps and no rub at the opening arc
- hinges, slides and soft-close devices operating smoothly through full travel
- worktop joints sealed, splashback interface clean, no visible fixings
- scribes and fillers tight to the wall with no daylight gap
- surfaces free of handling marks, adhesive residue and dust after final cleaning
- spare panels, hinges and slides handed over against the same references used in the specification
Handover is complete when the snag list is closed and the as-built setting-out record matches what was installed. For multi-unit projects, one approved sample kitchen signed off before volume production is fitted out saves far more than it costs.
How a manufacturer's project team supports this
Because our cabinetry is made to measure, the installation plan starts at quotation stage rather than on site. Layout and finish are confirmed against the site dimensions we work to, hardware and supporting components are listed in the same specification, and cartons are labelled so that a fitter can match each component to its room or unit reference. Our installation and after-sales support covers site guidance, inspection and snagging, with replacement panels supplied against the original specification if something is damaged in transit or on site.
If you are planning a kitchen package for a villa renovation or an apartment development, send us the drawings and the appliance schedule along with your room dimensions. We will return a layout proposal, a finish and hardware specification, and the setting-out checklist that your site team needs to complete before delivery.
Frequently asked questions
When should final site dimensions be taken for melamine cabinets?
After all wet trades are finished and the screed, plaster and waterproofing are dry, and after floor levels and thresholds are fixed. Taking dimensions earlier means the deviations are absorbed by wider fillers on site.
Do matte melamine doors need different handling from gloss ones?
Yes, in two respects: keep protective film on until the room is otherwise finished, and avoid pressing or wiping the face with adhesive tape or solvent cleaners. Matte surfaces also show uneven reveals more readily, so door adjustment at the end of installation is worth the extra time.
What should be confirmed before production starts?
The signed setting-out drawing, the appliance schedule with recess sizes and hinge sides, the internal storage layout, the hardware list, and the wall finish detail at every cabinet interface. Anything left open at that point becomes a site decision.