A flush hinged door only looks right when the wall, frame and hardware are agreed before anything is cut on site. When we prepare Santerson Flush Hinged Doors for a villa or apartment package, the drawings, opening preparation and finish schedule travel with the doors so the fitter on site is not improvising. Below is the installation plan we ask project teams to sign off, item by item.
1. A door schedule for every opening
Before production starts, list each door by room and reference number, and record for every one of them:
- Clear opening width and height, plus the finished floor level so heights are read from a fixed datum, not from a slab that has not been screeded yet.
- Wall build-up: substrate type, stud or masonry construction, total wall thickness and whether the wall will receive paint, veneer panelling or tile.
- Leaf size, swing direction and which hand the hinges sit on, drawn on the plan rather than described in an email.
- Lock, handle and hinge selection, including whether the project calls for a wood veneer hinged door leaf or a plain painted surface.
- Sign-off name and date, so late changes are visible as changes.
Our doors are made to measure, with material and finish chosen per project, so this schedule is the document production works from. Anything added after it is confirmed usually means re-cut openings on site.
2. Opening preparation agreed with the builder
Flush detailing fails when the opening is treated as a finished dimension too early. In the plan we set out who prepares what, and to which tolerance:
| Item to fix in the plan | Why it matters on site |
|---|---|
| Who frames the opening and with what | The surrounding structure has to carry the frame and stay square through the wall build-up. |
| Finished floor level and threshold line | Undercut and leaf height are set from this line; screed and topping change it. |
| Wall face line and finish thickness | The leaf sits proud or recessed depending on the final wall face, so panelling and tile thickness must be known. |
| Set-out sequence with skirting, cornice and panels | Where doors meet integrated door and panelling, the reveal is decided once for both trades. |
| Storage and handling on site | Leaves delivered early need a dry, flat store away from wet trades, or the plan has created its own damage. |
3. Hardware and ironmongery list
Hinges, locks and handles decide how much of the leaf edge is machined, so they belong in the plan and not in a purchase order placed later. For each door type we confirm hinge count and positions, lock case format, strike plates, door closer or magnetic holder if specified, and the finish of each item against the handle and ironmongery schedule. Where a project uses concealed or minimal-edge detailing, such as handleless concealed doors, we check the chosen hardware against the leaf thickness and the wall build-up before machining.
4. Finish schedule and sample approval
A flush door is judged on its surface, so the plan carries an approved finish reference: paint colour and sheen, laminate or lacquer, veneer species and grain direction, and how the door face relates to adjoining wall panels and joinery. We ask for sample approval before batch production, because a flush leaf that reads slightly different from the panelling beside it is the most visible defect in a finished room.
5. Delivery sequence and site logistics
Doors arrive with the rest of the fit-out package, and the plan says when. We arrange freight by sea, air or rail with the paperwork handled, and door-to-door delivery to site. For a flush door set, delivery timing matters more than for loose furniture: leaves installed before painting, flooring and site cleaning get damaged, while leaves delivered after those trades stall the programme. The plan fixes a delivery window that sits between first fix and decoration.
6. Installation method statement
The written method we agree with the site team covers:
- Frame fixing to the prepared opening, checked for plumb, line and twist before the fixings are final.
- Leaf hanging, with an even reveal on all four edges and a consistent gap to the finished floor.
- Lock and handle machining carried out in a controlled sequence, not free-handed on site.
- Protection of the leaf and frame while other trades finish the room.
- A snag list per door: sticking edges, misaligned strikes, marks to touch up, signed off with the contractor.
Our team provides on-site installation support, inspection and snagging, plus spare parts and maintenance guidance after handover through installation and after-sales support.
7. Responsibilities, dates and sign-off
The last page of the plan is a simple responsibility matrix: supplier prepares and delivers doors and frames to the approved schedule; builder prepares openings, levels and wall faces; both parties attend one set-out meeting before production release and one inspection before handover. Dates for drawing approval, production release, shipment and installation sit on the same sheet, so a slip in opening preparation is visible while there is still time to act.