A set of Textured Lacquer Cabinets leaves the factory long before it reaches your kitchen. What decides whether the job ends well is not the lacquer line but the paperwork, packaging and site preparation you settle two or three months earlier. This guide walks through the sequence we follow for made-to-measure cabinet orders shipped overseas, and lists exactly what your team needs to have ready at each stage.
What makes a textured lacquer order different to ship
Our textured lacquer cabinets are made-to-measure: sizing, layout, substrate and finish are specified per project rather than picked from stock dimensions. That single fact shapes the whole delivery plan. There is no replacement panel sitting in a warehouse if a container is delayed or a door is damaged in transit, so the order has to be produced once, correctly, and protected properly on the way.
Lacquered door fronts also behave differently from foil-wrapped or laminated panels in transit. The surface is finished before assembly, so handling marks, moisture trapped in packing and pressure between panels are the three problems we design around. Panels travel separated by protective interleaves, edge protectors and rigid corner battens, banded to pallets rather than loose-stacked, and the cartons stay sealed until the fitter opens them on site.
Step 1: Lock the specification before production starts
Because everything is cut to your drawings, an error found after lacquering cannot be touched out. Before we release the order to the floor, we ask for written confirmation of:
- Final shop drawings with every cabinet module numbered and dimensioned, including toe-kick, scribe and filler panels that are easy to leave off a layout.
- Appliance schedule — oven, hob, dishwasher, fridge and any integrated units — with model numbers and cut-out sizes.
- Door style and finish reference from the lacquer range: matte lacquer, high gloss lacquer, metallic lacquer or shaker lacquer, with the colour sample you approved quoted by code.
- Hinges, runners, handles and any integrated lighting, listed item by item so nothing is sourced separately later.
Step 2: Decide the Incoterms and who does what
The delivery model you choose determines where our responsibility ends and yours begins. Our logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, customs documentation, container loading and tracking through to the site.
| Delivery model | What we handle | What your side handles |
|---|---|---|
| Door-to-door (DDP-style) | Factory packing, ocean or rail freight, export clearance, import clearance support, duty and tax arrangement, last-mile delivery to the site address | Receiving at the address, storage, and installation labour unless booked separately |
| Port-to-port / CIF | Factory packing, ocean freight and marine insurance to the discharge port, shipping documents | Customs broker, import duty and GST, inland haulage to site |
| FOB / EXW | Packing, loading or handover per the agreed term, commercial documents | Freight booking from origin, insurance, clearance, inland transport |
For a single kitchen consignment, door-to-door keeps accountability with one party. For a multi-unit development where your freight forwarder already consolidates several suppliers, FOB or CIF usually costs less — provided the broker on your side knows how to describe cabinetry and hardware on the entry.
Step 3: Budget landed cost, not just the cabinet price
Buyers who quote a project on the ex-factory number alone are consistently surprised by the tail. Build the budget from:
- Cabinetry and hardware value, plus packing and palletisation.
- Ocean freight and insurance. Sea is standard for full sets; air only makes sense for a small replacement door or a late hardware order.
- Import duty, consumption tax or GST on the customs value, calculated on the goods plus freight and insurance in most jurisdictions.
- Broker fee, port and terminal charges, container detention if the site is not ready to receive.
- Inland delivery — a 40-foot high cube will not reverse into a narrow residential street, so confirm truck size and access with your carrier.
Ask us for the packing list before you book anything. Cube and pallet count drive the container choice, and a well-planned set of cabinet cartons often fits a 20-foot container where a poorly planned one needs a 40-foot.
Step 4: Get the documents right
Customs delays on cabinetry are almost always document problems, not cargo problems. Every shipment we send travels with a commercial invoice, packing list and bill of lading; where your import authority requires them, we also prepare a certificate of origin and any import permit paperwork requested by your broker.
- Make sure the packing list marks each carton with the module number that matches your shop drawings, so the fitter can find door 14 without unpacking everything.
- Have your broker confirm the tariff classification and declared value method before the vessel sails, not after arrival.
- If the order is split into two consignments — carcasses first, lacquered doors second — say so on both documents, with cross-references between them.
Step 5: Prepare the site for the day the container arrives
Made-to-measure cabinetry assumes the building is ready. Before delivery, confirm on site:
- Floors level and at finished height, walls plastered and squared, and the floor plan dimensionally re-checked against the drawings we worked to.
- Wet services, electrical runs and appliance positions where the drawings show them, with the first-fix locations signed off.
- A dry, covered storage area where unopened cartons can sit at stable room temperature until installation begins. Lacquered fronts should not be stacked against a wall or laid flat on a concrete slab.
- Delivery access and lift dimensions for the longest cartons, especially for apartments.
Our installation and after-sales support service covers on-site fitting, inspection and snag resolution, with spare parts supplied for any panel that needs replacing. Where your own joiner installs the set, send us the site re-measure before production and photographs at handover, and we will support alignment issues remotely.
Step 6: Inspect on arrival, then report quickly
Open cartons in order of delivery date and check each door front against the finish sample under site lighting. Photograph any transit damage with the carton label and module number visible, and send the photos with the packing list line reference. Claims need the packaging evidence, so do not discard interleaves or battens until the inspection is signed off.
A practical timeline to work backwards from
| Milestone | What has to be settled |
|---|---|
| Before order | Drawings, appliance schedule, finish sample approved by code, delivery term agreed |
| Production | Purchase of substrate and hardware, lacquering and curing, assembly check, packing plan |
| Before shipping | Booking confirmed, documents drafted, broker briefed on classification and value |
| In transit | Site completed to the point where cartons can be stored dry and installation can start on arrival |
| On arrival | Inspection against packing list, damage report if any, then installation and snag list |
Set your site completion date after the container's projected arrival, not before it. Empty storage costs less than a demurrage charge and a joiner standing idle.
Bringing it together
International delivery of made-to-measure cabinetry is a coordination job with five fixed points: a specification nobody changes, a delivery term both sides understand, a landed-cost budget that includes tax and inland haulage, documents your broker can clear without queries, and a site ready to receive. Handle those and the lacquered doors arrive as they left the factory.