Hidden cabinets only look simple. A run of flush panels on a wall reads as clean architecture, but behind those panels sit carcasses, doors that must swing or slide without fouling each other, hardware rated for the load, and services that have to stay reachable. When we quote hidden cabinets for a villa or apartment package, the work that prevents rework on site is rarely the design drawing itself — it is the quantity take-off and the coordination list that come with it. This guide walks through both, in the order we use them on real projects.
Count modules, not wall lengths
The most common quantity error is pricing a storage wall by its length. A long storage wall can resolve into two tall wardrobes and a niche, or into many narrow units with different doors, and the price, freight volume and installation crew differ completely. Break every run into modules first: each closed box, each drawer stack, each open display niche, each tall larder and each panel-only bay. Then record for each module its width, height, depth, door type and opening direction.
- Give every module a unique tag on the drawing, and use that same tag on the quotation, packing list and site plan.
- State which modules are full-height and which stop below the ceiling; scribes and filler panels are separate line items, not part of the cabinet width.
- List cut-outs — ovens, fridges, TV recesses, mirrors, basins — against the module that carries them, with the equipment dimension you were given at the time.
Order to measured sizes, and re-measure before production
Our custom built-in kitchen cabinets and storage-wall ranges are made to measure, with panel material, finish and layout set per project. That flexibility is the point, but it means a dimension copied from an architectural drawing is only a starting figure. Walls are rarely square, ceilings fall away slightly along their length, and skirting, cornice, floor build-up and door reveals all consume tolerance.
Take site dimensions after the wet trades, floor finish and plasterboard are complete. Where that is not possible, agree in writing which gaps will be closed with scribes and which require a revised order. For multi-unit runs, note the finished floor level at each end of the wall — an uneven floor along the run changes every door alignment.
Coordinate the products that sit inside and behind the panels
A hidden cabinet is really an assembly of separately sourced parts. Each item below has its own lead time, and each one fixes a dimension you cannot change later without changing the carcass.
| Element to coordinate | What must be agreed before production |
|---|---|
| Doors and opening hardware | Hinged, sliding, bi-fold or push-to-open; clearance in front of the door; whether two doors meet at a mullion and which one opens first. |
| Drawers and internal fittings | Runner type and load rating, drawer depths per stack, pull-out trays, hampers and dividers — these set internal clear heights. |
| Integrated lighting | Recessed channels, transformer position and a service access point for integrated cabinet lighting, plus the switch or sensor location. |
| Appliances and equipment | Model dimensions, required ventilation gap, the appliance door swing, and how the unit is released for replacement. |
| Adjacent finishes | How the cabinet meets wood panel partitions, wall panelling, flooring and architraves, and which trade installs first. |
| Matching doors and wardrobes | Where a hidden wardrobe shares a wall with an integrated door and panelling run, the panel batch, grain direction and finish must come from one order. |
Where a wall mixes open and closed fronts — a common pattern for living-room storage walls — decide the open-to-closed ratio per module rather than for the wall as a whole. Open niches need their own back panel detail and, if lit, their own wiring route; closed modules need their hinges and runners scheduled.
Add up quantities in a way purchasing can check
Once the module list exists, group it so that the purchase order mirrors how the goods arrive and how the crew works:
- Carcasses and panels by room or by wall, with the panel area recorded for each finish. Panels from one batch keep colour and grain consistent, so avoid splitting a single wall across two production lots.
- Hardware by type and quantity, including spares: hinges, runners, handles or profile pulls, legs, brackets and fixings. Order spare hardware with the main consignment; a matching runner is not always available later.
- Consumables that are easy to forget: scribes, filler panels, edge trim, sealant, shims and protective padding for transport.
- Installation units per site, with the working days implied by the module count, so the trades on site — electrician, plasterer, floorer — are booked against the same schedule.
Check the coordination list before you release production
Release nothing to the factory until every item on this list is signed off: final site dimensions; appliance and equipment models; door type and opening direction per module; internal fitting schedule; lighting circuit and transformer positions; finish code and panel batch; delivery address, access route and lift or stair constraints; installation sequence agreed with the other trades.
That single sign-off is what keeps a hidden cabinet run invisible in the right sense. The panels line up, the doors clear each other, and the wiring behind them can still be reached years later. If you are assembling a package for a villa or apartment project — cabinetry together with wall mounted cabinets, wardrobes and other interior fixtures — send us the drawings and the module list, and we will price it room by room, then handle production, packing and delivery to site.