A cabinet quotation is where a kitchen project either gets controlled or quietly drifts. Two suppliers can look identical on a spec sheet and still produce very different costs once sizing, hardware, packaging and freight are priced differently. The checklist below is written for buyers comparing a quote for matte pvc cabinets, but the same line-by-line reading applies to any made-to-measure cabinetry package.

1. Scope: what is actually inside the number

Start by asking which pieces are included in the quoted amount and which are extras. A cabinet price that excludes carcass, doors, kick boards, scribes, handles or internal fittings is not comparable to an all-in price. Write down the room list as it appears on the drawing, then match every item to a priced line.

  • Linear metres or item count of base units, wall units and tall units
  • Carcass material and door material stated separately
  • Whether worktops, splashbacks and trims are quoted at all
  • Internal items: shelves, drawers, baskets, corner mechanisms
  • Items deliberately excluded, stated in writing rather than assumed

2. Sizing basis: made-to-measure or modular

Cabinetry for a real room rarely fits standard modules exactly. Our matte pvc cabinets are produced as made-to-measure units, so the quote should reflect your drawing rather than a catalogue grid. When reading any quotation, confirm three things: whose drawing is being priced, whether dimensions are finished or structural, and how uneven walls, skirting, pipes and ceiling lines are handled.

Ask for the dimensioned elevation drawing that the price refers to, and check that it carries the same revision number as the drawing you sent back. A quote priced from an earlier revision is the most common cause of a mid-project cost change.

3. Finish and substrate: read them as two separate items

A PVC-wrapped door is a surface system on a board core, so both parts deserve their own line in the quotation. For matte finishes specifically, ask what the door face and edges are wrapped with, how the edge banding meets the wrap on a mitred or rounded profile, and which direction the grain runs on doors that sit side by side. If you are also considering a timber look, request the wood grain pvc cabinet option in the same quote so the two finishes are priced on identical carcasses and hardware.

Line to confirmWhy it changes the price
Door face material and wrap typeFilm quality and wrap method drive both cost and how the matte surface wears at edges
Edge treatment on profiled doorsMitred and continuous-wrap edges take more labour than straight banding
Carcass board and thicknessThicker carcass boards and matched colours raise material cost per unit
Colour or grain reference codeNamed references prevent substitutions between sample and production
Reveal and shadow-gap detailTight gaps need adjusted doors, which is fitting time on site

4. Hardware: brand, model and what is not quoted

Hardware is where a low headline price usually reappears later. Ask for hinge and slide brand plus model reference, not just "soft close". Check whether the quote includes handles or integrated profiles, drawer fronts versus drawer boxes, door dampers, and any light fittings cut into shelves. Where a quotation lists hardware generically, request a priced alternative so you can see the difference rather than accept one option.

5. Samples before you sign

Ask what physical evidence comes with the price: a door sample in the exact finish and grain direction, a carcass corner sample showing board edge and bore holes, and a hardware sample if the handles are being supplied by the cabinet maker. A door photographed on a rendered kitchen is not the same as a sample you can hold under site lighting, and matte surfaces in particular shift in appearance depending on the light in the room.

6. Packaging, freight and delivery terms

For imported cabinetry the ex-factory price tells you very little. Read the quotation for the Incoterm it is priced on, the packaging standard per unit, whether doors travel loose or assembled, and how tall units are protected. A supplier quoting logistics and door-to-door delivery should show freight as a separate figure so you can compare landed cost against your own forwarder rather than guessing.

  • Incoterm stated on the quotation, not agreed verbally later
  • Packaging list with carton count, dimensions and total volume in cubic metres
  • Whether glass, mirrors and worktops ship separately from carcasses
  • Consolidation with other trade packages, if you are buying more than cabinets

7. Lead time, milestones and what restarts the clock

Ask which event starts production: signed drawings, paid deposit, or approved samples. Then ask what happens if a wall dimension moves after that point. A useful quotation states the production window, the drawing-approval cut-off, and how late changes are handled. This matters most on kitchens where tiling and flooring set the final dimensions.

8. Payment terms and change control

Confirm the deposit percentage, what triggers the balance, and whether payment follows shipment or delivery. Then look for a change-order clause: how a variation is priced, who signs it, and whether removed items are credited at the quoted rate. A quotation with no change mechanism usually means every adjustment becomes an argument.

9. Installation responsibility

Decide before you compare quotes who fits the kitchen. If the supplier provides fitting, check whether it is their own team or a local crew, and what snag handling looks like after installation. If you are using your own installer, ask for assembly instructions, a full parts list with unit codes on each carton, and hardware pre-drilled to drawing. Both options are priced differently, so request the version that matches your site plan.

10. How we quote cabinetry

SANTERSON is a China-based manufacturer supplying furniture and building materials for residential, villa and hospitality projects, operating since 2008. Cabinet quotations are prepared from your drawing, with made-to-measure sizing, selectable material and finish options, and a layout set to the project rather than a fixed module range. That means the quote you receive from us lists carcass, doors, finish reference and hardware explicitly, so two configurations can be compared honestly instead of on a single averaged rate.

Because kitchens are usually only one part of a fit-out, buyers often ask us to price cabinetry alongside other rooms in the same custom and OEM service order — wardrobes, doors and flooring included — so the package is quoted on one set of dimensions and one delivery plan. One combined quotation removes the gap between trade packages, where costs tend to appear.

A pre-signature checklist

  • Drawing revision number on the quote matches the drawing you approved
  • Inclusions and exclusions listed, not implied
  • Door finish and carcass board priced as separate lines with reference codes
  • Hinge and slide brand plus model reference stated
  • Physical samples confirmed before production release
  • Incoterm, carton list and cubic-metre total shown
  • Production start event and drawing cut-off written down
  • Change-order pricing method agreed in advance
  • Fitting responsibility named on the quotation