A glass-front bar cabinet looks simple on a drawing. It is one door, a few shelves, some glass. In a real project it sits inside joinery that has to be measured, finished, glazed, lit, packed and installed alongside everything else. This article shows how procurement teams and design leads can carry Santerson Glass Front Bar Cabinets through a whole-project materials schedule, so the item arrives with the rest of the fit-out instead of becoming a late variation.
What a bar cabinet actually needs from a materials schedule
In our catalogue, glass-front bar cabinets sit under built-in furniture, in the Bar Cabinets group. The listed configuration options are made-to-measure sizing, material and finish choices, and layouts tailored to the project. That flexibility is useful on site and awkward on paper: a made-to-measure item cannot be ordered off a category name alone.
A single bar unit touches several other lines in a schedule. The carcass has to match the finish of adjacent kitchen or dining cabinetry. Glass needs a type, thickness and safety treatment agreed with the specifier. Interior lighting, if shown, pulls in an electrical line, a driver location and a maintenance access. Benchtop or wall panelling that the cabinet abuts must be dimensioned so the reveal is consistent. If any of those dependencies are left implicit, the cabinet is delivered as a box that does not fit the hole made for it.
Step 1: place the item in a trade package, not on a shopping list
The first decision is which package the bar cabinets belong to. Where joinery, panelling, doors and wardrobes come from one supplier, keep the bar cabinet inside that joinery package rather than treating it as loose furniture. Built-in units share carcass construction, edge banding, door profiles and finish batches with the cabinetry around them; ordering them separately usually means two slightly different whites or two different oak tones in the same room.
For a villa or hospitality project we work from whole-space schemes rather than individual items. The same applies to scheduling: group by trade interface, then let one supplier carry the interface risk between the parts that meet each other.
Step 2: set the schedule fields before you request a quotation
Most delays on built-in items come from incomplete schedule rows, not slow factories. Before sending an enquiry, fill in every field below for each unit type.
| Schedule field | What to record | Why it delays the job if left blank |
|---|---|---|
| Item code and location | Unique code per unit, plus room and wall reference from the drawing | Identical units in different rooms get mixed up at packing and on installation day |
| Opening dimensions and tolerance | Height, width, depth taken from site survey, with finish-floor level noted | Made-to-measure carcasses cannot be corrected on site the way loose furniture can |
| Door style and glass type | Frame material, glass colour and texture, handle or push mechanism | Glass is cut to size; a late change restarts the glazing line |
| Finish reference | Named finish batch matched to adjoining cabinetry and panelling | Separate batches produce visible tone differences under site lighting |
| Interior lighting | Driver position, cable route, switching, spare access | The electrical package will not return to a closed cabinet to add a feed |
| Internal layout | Shelf heights, glass versus solid shelves, provision for appliances or decanters | Drilling and rebating are done in production, not afterwards |
| Order of work and install date | Which trades must finish first: flooring, plaster, electrical, benchtop | Units delivered into an unfinished room get damaged or stored and lost |
| Delivery route and packaging | Container share, crate type for glass, delivery point on site | Glass-front units shipped loose arrive with broken doors and a replacement order |
Step 3: align the bar cabinet with adjoining lines
Once each row is complete, check the interfaces. Three checks catch most problems:
- Finish continuity. Confirm the bar cabinet door finish is specified from the same source as the kitchen or dining cabinetry it stands next to. Where a project also uses Santerson Integrated Bar Systems elsewhere, specify both against one finish schedule so the joinery reads as one design.
- Reveal and alignment. Record the reveal between the cabinet frame and wall panelling or door linings. If panelling is on a separate line, both suppliers need the same wall build-up dimension.
- Services. Anything lit, cooled or switched inside a cabinet needs its feed, control and access confirmed before production drawings are signed off.
Step 4: sequence production, packing and delivery
In our process the schedule drives production directly: design consultation and space planning, material selection and product specification, then manufacturing with quality control, project management and site coordination, and finally installation and handover. For glass-front units we add two practical notes.
First, batch the glazing. Doors for several units ordered together are cut in one run, which keeps glass tone consistent across the job. Second, pack for the route. Our logistics scope covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery. Glass-front doors travel crated and separated from carcasses; the packing list should show crates and carcasses against the same item codes so the site team can reconcile the delivery against the schedule line by line.
For projects outside the country of manufacture, put the bar cabinets in the joinery container rather than a later furniture consignment. A missing cabinet door stops handover; a missing sofa does not.
Step 5: verify on site and close the line
Install after flooring, painting and first-fix electrical are complete. Check against the schedule row, not the drawing: opening size, door operation, glass condition, lighting function, finish match under actual site lighting. Our installation scope covers on-site installation, inspection and snags, spare parts and replacement, and ongoing maintenance. Record any snag against the item code so it can be traced to the production record.
Only mark the schedule line closed when the door closes squarely on the reveal agreed in Step 3. That single check prevents most of the variation claims that follow joinery work.
Schedule template, ready to fill
Item code | Room and wall reference | Surveyed H/W/D and FFL | Door profile and frame material | Glass type, colour and thickness | Finish reference and batch | Interior layout and shelf heights | Lighting feed and driver position | Adjacent trades and reveals | Required on-site date | Container and crate plan | Snag and sign-off column
Common questions from procurement teams
Should glass-front bar cabinets be ordered with the kitchen cabinetry?
Yes, when they abut it. Same finish batch, same production window, one set of production drawings to approve.
When should dimensions be frozen?
After the floor finish level and wall build-up are fixed on site. Made-to-measure sizing is a listed configuration option, but it only helps if the measurement is taken from a built condition rather than a design dimension.
What details should the enquiry include to avoid a second round?
The completed schedule row, the drawing extract showing the location and adjoining finishes, and the lighting arrangement. Confirm dimensions, materials, finishes and hardware for each project before production starts; product pages give the range of options, not the fixed specification for your job.
Putting it together
A glass-front bar cabinet is a small item that exposes weak scheduling. Treat it as joinery, specify it against the finishes around it, resolve its lighting and reveals before production drawings, and ship it with the cabinetry. Do that and it arrives on the same truck as the rest of the fit-out and installs in an afternoon.