A materials schedule that works on site is one every line item can be traced back to: same reference, same finish code, same supplier, same trade package. Mirror cabinets sit awkwardly in that system. They are small, they hang on a wall above a basin, and their electrical and storage details are decided long before anyone looks at the bathroom schedule. This article shows how to carry the Santerson LED Mirror Cabinet through a whole-project materials schedule — from line-item structure and finish coordination to electrical interfaces, delivery sequencing and handover.
Why mirror cabinets break schedules
In most fit-out packages the mirror cabinet is treated as an accessory: added late, priced roughly, and fixed on site. Three problems follow from that habit.
- The item changes after pricing. Once a bathroom schedule carries a generic "mirror cabinet with light" line, substitutions arrive at order stage — different width, different door direction, different light output — and the priced package no longer matches what is being installed.
- Electrical work is set before the item is chosen. Wall outlets, isolators and connection points are usually built out from first-fix drawings. If the mirror unit's connection position and switching arrangement are not fixed at that stage, electricians end up chasing a new outlet or leaving a visible cable.
- The cabinet competes with other trades for the same wall. Vanity tapware, wall lights, towel rails, tile set-out and any recessed niche all share one small area. Whoever gets to the drawing first wins, and mirror cabinets are rarely first.
Because our mirror cabinets are made to measure rather than stocked in fixed sizes, none of these three problems can be solved by picking a catalogue code. They are solved on paper, in the schedule itself.
Step 1 — Set one line-item format and keep it identical everywhere
Write the mirror cabinet entry so that the same string of information repeats across the bill of quantities, the door schedule, the purchase order and the packing list. A practical format for a residential or hospitality bathroom package:
| Schedule field | What it must record |
|---|---|
| Item code | Project prefix plus room type, e.g. BR-MC-01 for the principal bathroom, so the same code appears on drawings, orders and cartons. |
| Product reference | The exact catalogue name used on our site — LED Mirror Cabinet, Tall, Round or Standard — not a generic description. |
| Made-to-measure size | Width, height and projection, plus the ceiling, mirror-centre and finished-floor datums each dimension is taken from. |
| Body and door finish | Material and finish code, matched to the cabinetry schedule rather than described in free text. |
| Glass and shelving | Mirror or glass door type, shelf count and shelf positions where storage layout matters. |
| Lighting | Integrated lighting arrangement, switching method and the electrical specification to be confirmed for that project. |
| Mounting | Wall build-up, fixing method and any reinforcement or blocking inside the wall. |
| Quantity and location | Room-by-room quantities, never one lump figure for "bathrooms". |
The point of a fixed format is auditability. When the same eight fields appear on the order and on the carton label, a site supervisor can check a delivery against the schedule without opening a single box.
Step 2 — Coordinate finishes with cabinetry and wall surfaces
Our Santerson Tall Mirror Cabinet, the round variant and the Standard Mirror Cabinet are all listed with made-to-measure sizing and material and finish options. That flexibility is useful only if the schedule states which cabinetry line the cabinet must match.
Practically, that means three cross-references in the schedule:
- Vanity match. Where the mirror cabinet sits above a Santerson Floating Vanity, record the vanity item code in the mirror line so both are ordered from the same body finish and the same production batch.
- Wall surface match. Note the tile or panel product on that wall, because the cabinet's reveal and shadow gap read differently against a large-format slab than against small mosaic.
- Lighting match. Where the design also specifies Vanity Lighting, decide in the schedule whether the room is lit by the integrated cabinet lighting or by separate sconces. Two light sources at mirror height, both uncoordinated, produce competing reflections.
Where a project needs more than one bathroom type, group items by bathroom type rather than by floor. A three-apartment villa with two identical secondary bathrooms should carry one secondary-bathroom line repeated in quantity, not three separately described lines.
Step 3 — Lock the electrical interface before first fix
The LED Mirror Cabinet page describes a configurable unit for residential bathroom projects, with finish, layout and dimensions specified per space; lighting and electrical specifications are to be confirmed for each project. That is exactly how it should appear in the schedule: one line stating that the electrical specification is project-confirmed, with a signature date.
Before first-fix drawings are issued, confirm and record:
- Connection position relative to the finished floor and to the mirror centre line;
- Switching arrangement — wall switch, touch, or switching shared with the room lighting circuit;
- Whether a socket is required inside or beside the cabinet for shavers or toothbrush charging;
- Driver or transformer location, and whether it must stay accessible after installation;
- The zone the unit is installed in and the electrical details required for that zone.
Schedule discipline that actually saves money: freeze the electrical interface line before the wall is closed up, not before the cabinet is ordered. Ordering can be revised; a chased-out wall cannot.
Step 4 — Sequence delivery by bathroom, not by trade
Mirror cabinets arrive with glass and are installed late, which makes them a classic source of damage when they land on site weeks early. In the procurement section of the schedule, group these items into a final-fix bathroom package delivered room by room:
| Package | Contents | Site timing |
|---|---|---|
| First fix | Reinforcement and blocking for wall-hung items, concealed cisterns, valve positions | Before wall closure |
| Wet goods | Ceramic basins, WC suites from the Bathroom Sanitary Fixtures range, shower set valves | After tiling, before final cleaning |
| Joinery and mirror package | Vanity units, mirror cabinets, tall storage cabinets | Last, room by room, with protective packing |
Because our logistics service covers freight forwarding, packaging and container loading, and door-to-door delivery, the same package grouping can be used on the packing list. Cartons marked with the item code from Step 1 arrive at the right apartment and go straight up, instead of sitting in a store room where glass gets broken.
Step 5 — Carry the schedule through to handover
At practical completion the materials schedule should convert directly into the owner's maintenance document. For each mirror cabinet line, the handover record needs: item code, final dimensions as built, finish code, lighting specification as supplied, spare key or hardware reference, and the cleaning method for the mirror and body surface. Where our installation and after-sales service is used — on-site installation, inspection and snags, warranty coverage and spare parts — the same codes should appear on snag lists and replacement requests, so a follow-up order references an existing line rather than starting a new description.
A worked example: three bathrooms, one villa
Principal bathroom: BR-MC-01, LED Mirror Cabinet, width matched to the floating vanity below, body finish copied from the vanity line, integrated lighting on a shared room-lighting circuit, connection set out at the datum shown on drawing E-02.
Secondary bathrooms ×2: SEC-MC-01, same product reference and same finish code as BR-MC-01 but a narrower made-to-measure width, identical electrical arrangement, ordered as one line with quantity two.
Guest powder room: GST-MC-01, a smaller mirror cabinet with no storage requirement, lighting by separate sconce because the wall is narrow. Three lines total, each traceable, each with its own delivery window.
Common errors to avoid
- Describing the item as "mirror cabinet with LED" in a bill of quantities — no finish, no size datum, no electrical interface, and therefore an open substitution risk.
- Specifying made-to-measure dimensions from structural rather than finished floor levels, so the unit lands off-centre against a tiled wall.
- Ordering mirror cabinets in the joinery drop without checking that the tiling is complete and the electrical outlet is where the drawing says it is.
- Listing one lighting line for the whole bathroom when both integrated cabinet lighting and separate vanity lights are on the drawings.
FAQ
Can mirror cabinets be ordered in one batch with kitchen cabinetry?
They can be manufactured together, but the schedule should still show them as a separate final-fix package. Kitchen joinery goes in early; bathroom mirror cabinets go in last to protect the glass and mirrors.
How many dimension datums do I need for a made-to-measure unit?
Three at minimum: finished floor level, finished wall face, and the mirror centre line. Anything specified without those three will be re-measured on site.
Who confirms the electrical specification for the LED version?
It is confirmed per project with our team before first-fix drawings are frozen, and the confirmation date belongs in the schedule line so the whole team can see whether the interface is fixed or still open.
Send us your bathroom schedule
If you are compiling a materials schedule for a villa, apartment or hospitality project, send the bathroom lines and we will return item codes, made-to-measure dimensions, finish references and the electrical details to lock before first fix. Part of our One-stop Furniture and Building Materials Supplier service for project procurement.