A textured lacquer kitchen is only as good as the wall it hangs on. The finish itself — a made-to-measure door with a tactile, low-sheen surface that hides fingerprints and catches light differently across each panel — is produced in the factory. Everything else, from the level of your floors to the sequence in which units are craned into an apartment, is decided on site. That is why serious buyers ask for an installation plan before they sign a purchase order, not after the crates arrive.

Below is what a complete Textured Lacquer Cabinets installation plan should contain, written for the project managers, contractors and homeowners who have to make the schedule work.

Why textured lacquer needs a plan of its own

Lacquered doors behave differently from foil-wrapped or laminated panels during installation. The surface is built up in layers and cured, so it is harder to touch up in the field: a chip on a textured panel usually means replacing the door rather than filling and repainting it. Wide panels also show every twist in the wall behind them, because the texture scatters light along the whole face instead of hiding a flat spot.

Two practical consequences follow. First, the substrate has to be close to true before fixing, not corrected by shims at the last minute. Second, handling matters: units should reach the room in an order that matches assembly, and protective coverings stay on until the trades who create dust have finished. Both of these are scheduling decisions, which is exactly what an installation plan records.

Section 1 — Site data and measured drawings

The plan starts with numbers taken on site, not from the architect's original drawing. For a made-to-measure run such as our Custom Built-in Kitchen Cabinets, the survey record should show:

  • Finished floor levels at each end of every wall run, and the deviation from a straight line across the run.
  • Completed wall surfaces: plaster, tile or panel cladding, with flatness checked over a 2 m straight edge.
  • Exact positions of soil stacks, waste outlets, water points, gas points and electrical sockets, measured from two fixed reference lines.
  • Ceiling height at several points along the run, plus the position of any bulkhead, beam or duct that a tall unit must clear.
  • Access route for delivery: lift dimensions, stair widths, corridor turns and whether a crane or hoist is needed on upper floors.

These figures should be re-verified after the wet trades have finished. A survey taken before plastering is a guess; a survey taken after tiling is a fact. Any change larger than a few millimetres goes back to the factory for revised drawings before production starts, because lacquered doors are not trimmed on site.

Section 2 — Confirmed specification and shop drawings

The plan must attach the approved drawings, not reference them. Each elevation should show unit codes, door direction, drawer stack heights, and where the make-up piece is placed so that a scribed edge lands in a corner rather than beside an appliance.

Item to confirmWhy it belongs in the plan
Door style and texture sample referenceTexture depth reads differently at grazing light; approve a physical sample under the real lighting.
Carcase and shelf colour matchInterior panels sit against the lacquer edge and must be ordered in the same batch decision.
Worktop thickness and edge detailDetermines the scribe height, splashback rebate and whether wall units need a setback.
Integrated appliances with dimensionsTall housing ventilation gaps and door overlay must be fixed before the carcass is built.
Handle or handleless routingAffects door spacing, drawer fronts and hardware fixing positions.
Internal fittings layoutCorner mechanisms, pull-outs and bins change which panel can be removed for service access.

Section 3 — Preceding works and the responsibility matrix

Most installation failures are handover failures. The plan should name, in one table, who completes each item before the cabinetry crew arrives, with a date beside it:

  • First fix complete: waste pipes pressure-tested, water and gas commissioning done, electrical circuits tested and sockets set out to drawing positions.
  • Floors and walls finished, fully cured and dry, with the final floor level documented so toe-kick heights are correct.
  • Appliance delivery confirmed, with units on site or a written delivery window that sits inside the installation week.
  • Protection in place: floor covering, and dust screens if other trades remain in the building.

Where the project is a villa or hotel fit-out, this matrix also lists who supplies the worktop template, the splashback and the lighting to the cabinetry — three items that routinely sit between suppliers and stall a handover.

Section 4 — Delivery logistics and sequencing

A plan that says "deliver to site" is not a plan. It should specify the container or pallet breakdown, the crate numbering scheme that matches the drawing codes, and the unloading path. For apartments and resort rooms, crates should be labelled by elevation so crews carry each set straight to its room instead of staging everything in one corridor.

For international orders, allow buffer between vessel arrival and installation day. Customs clearance, port handling and last-mile transport each absorb time that the on-site crew cannot recover later. Our Logistics & Door-to-Door Delivery service covers freight forwarding, packing lists and container loading planning, which is where crate numbering and delivery sequencing get decided.

Inspection on arrival. Open each crate against the packing list before storage. Check door faces for transit damage, verify that every make-up panel and hardware kit arrived, and photograph anything damaged the same day. Claims filed after doors are hung take far longer to resolve.

Section 5 — The installation method statement

This is the operational core. It should set out the order of work, the fixing details and the tolerances the crew is working to:

  1. Mark datum lines on the wall from the confirmed finished floor level; scribe or cut make-up pieces to the recorded deviations.
  2. Fix wall brackets or a mounting rail into the substrate, with fixings chosen for the actual wall build-up — solid masonry, timber frame and steel stud all need different anchors.
  3. Install base units first, levelled in two directions and connected to each other before any unit is fixed to the wall.
  4. Hang wall units at the recorded height, checking line and projection along the whole run rather than unit by unit.
  5. Fit tall units and ovens last, confirming door swing clearance against adjacent runs and appliance handles.
  6. Template and fit worktops, then seal the perimeter with a neutral-cure silicone that will not attack the lacquer edge.
  7. Fit doors and drawers, adjusting for an even reveal across every gap; then fit plinths, trims and light valances.
  8. Install internal fittings, task lighting and any integrated electrical components, and test each circuit with the doors open and closed.

The method statement should also state the environmental limits the crew will work within: a heated, ventilated, dry space, with no wet trades running alongside. Damp plaster and airborne gypsum dust both damage a cured lacquer surface over time.

Section 6 — Snag list, handover and after-sales

Close the plan with a documented sign-off. A practical snag sheet covers door alignment and reveal consistency, drawer run-out without fouling, soft-close behaviour, sealant lines, visible adhesive or marker marks, and the condition of every door face once protection is removed.

Handover should give the client the spare-parts list — hinges, runners, handles and one spare door per texture if the project has volume — plus a cleaning note. Textured lacquer is maintained with a soft damp cloth and a neutral cleaner; abrasive pads and solvent-based products dull the surface permanently.

Our Installation & After-sales Support covers on-site fitting, inspection with a snag list, warranty terms and spare-part replacement. Confirm the scope, response times and warranty conditions for your specific project in writing before installation begins.

Section 7 — Programme and risk register

Finally, the plan needs dates and named owners. A workable sequence looks like this:

StageOwnerMust be complete before
Site survey after finishesContractor with supplier's surveyorShop drawings are released for production
Drawing and sample approvalClient / designerFactory starts panel processing
Production and QCManufacturerBooking of the shipping window
Freight and clearanceLogistics coordinatorSite is ready for delivery
Delivery and crate inspectionSite managerCrew mobilises
InstallationFitting teamWorktop templating can start
Snagging and handoverAll partiesDefects liability period begins

The register beside it should carry the three risks that most often move a kitchen handover: a late floor finish that changes datum levels, an appliance delivered to the wrong site, and a wall build-up that cannot take the specified fixings. Each has a cheap early answer and an expensive late one.

A short checklist before you commit

  • Survey re-taken after all wet trades, with deviations recorded numerically.
  • Physical texture and colour sample signed off under the real lighting scheme.
  • Responsibility matrix naming who supplies worktop, splashback and lighting.
  • Crate numbering that matches drawing codes, plus an unloading route for the actual building.
  • Fixing specification matched to the wall build-up, not a generic anchor schedule.
  • Snag sheet, spare-parts list and cleaning instructions included in the handover pack.

SANTERSON manufactures lacquered cabinetry — including textured, matte and Matte Lacquer Cabinets finishes — as made-to-measure runs with project-specific dimensions, materials and layouts. Send us your drawings, the finished floor levels and your target installation date, and we will return a shop drawing set and an installation schedule you can build a programme around.