A pocket door looks simple on a drawing. It is one panel, a frame, a track and a wall cavity. That is exactly why an international order for Classic Pocket Doors can go wrong quietly: the parts that matter most are hidden inside the wall, and a mistake only becomes visible after the container has been shipped and the plasterboard is up. This guide walks through the sequence we recommend for buyers, contractors and interior fit-out teams who are ordering made-to-measure pocket doors from China for a villa, apartment or hospitality project overseas.

Why Pocket Doors Deserve Their Own Delivery Plan

Unlike a loose armchair, a pocket door is a built-in component that has to agree with three other trades: the framing that forms the cavity, the wall finish that closes it, and the floor covering that the panel clears. Order it late and the wall stays open waiting for stock. Order it early without confirmed dimensions and you receive panels that no longer match the opening.

Our pocket doors are made to measure. Finish, layout and dimensions are specified per space, so there is no standard size to fall back on when a drawing changes. For an international project this means the dimensional information has to be frozen before production starts, and it has to be frozen in coordination with everything else you are buying for the same building.

A practical rule: treat the pocket door schedule as part of the wall build-up, not as door hardware you can decide on site. Decide the opening, the cavity depth and the track type while the partitions are still being designed.

Step 1 — Lock the Door Schedule Before Anything Ships

Before a quotation is meaningful, each door in the project needs an entry on a single schedule. For every opening record:

  • The clear opening width and the finished floor level, taken from the coordinated drawing set rather than from a site tape measure.
  • The wall build-up on both faces: stud depth, board type and thickness, and any tile or stone that will be added later.
  • Which face carries the visible track or bottom guide, and whether the panel is single or double.
  • The finish you want — a painted panel, a wood veneer panel, or a glazed pocket door where the frame and glass detail have to match adjacent joinery.
  • Whether the same opening also has to coordinate with wardrobes, wall panelling or concealed doors elsewhere in the room.

This is where a single supplier for several trades saves time. When pocket doors, built-in furniture and wall panelling come from the same factory, one production team checks that the veneer, the edge detail and the reveal are consistent across all three, instead of three separate factories each guessing what the other is doing.

Step 2 — Decide What Travels Together

Freight is where an order for pocket doors becomes either efficient or wasteful. Panels are flat, heavy and fragile at the edges; frames and tracks are long and awkward; hardware is small and easy to lose. Split them across three shipments and you pay three times for handling, and you risk arriving on site with panels but no track.

We normally group a door order with the other fixed items for the same building — cabinetry, joinery, wall panels and windows and doors — so that one container carries a complete room set. That gives you two advantages:

  • One loading plan. Panels are packed flat against dunnage, long sections run along the container floor, and small hardware is boxed and labelled to the opening it belongs to.
  • One delivery window. The wall can be closed once the complete set for that room arrives, rather than being opened and re-opened.

Step 3 — Choose the Freight Mode Against Your Site Programme

Our logistics and door-to-door delivery service covers forwarding by sea, air and rail, together with the paperwork that goes with each consignment: commercial invoice, packing list, certificate of origin and any import documentation your country requires.

Situation on siteWhat we usually suggest
Full villa or apartment block, walls not yet closedSea freight in a consolidated container with the rest of the joinery. Lowest handling cost per unit, and one delivery event to coordinate.
A handful of replacement panels after the main orderAir freight for the panels only, once the confirmed dimensions from the original order have been re-checked against the opening on site.
Mid-range volume with a fixed installation date and no sea window that fitsRail as the middle option between cost and transit time, booked against the same loading plan as the main shipment.

Whichever mode you choose, ask us to label every package with the room and opening number from your door schedule. On a multi-storey job that single habit prevents the most common installation delay: correct panels sitting in the wrong apartment.

Step 4 — Handle Customs and Duties as Part of the Order, Not After It

Import terms are decided case by case, and we do not promise a duty rate or a clearance time in advance. What we do handle is the documentation side: preparing the invoice and packing list so that the declared descriptions match what is actually in the container, arranging the certificate of origin where it applies, and supporting your clearing agent if they query a description.

Two things to settle with your own agent before the goods move:

  • Who acts as importer of record, and whether you want door-to-door delivery all the way to the site gate or port-of-arrival terms with local haulage arranged by you.
  • Whether cargo insurance is being taken on this consignment. Made-to-measure panels cannot be replaced quickly, so an insured shipment is worth discussing for any order where a damaged panel stops a wall from closing.

Step 5 — Receive, Store and Install in the Right Order

On arrival, check the crate list against the door schedule before anything is carried inside. Panels should be stored flat and dry, off the ground, and kept in their packing until the room is painted and the floor covering is laid. Fitting a pocket door panel into a wet, freshly plastered cavity is how a straight panel becomes a warped one.

Our installation and after-sales support covers on-site fitting guidance, inspection of the finished work with your team, and spare parts or replacement for anything damaged in transit. If your own crew is doing the fitting, send us photographs of the framed cavity before they close the wall — that check takes minutes and catches the small errors that are expensive to undo.

Working With One Supplier Across Doors, Joinery and Finishes

Pocket doors rarely sit alone in a room. The same wall may carry a concealed door, a run of wardrobe, or panelling that the door has to disappear into. When those items are ordered separately, each factory works from its own interpretation of your drawing, and the differences show up at handover: mismatched veneer, inconsistent reveals, architraves that do not line up.

Ordering them together means one production order, one quality check and one container. If your project also needs interior fixtures for the same building, they can join the same shipment, which reduces the number of delivery events your site team has to receive and inspect.

A Short Checklist Before You Confirm the Order

  • Every opening measured from coordinated drawings, with finished floor levels agreed.
  • Cavity depth confirmed against the wall build-up on both faces, including tile thickness.
  • Finish and glass or panel type approved per room, matched to adjacent joinery.
  • Packaging and labelling specified by room and opening number.
  • Freight mode and delivery terms agreed, with insurance decided explicitly.
  • Clearing agent briefed, with our documentation matching the physical cargo.
  • Storage conditions on site arranged before the panels are unloaded.

Planning a project order of pocket doors? Send us your door schedule and drawings, and we will quote the panels, frames and track as one package, group them with your other joinery for a single container, and support the delivery through to installation. Contact PHILLIP on WhatsApp +86-13928214007 or email santerson@qq.com — enquiries receive a reply within 24 hours.