A matte acrylic wardrobe rarely fails because of the door finish. It fails on the paperwork around it: a room measured once instead of twice, a hanging rail ordered to a generic length, an internal layout confirmed before the electrical drawings were final, or a set of panels shipped in three separate consignments that arrive on different days. For villa and apartment projects, wardrobes are built-in joinery, which means quantity planning and product coordination have to be settled before production starts, not on site.
This guide walks through how we count quantities for matte acrylic wardrobes, what has to be coordinated with the other fixtures in the same room, and where projects usually lose time. It is written for contractors, interior designers, developers and procurement teams buying built-in furniture from a China-based manufacturer.
Start With Room-by-Room Quantities, Not a Wardrobe Count
The most common quantity error is treating wardrobes as line items on a schedule — "12 bedrooms, 12 wardrobes". Each wardrobe opening is a separate production job with its own dimensions, door type and internal layout. Two identical bedroom plans can still need different carcasses if one wall has a structural column, an air-conditioning return, or a skirting that the design intends to scribe around.
Build the quantity sheet from the room list rather than the unit list, and record for every opening:
- The clear width, height and depth of the finished opening, measured off the completed floor and finished wall lines, not the structural slab.
- Whether the run is straight, L-shaped at a corner, or interrupted by a door reveal or window sill.
- Door operation — hinged, sliding, or an open modular configuration — because this changes both the panel count and the clearance needed in front of the unit.
- The internal split: long hanging, double hanging, drawers, shelves, trouser tray, lighting provision.
- Which rooms repeat exactly and which are one-offs. Repeats are what make a run economical to produce.
Our matte acrylic wardrobe range is made-to-measure: sizing, finish and layout are specified per project rather than chosen from fixed widths. That flexibility removes the "nearest available size" compromise, but it also means nothing can be counted from a catalogue. Every dimension on the sheet becomes a manufacturing instruction.
Group the Wardrobe Runs by Finish Before You Count Panels
Acrylic panels are produced in batches, and the finish you select drives how the run is grouped. A project that specifies three different matte acrylic colours across twelve bedrooms creates three separate panel sets, three rounds of finish approval and three chances for a shade mismatch at handover.
A practical way to group runs:
| Grouping basis | What it controls | Planning note |
|---|---|---|
| Door finish family | Panel batch, edge banding, approval samples | Keep one matte acrylic colour per bedroom floor where the design allows it; keep feature finishes for master suites and show units. |
| Door operation | Carcass depth, track and hardware set, front clearance | Hinged and sliding runs in the same room type should not share a single generic dimension. |
| Internal layout family | Shelves, drawer stacks, hanging rails, accessories | Repeat one or two standard layouts and reserve custom splits for irregular rooms. |
| Mixed-material combinations | Glass, aluminium frame and acrylic elements ordered together | Where a design combines glazing with acrylic doors, place those items on the same production schedule so trims align. |
If the specification mixes finishes deliberately — for example matte doors in the secondary bedrooms and a two tone acrylic wardrobe treatment in the master suite — write that split into the quantity sheet from day one. Late finish changes are the single biggest cause of re-ordering panels.
Coordinate the Wardrobe With Everything It Touches
Built-in joinery sits between flooring, wall finishes, ceiling lines, lighting circuits and doors. Coordination is not a courtesy to other trades; it protects your own installation date.
Flooring and ceiling
Confirm whether the wardrobe lands on the finished floor or is scribed above it, and whether the ceiling profile — cornice, shadow gap, cove lighting, sprinkler head — cuts into the top of the carcass. A run drawn to a clear 2700 mm will not arrive at site as expected if the design later adds a bulkhead. Record the finished floor level and finished ceiling level for each room on the same sheet as the wardrobe dimensions.
Lighting and power
Internal wardrobe lighting needs a driver location, a switched feed and a cable route decided before the carcass panels are drilled. Where the design calls for integrated lighting in display bays, coordinate it with the wider lighting package so drivers, switching and control type match across the room rather than being solved by whoever installs first.
Doors, skirting and architraves
Decide which comes first — door lining or wardrobe return — and who trims the reveal. The same question applies to skirting and architrave: either the carcass is notched around it, or the joinery is installed before those items and the trim finishes into it. Put that decision in writing with the site team.
The rest of the fit-out
Wardrobes are usually ordered alongside vanities, kitchen cabinetry and other built-in furniture. Where those items share a wall or a corner, they should be dimensioned from one coordinated drawing set, not three separate supplier sketches. A single measurement round covering cabinetry, wardrobes and bathroom fixtures removes most clashes before they become site problems.
Sequence Production, Packing and Delivery Around the Site Programme
Once quantities and coordination are settled, delivery planning decides whether installation runs smoothly. For multi-unit work we schedule production by room group and pack by unit or floor, so a crew installing level two is not waiting on panels stored in a container destined for level three.
- Release dimensions in one round where possible. Partial releases are sometimes unavoidable, but each additional release adds its own approval and production cycle.
- Fix the finish sample before volume production. Approve a matte acrylic door sample against the drawing, then freeze the colour reference for the whole run.
- Pack to the installation sequence. Label sets by room or unit number, and keep hardware sets with the panels they belong to.
- Confirm the receiving arrangement in advance. Door-to-door delivery covers freight and documentation, but the site needs a crane window, storage area and access path agreed before the truck arrives.
A note on lead time: it is set by the drawing freeze date, not the purchase order date. A wardrobe package that goes into production while its internal layouts are still open will be re-cut, and re-cut panels arrive later than if the same package had simply been released later.
A Pre-Production Checklist
- Clear opening dimensions recorded against finished floor and finished ceiling levels, room by room.
- Door operation confirmed per room, with front clearance checked against the furniture layout.
- Internal layouts agreed, with a maximum of two or three standard configurations across repeating rooms.
- Finish sample approved in writing and the colour reference locked for the run.
- Lighting, power and driver locations shown on the coordinated services drawing.
- Flooring, skirting, architrave, cornice and bulkhead interfaces assigned to a named trade.
- Packing list matched to the installation sequence, labelled by unit or floor.
- Delivery date, access route and storage area confirmed with the site team.
Common Problems and How They Are Avoided
Shade variation between rooms. Usually caused by panels produced in separate batches against an unfrozen finish. Avoided by approving one sample and grouping the run by finish before production.
Carcass will not fit the opening. Almost always a measurement reference problem — dimensions taken from structural lines while the walls and floors were still unfinished. Avoided by measuring against finished levels and recording that reference on the sheet.
Sliding doors bind or cannot travel. Typically a clearance or track-setting issue created when the front-of-wardrobe layout changes after the door type was fixed. Avoided by locking furniture layouts before the door operation is chosen.
Internal lighting retrofitted on site. Happens when services were never coordinated with the joinery drawing. Avoided by showing drivers, switches and cable routes on the same drawing set.
Frequently Asked Questions
Can matte acrylic wardrobes be ordered in mixed sizes for a single development?
Yes. These units are made to measure, so each opening is produced to its own dimensions. The practical limit is administrative rather than technical: every distinct size and finish needs its own measurement record and approval, so grouping similar rooms keeps the package manageable.
When should wardrobe dimensions be released to the manufacturer?
After the architectural and services drawings are stable and finishes are selected — that is, once floor levels, ceiling profiles, bulkheads and lighting positions are fixed. Releasing earlier is possible but usually means a second measurement round.
Should wardrobes be ordered with kitchen cabinetry and vanities from one supplier?
There is no requirement to do so, but ordering coordinated built-in packages from one manufacturer simplifies dimensioning, finish matching, packing and delivery. Santerson supplies wardrobes together with kitchen cabinets and bathroom fixtures under one project schedule, which is why multi-room fit-outs often come to us as a single package.
What information do you need to quote a wardrobe package?
Room-by-room dimensions taken against finished levels, the door operation for each opening, the internal layout per room type, the selected finish, and the target installation sequence. Drawings are welcome; a marked-up floor plan with dimensions works as well.
Move From Drawing to Production Without Re-Cutting
Quantities and coordination are not extra administration around a wardrobe order — they are the order. Count by room, group by finish, resolve every interface on paper, and pack to the site programme. Do that and matte acrylic doors read as designed: flat, even, continuous across a wall, with no visible compromise between one unit and the next.
Send us your room schedule or drawings and we will return a measured wardrobe package with finish samples, coordinated internal layouts and a delivery sequence matched to your programme — supported by our custom manufacturing, logistics and installation services.