A two-piece WC looks like a small line item on a bathroom schedule, and that is exactly why it causes rework. Trap orientation, rough-in distance and seat compatibility are decided by the slab and the soil run, not by the finish schedule. The record below is what our project team asks procurement teams to lock down before an order for the Two Piece Washdown Toilet 1038A, Dual S Trap & P Trap Ceramic WC Toilet for Hotel Bathroom is placed.

Why this fixture appears on hotel schedules at all

The 1038A is a two-piece washdown toilet in vitreous china, and the reason it keeps coming up on guest-room and public-restroom lists is that one model covers two very different site conditions. The page describes both a wall outlet arrangement (P-trap) and a floor outlet arrangement (S-trap), so a single item code can follow a building where some bathrooms were cast with a floor branch and others with a wall branch. For a procurement team, that means fewer substitutions, but only if the two variants are documented as separate line items.

The rest of the specification is ordinary for commercial work: a washdown flushing action, a glazed surface intended to resist dirt build-up and simplify daily cleaning by housekeeping, and support for bulk supply and project customisation. Those points matter to operators, but they do not decide whether the unit fits on site.

Item 1: trap type per bathroom, not per project

The most common error we see in requisitions is a single trap type applied to a whole building. Record the outlet for each bathroom type and mark it on the reflected ceiling or fixture plan:

  • Floor outlet (S-trap) — the pan connects downwards into the slab. Typical of concrete-slab construction and of retrofit work where the soil run stays below the floor.
  • Wall outlet (P-trap) — the pan connects into a wall chase or duct. Typical of shaft-based guest-room layouts, and the arrangement usually paired with concealed cisterns and boxed-in ducts.

The 1038A page lists an 180mm rough-in for the wall-mounted P-trap version and a 250mm floor S-trap rough-in. We quote those figures because they are what the product page states, and we ask you to confirm them against the technical sheet that comes with your order before any setting-out is released. On site we check the actual dimension from the finished wall face to the centre of the outlet, and from the finished floor level up for a floor branch, because tile build-up changes what "finished" means.

Item 2: cistern, seat and flush interface

A two-piece WC is three parts that can be ordered wrongly in three different ways. Your documentation should name each one:

ComponentWhat to recordWhy it fails later
CisternClose-coupled to the pan, or supplied separately; single or dual flush; inlet side and water supply heightThe supply point is already in the wall by the time the cistern arrives, and an inlet on the wrong side means exposed pipework in a guest room.
Seat and coverHinge type and fixing centres, soft-close or standard, material grade for the traffic level of the locationPublic restroom seats are replaced far more often than guest-room seats; specifying one grade for both drives up maintenance calls.
Flush interfaceButton or lever, access to the valve through the access panelAn access panel placed for aesthetics rather than for the valve cannot be serviced without removing tile.

Item 3: what goes in the submittal before you order

We ask for one consolidated document per bathroom type, and we treat an incomplete one as the reason orders stall. It should contain:

  • Bathroom tag numbers grouped by outlet type, with the measured rough-in for each group rather than a single nominal figure.
  • The pan model, the matching cistern and the seat as three linked line items with quantities per group.
  • Water supply pressure and mains arrangement for the building, since flushing performance is judged against the supply you actually have, not the supply assumed at tender.
  • Access panel location relative to the flush valve, drawn, not described in a note.
  • Replacement stock quantities: spares for seats, cover sets and flush mechanisms, sized against room count and expected service life rather than copied from another project.
  • Spare-pan quantity for the two trap variants separately. A floor-outlet spare does not solve a wall-outlet failure.

Item 4: procurement documentation after the sample

Approving a sample is where most teams stop documenting. Three things should still be written down and attached to the purchase order:

  • Approved physical sample reference. Photograph the approved pan, cistern and seat together with the item code visible, and keep it in the project file. Colour and glaze look different on a screen than under guest-room lighting.
  • Bulk packaging and pallet configuration. Ceramics travel as fragile cargo. Confirm the carton count, pallet stack and handling notes so the site team can plan storage and unloading for the full delivery, not a sample crate.
  • Inspection point on arrival. Agree who opens cartons, what counts as transit damage, and how replacement units are raised, before the container is unloaded. This clause costs nothing at order stage and saves weeks when a batch arrives damaged.
How to keep the record usable. One spreadsheet per project, one row per bathroom tag, columns for outlet type, measured rough-in, pan code, cistern code, seat code and access panel reference. When a later phase or a second property repeats the same guest-room layout, that sheet is the specification — no re-measuring, no guessing which trap variant was installed.

Ordering it as part of a wider bathroom package

The 1038A rarely travels alone. In our own range, the same guest-room package normally pulls in basins, vanities, shower fittings and mirror cabinets alongside the WC, and coordinating those items on one schedule avoids the classic mismatch of a pan ordered for a wall outlet while the basin and vanity were set out for a different chase depth. As a one-stop furniture and building materials supplier working on hospitality and villa projects, we handle that coordination as part of project supply: you send the bathroom schedule with trap types and rough-ins marked, and we return an item list mapped to it, including bulk quantities and project customisation where required. Our custom built-in kitchen cabinets for hotel and apartment projects follow the same documentation discipline, which is why cabinetry and ceramics arrive on site compatible rather than in conflict.

Pre-order checklist for the 1038A
  • Outlet type confirmed per bathroom tag, floor or wall
  • Rough-in measured from finished surface and cross-checked against the technical sheet for your order
  • Cistern type, flush control and supply inlet side recorded
  • Seat grade split between guest room and public restroom
  • Access panel drawn over the flush valve
  • Packaging, pallet and arrival-inspection terms in the purchase order
  • Spare pans listed by trap variant; spare seats and flush mechanisms listed separately
Send us your bathroom schedule

If you are specifying this WC for a hotel, serviced apartment or villa development, send the fixture schedule with outlet types marked and we will confirm which 1038A variant matches each group, together with matching basins and other interior design service items for the same rooms. Enquiries are handled by our project team through the contact page.