A swim spa arrives on a flatbed, sits on a slab that has already been poured, and plugs into an electrical supply that has already been sized. Everything that usually goes wrong with a project like this happens before the crate leaves the factory. Here is how we plan delivery and installation for Outdoor Swim Spa WS-S06B, in the order the decisions actually have to be made.

What you are coordinating

WS-S06B is a configurable outdoor swim and hydrotherapy spa. The catalogue dimensions are 5800 × 2200 × 1250 mm, with a single control system, three water pumps, one filter pump, 48 jets in total, LED lighting (three fixtures plus 26 small LEDs), ozone sanitisation and a waterfall feature. Total power for the configuration shown on the product page is 13.35 kW.

Those numbers set three hard constraints that drive the whole schedule:

  • A footprint, not just a package. A 5.8 m long shell needs clear access from the truck to the final position, plus working space around it for levelling, plumbing and later servicing.
  • An electrical load that has to be sized before trenching. The 13.35 kW figure is the spa alone; add the heat pump or other options and the supply, protection and cable run change accordingly.
  • A configuration that has to be frozen early. Options listed in the catalogue include control systems, UV sterilisation, additional water pumps, heat pumps, sand filtration, insulation and steps. Each one changes what your electrician and plumber need on site.

This is why we treat a swim spa as part of the turnkey project scope rather than as a piece of equipment ordered at the end. As a one-stop furniture and building materials supplier, we already coordinate product manufacturing, freight and site work on villa and hospitality projects, so the spa is scheduled against the same programme as the paving, the decking and the landscape lighting.

Confirm the configuration before anything else

The single most expensive mistake on a swim spa project is a site that was prepared for one specification while the delivered unit carries another. Before you release any civil work, lock down and put in writing:

  • The exact model and finish, and which catalogue options are included versus added later.
  • Total connected power and the supply requirement for that configuration, including the heat pump if selected.
  • Whether filtration is the standard filter pump or the optional sand filtration system, because the plant space and pipework differ.
  • Access route and lifting method: crane, forklift or manual route across the site.
  • Drainage and overflow arrangement, and where the discharge point sits relative to the 1250 mm shell depth.
  • Steps and any perimeter decking or paving detail, so the finished level matches the spa edge.

If you are specifying several units across a resort or a multi-villa development, confirm the configuration per unit rather than assuming one specification carries across. Options vary by model and availability, and we will always ask you to confirm the selected configuration before production starts.

Site preparation: what your local contractor needs from us

The civil and electrical work is normally done by a local contractor. To do it properly they need our dimensioned arrangement for the confirmed unit, not a brochure image. In practice the handover pack should cover:

ItemWhat to confirm on site
FoundationA level, structurally adequate slab sized beyond the 5800 × 2200 mm footprint, with the finished level set against the spa edge and any steps.
Clearance and accessWidth and height of the route from the delivery point, plus turning space. Check gates, overhead lines and roof overhangs.
PowerSupply capacity and protection for the confirmed configuration, cable route, and an isolator within reach of the control system.
Water and drainageFill connection, drain point, overflow discharge, and access for future filter and pump servicing.
FinishesDecking, paving and lighting set out around the shell so the spa reads as part of the outdoor design rather than an addition.

We are not your local builder and we do not design your slab or certify your electrical installation. What we do is give you dimensioned, configuration-specific information early enough that your contractor can price and programme the work without guessing.

Freight: packaging, documents and the delivery window

For international projects we arrange freight forwarding by sea, air or rail, together with the paperwork side: commercial invoices, packing lists, certificates of origin and import permits where required. Packaging and container loading are planned around the shell dimensions so the unit ships protected and lands in a sequence your site can receive.

Three points that save time on Australian and other long-haul projects:

  • Book the spa into the container plan, not after it. A 5.8 m shell is not a drop-in addition to a mixed load of furniture and joinery; it affects how the rest of the order is loaded.
  • Agree Incoterms and who handles customs clearance before the order is placed. Import duty, inspection requirements and delivery scope are project-specific and should be confirmed case by case rather than assumed.
  • Consider cargo insurance for the shell. Acrylic and composite shells, glass features and jet assemblies are the items most likely to be claimed for in transit.

Our logistics and door-to-door delivery service covers freight coordination and shipment tracking, with dedicated coordinators handling the documentation. Your role is to make sure someone competent and available is on site at the agreed window, with the access route clear and the slab cured.

Installation sequence on site

Once the unit lands, the practical order of work is short but strict:

  • Position and level. The spa is placed on the prepared base and levelled before any connection is made. Levelling after pipework is connected is where damage happens.
  • Electrical termination. Supply, protection and isolator are connected by a licensed electrician to the confirmed load for your configuration.
  • Filtration, jets and features. Pump, jet circuit, waterfall and lighting connections are checked against the specification you ordered.
  • Commissioning and handover. Fill, run the control system, check each jet zone, ozone and lighting function, then record the configuration actually installed for future servicing.

Our installation and after-sales support covers on-site installation, inspection and snag resolution, warranty coverage, spare parts and ongoing maintenance. What we ask of you is the same as with any fit-out: have the local services ready before our team works to the site programme, because a spa sitting in a crate while an electrical supply is still being approved costs both sides time.

A coordination timeline you can work backwards from

StageDecision or action
Design stageselect model and options; agree the spa as part of the outdoor layout, with decking, steps and lighting set out around it.
Specification sign-offFreeze configuration, connected power and included equipment. Issue dimensioned information to the local contractor.
ProductionManufacture to the frozen specification; confirm option availability per unit.
Freight planningAgree mode, Incoterms, insurance and documents; schedule delivery into the site programme.
Site works (parallel)Slab, power supply, water and drainage completed while the unit is in transit.
DeliveryAccess route clear, lifting method agreed, receiver on site at the booked window.
Installation and handoverLevel, connect, commission, record the installed configuration, close out snags.

The point of working backwards is simple: site preparation runs in parallel with production and freight, so the spa arrives to a ready base instead of waiting for one. Projects that sequence it the other way round pay for storage, re-mobilisation and an outdoor area that stays unfinished weeks longer than planned.

Before you order: the checklist

  • Configuration frozen in writing, including power, heat pump, filtration and steps.
  • Access route surveyed from truck to final position, with lifting method agreed.
  • Slab design, supply capacity and drainage signed off by your local engineer or contractor.
  • Incoterms, customs responsibility, insurance and delivery address confirmed.
  • Delivery window booked against a site programme that has the base ready.
  • Installed configuration recorded at handover for warranty and spare-parts reference.

Note: dimensions, jet counts and power figures quoted here are the catalogue values shown on the WS-S06B product page. Options and included equipment vary by model and configuration, so confirm the selected specification with us before ordering and before your contractor fixes any site works.