A decorative wall panel rarely fails on site because the panel itself was wrong. It fails because the modern decorative wall panel arrived without a matching installation plan: no substrate note, no cut list, no finish schedule, no spare allowance. If your interior decoration work is being handed to a site crew in another city or another country, the drawing package and the written plan are what keep the wall looking like the sample board. Below is the checklist we use when preparing wall panel packages for villa, hotel and apartment projects.
1. The scope sheet: which walls, which panels
Start with a room-by-room schedule rather than a single line item. Each wall gets its own entry stating the panel type, the finish reference and the boundary conditions. A single project often mixes three different surfaces — a flat feature panel behind the reception desk, a luxury decorative 3D wall panel in the lounge, and a flexible sheet wrapping a curved soffit where a rigid board simply cannot go.
- Wall reference number taken from the layout drawing, not "lobby wall".
- Panel type and surface finish code for that wall.
- Start and end points, plus how the panel meets floor, ceiling and adjacent openings.
- Whether the wall is straight, curved or includes arches and niches.
- Who supplies trims, edge profiles, adhesive and fasteners: you or the panel supplier.
2. Measured dimensions, not drawing dimensions
Design drawings give nominal sizes; panels need measured ones. Ask for a site measurement sheet per wall: length and height at three points, out-of-plumb deviation, position of sockets, switches, air diffusers and door frames, and the finished floor level. Panels are made to measure on our side, so a dimension taken from a plan that was never reconciled with the built condition is the most common source of rework.
Record the ceiling height variation along the wall run. Even a small difference across a four-metre wall run changes every panel in the row, and it is far cheaper to absorb that in the shop than on site.
3. Substrate and surface preparation notes
The plan must state what the panels are fixing to and what condition that surface must be in before delivery. Write it down even when it feels obvious: blockwork, plasterboard, existing tile, existing paint, or a new timber batten frame.
- Substrate type and whether it is sound, dry and flat enough to receive panels.
- Levelness tolerance the site team must achieve, checked with a straight edge.
- Primer or sealer required on painted or glossy existing surfaces.
- Batten or framing layout where services, backlit features or heavy fixings sit behind the panels.
- Moisture control for walls adjoining bathrooms, kitchens or external walls.
Moisture resistance is a panel property, not a substitute for wall preparation. Panels listed as moisture resistant suit humid indoor environments, but a leaking or rising-damp wall still has to be fixed before anything is clad over it.
4. Panel selection record
Attach one page per selected panel showing the sample reference, the surface effect, and where that panel is allowed to be used. This prevents substitutions happening silently at the store counter.
| Panel type | Where it works | What to confirm before ordering |
|---|---|---|
| Flat decorative wall panel | Villa background walls, hotel lobbies, bedrooms, offices, restaurants, retail | Colour and texture reference, panel size, stain-resistant surface, cleaning method |
| 3D decorative panel | TV and feature walls, lounge accent walls, reception | Pattern direction, relief depth, how corners and skirting are closed off |
| Flexible wood grain cement sheet | Curved walls, arches, columns, façade and renovation cladding | Bend radius on site, fixing method on curved substrate, whether the raw surface will be painted to a chosen colour |
| Wall panel system with integrated lighting | Backlit feature walls, media walls | Driver location, access panel, cable route, who wires the fitting |
5. Layout, cut list and setting-out drawing
A setting-out drawing is the single most useful document in the pack. It shows panel joints, where the first panel starts, how off-cuts are distributed, and how the pattern reads around openings. For 3D and textured panels, mark the pattern direction with an arrow on every panel in the elevation.
- Panel joint grid with dimensions from a fixed datum line.
- Cut list keyed to each panel number, so pieces arrive labelled.
- Detail for internal and external corners, and for the top and bottom edges.
- How panels are cut around sockets and diffusers — cut into the panel or split the joint around them.
- Expansion gap expectation at changes of material.
Lightweight panels can be cut and drilled on site, so a small number of field adjustments is normal. What should not be normal is re-cutting half a shipment because nobody drew the joint grid.
6. Fixing method and hardware schedule
State the fixing method per substrate, then list the hardware so nothing is bought locally at the last minute. Include adhesive type, fastener type and spacing, trim profiles, and whether a concealed or face-fixed system is used.
- Adhesive or mechanical fixing specified for each substrate in the project.
- Fastener spacing and whether concealed fixings need a batten frame.
- Matching trims, closing profiles and corner beads by finish code.
- Adhesive curing conditions: temperature range, ventilation, open time.
- Load-bearing note for mirrors, screens, wall-hung basins or heavy art fixed over panels.
7. Services, lighting and access
Feature walls usually hide something: LED drivers, a TV bracket, speaker cable, a switch loop. The installation plan should show these before the panels close the wall in. Where backlit or illuminated features are part of the design, confirm the driver position and provide an access point, because a driver sealed behind a fixed panel is a maintenance problem you will meet again later.
8. Delivery sequence and site readiness
Panels should arrive when the wall is ready, not when the purchase order was placed. Build the plan around the site programme:
- Wet trades, screed and paint complete in the room before panels are delivered.
- Rough-in of electrical and services signed off.
- Storage area agreed: dry, level, panels stored flat and acclimatised to the room.
- Delivery split by zone or floor so crews are not sorting cartons in a corridor.
- Packaging labels matching the panel numbers on the setting-out drawing.
9. Quantity take-off, wastage and spares
Take off quantities from the setting-out drawing rather than the floor area, then add a wastage allowance for cuts, damage in transit and future repairs. Order the full batch of one finish code at once — panels from different production runs can read differently even under the same name. Keep unused full panels as spares for the handover file; matching a repair panel years later is difficult when the run has closed.
10. Quality checkpoints and sign-off
Put sign-off checkpoints in the plan and name who signs each one: substrate accepted, first panel bay approved, full wall approved, and final clean and protection. Approving the first bay is worth the time it takes — joint width, pattern alignment and trim fit are all visible there, before the whole wall is fixed.
- Substrate flatness and dryness checked and recorded.
- Sample panel or first bay approved by the designer or client.
- Joint widths, pattern direction and trim fit inspected along the full run.
- Surface protected and cleaning method handed over with the maintenance manual.
Working from drawings only? Send us the wall elevations, measured dimensions and finish references. As a manufacturer of wall panels and wall cladding, we prepare made-to-measure panels with the cut list, layout and fixing notes that a site crew can follow without calling you every day.
Common gaps worth avoiding
No finish schedule. Panels get substituted at the counter because nothing recorded the exact reference. One page per panel type closes this.
Curved walls treated as flat walls. Arches, columns and curved soffits need a flexible sheet and a stated bend radius, not mitred rigid boards.
Lighting decided after the panels. Backlit features, drivers and access points belong in the layout drawing from the first revision.
No spares. Repairs without matching stock end in visibly different panels. Order the spare set with the main order.
Trims left out of the order. Missing closing profiles stall a completed wall for days. List every trim by finish code on the packing list.
Before you release the order
- Room-by-room wall schedule with panel type and finish code.
- Site-measured dimensions per wall, including out-of-plumb and ceiling height variation.
- Substrate preparation notes and tolerance requirement.
- Setting-out drawing with joint grid, pattern direction and cut list.
- Fixing and hardware schedule matched to each substrate.
- Services, driver positions and access points shown on the drawings.
- Delivery sequence tied to site readiness, with labelled packaging.
- Wastage allowance and spare panels ordered in the same batch.
- Sign-off checkpoints named with responsible parties.
A wall panel installation plan is not paperwork for its own sake. It is the difference between a crew that finishes a feature wall in a day and a crew that stops work to ask what the drawing did not say. Prepare it once, reuse the structure across rooms, and let the panels arrive already knowing where they go.