A Santerson Storage & Display Combo looks simple on a drawing: one wall, open shelving for display, closed cabinetry for everything else. In practice it touches more trades than almost any other item in a villa or hospitality package — joinery, electrical, lighting, AV, wall finishes and the site programme. The unit itself is straightforward to manufacture. The approvals around it are where projects lose time. This guide sets out who signs off what, in what order, and what each party needs to see before they sign.

Why this one item collects more signatures than the rest

The Storage & Display Combo sits in our Media & TV Walls collection and is made to project-specific dimensions, layout and finish. That configurability is the reason it needs a defined approval path rather than a single purchase order.

  • It spans disciplines. A media wall carries the television or projector position, concealed cabling, socket outlets, sometimes integrated lighting in the display niches, and the load path for anything fixed to the wall behind it.
  • It is visible from the room, not just inside it. Owners, interior designers and sales teams all have an opinion on how much of the unit reads as open display and how much closes away. That debate needs a deadline, or it runs through production.
  • Its dimensions come from site. A wall system is set out against finished floor and finished ceiling levels, plus the position of existing services. Those numbers arrive late on many jobs, which is why dimensional sign-off needs an owner and a date.
  • It is often a variation magnet. Once the client sees the first elevation, requests follow — a deeper shelf, a different handle detail, an extra niche. Each one resets several approvals at once if they are not separated cleanly.

Who signs off what

Before any drawing is issued, name the person accountable for each decision. On Australian villa and apartment projects we typically see four parties around this item, and confusion about their boundaries causes most of the delay.

DecisionRecommendsApprovesNeeds to be settled by
Layout, proportions, open-to-closed ratioInterior designer / design leadClient or owner's representativeDetailed design sign-off
Materials, veneer or laminate, colour and edge detailDesign lead with manufacturer finish samplesClient, against a physical sampleFinish approval stage
Dimensions set out on site (FFL, FCL, service locations)Main contractor's site engineerContractor's project managerBefore shop drawings are released for manufacture
TV position, cable routes, socket and data outlets, integrated lighting circuitsAV consultant and electrical contractorDesign lead, then clientCoordinated services drawing sign-off
Wall substrate and fixing method behind the unitMain contractor / structural engineer where requiredContractor's project managerBefore wall lining is closed up
Purchase order, delivery sequence, install windowProcurement or project managerCommercial leadAfter all technical approvals above

The pattern to avoid: one person approving everything. A design lead who approves the electrical coordination without the AV consultant's input will reverse that decision later, and reversals after manufacture has started are expensive.

A four-stage approval sequence that holds on site

Stage 1 — Concept layout, approved against the room

Issue one elevation and one plan, not options. Give the client two layouts maximum and ask them to choose. At this stage the only decisions that matter are width, height, where the television sits and how the open display is distributed. Fixing these early protects everything downstream. If your scheme also uses open display niches elsewhere in the property, review them in the same session so the language of the joinery is consistent across rooms.

Stage 2 — Coordinated services drawing, signed by three parties

This is the stage most teams skip and most teams regret. The drawing shows the unit with every socket, data point, TV bracket zone, cable chase and light circuit marked against a common dimension line. Electrical contractor, AV consultant and design lead all initial it. Only then does the wall lining go up.

Where the brief calls for media storage that also houses consoles, speakers and media libraries, our Integrated Media Storage configuration is the reference point for how a closed run carries equipment. Your services drawing has to allow the ventilation gaps and cable access that arrangement depends on.

Stage 3 — Finish approval against a physical sample

Do not let a finish be approved from a screen. Veneer figure, laminate sheen and the way an edge band catches light all read differently on site. Issue a sample board with the exact door panel, carcass edge and shelf material, and have the client sign the physical piece. Record the sample reference number in the approval document, so the item that arrives matches the item that was signed.

Stage 4 — Dimensional release for manufacture

The final signature is a site one. Someone with measurement responsibility confirms finished floor levels, finished ceiling levels, plumb and square of the wall, and the as-built position of services. That single sign-off releases production. Give it to a named person with a date attached, and hold the install window open until it lands.

Practical rule: stages 1 and 3 belong to the client; stage 2 belongs to the design team plus consultants; stage 4 belongs to the contractor. Written sign-off at each boundary is what stops a change request in month five from becoming a claim.

The approval pack we need before production starts

For any made-to-measure wall system on our side, a complete submission contains:

  • Signed final elevation and plan, with revision number and date
  • Coordinated services drawing showing outlets, cable routes and lighting circuits
  • Confirmed finish reference, matched to a signed physical sample
  • Site-verified dimensions against finished levels, with the surveyor's name
  • Confirmation of wall substrate and fixing method behind the unit
  • Agreed delivery sequence and install window for the site programme

When those six items arrive together, production moves without queries. When two of them are missing, we come back with a question — and on a compressed programme, one round of questions is often the whole float.

Handling change requests without unraveling the approvals

Change is normal. The problem is not the change itself but the way it reopens decisions that were already closed. Three habits keep it contained:

  • Separate cosmetic from technical. A shelf depth change inside an approved envelope affects one drawing. Moving a cable chase affects three approvals and the wall lining. Treat them as different classes of request with different review paths.
  • Set a cut-off per stage, not one global deadline. Finish changes can often be accepted later than layout changes. Say so at the start, so the client knows which doors stay open longer.
  • Re-issue with a revision number every time. An unnumbered revision is how two versions of the same elevation end up circulating on site.

Where the wall combines open shelving and closed cabinetry, our Mixed Open & Closed Storage configurations give clients a starting point for the open-to-closed split. That ratio is the parameter clients revise most often, so settle it deliberately at stage 1 rather than by default.

Procuring the wall as part of a wider package

Media walls rarely sit alone. In a villa or apartment fit-out they share a finish palette with wardrobes, sideboards, kitchen cabinetry and hidden cabinets that carry everything the display shelves should not. Ordering them from one manufacturer keeps veneer batches, edge details and hardware consistent, and it puts a single coordination contact on the drawing distribution list rather than four.

That is also where approval discipline pays back. Once one item's approval sequence is working — recommendation, coordination, finish sample, dimensional release — apply the same sequence to every joinery item in the package. The overhead disappears and the variation rate drops with it.

SANTERSON works as a single supplier across built-in joinery, loose furniture and building finishes for villa, hospitality and office projects, from design coordination through production, door-to-door delivery and installation support. For a package that includes media walls, wardrobes and matching cabinetry, we can consolidate the approval documents so your client signs one coordinated set rather than separate packs per trade.

Product configurations, dimensions, materials, hardware and integrated electrical options are project-specific and confirmed at each approval stage. Speak to our project team for the specification of your particular installation.