Flush hinged doors look simple on a schedule and are anything but simple on site. The whole point of the detail is that nothing gives away where the leaf ends, so every dimension, reveal and finish has to be agreed before production starts. This guide sets out what procurement teams should record for Santerson Flush Hinged Doors so that the order, the opening and the installation all line up.
Why flush hinged doors need a fuller specification than ordinary internal doors
A standard internal door is allowed to look like a door: frame, architrave, visible leaf. A flush hinged door is specified the other way round. It sits in the wall plane, and the design intent is usually continuity of finish across the opening. That single decision changes what has to be documented, because the door now inherits everything the surrounding wall carries — alignment, paint or veneer break lines, hardware choice, and the tolerance stack-up between the wall build and the frame.
Santerson's product pages for this range describe made-to-measure sizing, material and finish options, and a layout tailored to each project, with an explicit instruction to confirm dimensions and selected specifications for each project. That wording is a procurement instruction in itself: there is no standard leaf size to fall back on, so the documentation you produce becomes the specification.
The documentation set to build for each opening
Treat each door as its own line item. A single "flush door, typical" note across a villa or apartment package is where cost and programme problems start. For every opening, record the following.
1. Opening and finish-line data
- Clear opening width and height, plus the finished floor level the dimension is taken from.
- Wall build-up at the opening — substrate, framing, and total wall thickness the frame has to sit in.
- Which face is the visible face, and on which side the leaf is required to sit flush.
- Required reveal or shadow gap, if any, and whether it is expected on all four edges or only three.
- Door schedule reference number matched to the room, not just to a type code.
2. Leaf, frame and finish selection
- Core and substrate required for the location, and who signs it off.
- Finish system — painted, lacquered, veneered or laminated — with a physical sample approved and referenced by code, not by colour name alone.
- Grain direction and panel layout for any veneered leaf, confirmed against the elevation drawing.
- Whether the same finish continues onto adjacent panelling, so the door and wall are ordered as one package rather than two.
3. Hardware and clearance
- Hinge type, count and position, together with the load the leaf will carry at the finished size.
- Handle or no handle. Concealed and handleless concealed door details change the edge preparation, so decide this before the leaf is cut.
- Lock, latch or privacy set, and the key or access control schedule entry it belongs to.
- Leaf swing direction and clearance against adjacent furniture, skirting, flooring thickness and any door stop.
4. Interface and sequence notes
- Who supplies and installs the frame, and who supplies and finishes the surrounding wall.
- Whether the frame is installed before or after the wall closure, and who protects the leaf once hung.
- Paint or finish touch-up responsibility after hanging — a named party, not "site to sort".
- Site-verification step: which dimension is re-measured on site after the wall is closed, and by whom.
How to keep the door schedule usable
A schedule that only lists sizes fails for this product type. Add a column for finish code and sample reference, a column for hardware set, a column for swing direction, and a column for "site-verified dimension" that is deliberately left blank until the opening has been measured after wall closure. That last column does two things: it forces the verification step into the programme, and it gives you a written record if a discrepancy appears later.
Where an opening needs a different operating principle — a pocket detail, or a flush sliding door for a tight circulation route — give it its own schedule entry rather than annotating the hinged line. Sliding and hinged flush doors have different frame, track and wall-cavity requirements, and mixing them in one row invites the wrong product into production.
| Document | What it must settle before the order is placed |
|---|---|
| Door schedule | Reference numbers, sizes, finish codes, hardware sets, swing direction, site-verified column |
| Elevations / marked-up drawings | Flush face, reveal or shadow gap, alignment with skirting and ceiling lines, panel layout |
| Finish sample record | Approved physical sample, code, date, who approved it |
| Wall-build detail at opening | Total wall thickness, substrate, framing support for the frame and hinges |
| Interface responsibility matrix | Frame supplier and installer, wall finisher, protection and touch-up owner |
| Site verification record | Re-measured dimensions after wall closure, signed and dated |
Coordinating the doors with the rest of the fit-out
Flush doors rarely sit alone. They usually continue into panelling, storage walls or concealed access, which is exactly where a single supplier becomes useful rather than merely convenient. Santerson is a China-based furniture and building materials manufacturer offering turnkey project solutions for villas, hospitality and office projects, with custom and OEM service covering bespoke finishes and layouts, plus logistics and door-to-door delivery. Ordering doors together with the panelling, joinery and wall panel systems they sit against puts the finish match and the interface detail in one pair of hands.
That convenience only works if the documentation is handed over complete. Send the schedule, the marked-up elevations, the approved finish sample reference and the wall-build detail together at enquiry stage. A query answered with a full pack returns a quotation you can compare; a query answered with a room name and a rough size returns an order you cannot defend when the wall closes.
Before you release the order: a short check
- Every opening has its own schedule line, reference number and marked-up elevation.
- Flush face, reveal requirement and swing direction are stated for each leaf.
- Finish is referenced to an approved physical sample with a code.
- Hinge type and hardware set are fixed, including the handleless decision where relevant.
- Wall thickness at each opening is confirmed against the as-built wall build, not the design-stage assumption.
- Frame supply, installation, protection and touch-up each have a named owner.
- A site-verification step sits in the programme before final leaf production where the wall build allows it.
Product configuration, materials, dimensions and finish options for this range are made to project requirements. Confirm all dimensions and selected specifications with the supplier for each individual project before ordering.