Mirror sliding door wardrobes are one of the easiest built-in items to specify and one of the easiest to get wrong on quantity. The doors look like a single product, but a working wardrobe is a set of interacting parts: carcasses, panels, door leaves, tracks, hanging areas and finish schedules that all have to arrive together. When one element is short or one opening is measured differently from another, the whole room stops. Below is how we count, group and coordinate these wardrobes on villa and apartment projects so that what reaches site actually fits the space.

Start From Openings, Not From A Room Count

A common early estimate says "eight bedrooms, therefore eight wardrobes". That number almost never survives design development. Mirror sliding door wardrobes are made to measure for each project, so the unit of purchase is the opening, not the room. Two identical guest bedrooms can still need different wardrobes if one has a structural column, a different ceiling height or an air-conditioning return that changes where the carcass can sit.

Before any quantity list goes to a supplier, record for every opening:

  • Floor-to-soffit height at the left end, middle and right end of the opening, not one averaged figure.
  • Clear width after skirting, architrave, tiles or stone have been accounted for.
  • Which walls are true and plumb, and where packing or scribing will be needed.
  • The position of switches, sockets, downlights, sprinkler heads and thermostat panels that sit inside or beside the opening.
  • Floor finish build-up, because a 25 mm difference between a carpet and a tiled threshold changes the door drop.

These notes are what allow a made-to-measure quotation to be compared against the site condition later. A quantity list that only carries widths and heights cannot be checked when the joiner arrives.

Count The Set, Not Just The Door Leaf

Mirror-fronted sliding wardrobes in our catalogue are listed as wardrobe products, for example the Mirror Sliding Door Wardrobes line within our sliding door wardrobe collection. Each order is confirmed by dimensions and selected specification, and the same applies to related layouts such as Two Tone Sliding Door Wardrobes or Sliding Door Corner Wardrobes, where a return changes both the panel schedule and the hardware set.

Split every wardrobe into these lines in your bill of quantities so nothing is assumed to be "included":

ElementWhat To CountWhere It Usually Goes Wrong
Carcass / bodyNumber of bodies, width of each, depth, and whether the top is closed to the soffitFull-height bodies need a site-built filler or scribe; this is often left off the list
Door leavesLeaf count per opening (two or three leaves), plus one spare leaf for high-traffic roomsMirror leaves are fragile in transit, so replacements ordered after delivery cost far more than spares shipped with the original consignment
Track and hardwareTop track length, bottom guide, hangers, bumpers, per openingHardware is set-based; ordering leaves without matching sets means two deliveries instead of one
Interior fit-outShelf lengths, hanging rails, drawer banks, trouser or shoe trays per bodyRail and shelf quantities are usually quoted per metre of body width, so a change in body count changes the fit-out list too
Finish scheduleMirror type, frame or panel colour, edge treatment, hardware finish for each room typeTwo similar rooms given different mirror tints creates a visible mismatch across a corridor

Quantity rule of thumb: every wardrobe opening needs one body schedule, one leaf schedule and one hardware set. If your list has only one of those three columns, it is not yet ready to be quoted.

Group Rooms So The Schedule Stays Consistent

Once openings are measured, group them by room type rather than by floor. Master bedrooms, guest bedrooms, kids' rooms and a shared hallway linen bay usually need different internal layouts even when the doors look identical from the corridor. Grouping lets you fix one interior standard per room type and vary only the dimensions, which keeps pricing stable and reduces the number of unique drawings to approve.

For each group, decide:

  • Hanging heights — short-hang, long-hang or a mix, and how many rails per body.
  • Drawer banks versus open shelving, since drawers change the minimum body width you can order.
  • Whether the mirror runs floor to ceiling on the leaf or stops at a rail height.
  • Whether any opening uses a corner return instead of a straight run; corner layouts are counted separately and often need their own hardware.

If part of the scheme sits outside the wardrobe family — a mirrored hinged door, a dressing-room screen or a vanity mirror wall — list those on a separate page of the schedule. Mixing them into the sliding wardrobe quantities is how mirror tints and frame finishes end up inconsistent between rooms.

Coordinate The Wardrobe Against Adjacent Trades

Wardrobes are built-in furniture, which means they sit in a queue behind flooring, ceilings and electrical work. Three coordination points decide whether installation runs in one day or three.

Flooring first, then measure

Confirm the finished floor level before final dimensions are released. Tiles, adhesive and underlay change the height available for the door drop, and a bottom guide fixed over a thick threshold will bind the leaf.

Ceiling and soffit detail

A full-height wardrobe needs a defined top condition: either the gypsum board stops at the wardrobe line, or the carcass is ordered to a reduced height with a site-built filler. Decide this on the drawing, not on site.

Electrical clearances

Downlights near the wardrobe line, bedside sockets and built-in lighting inside the body all need positions that survive the final carcass setting-out. Where interior lighting is wanted, note it at quotation stage so the wiring provision matches the shelf layout.

Because we supply wardrobes alongside other built-in furniture and interior fixtures — cabinetry, wall panels, doors, flooring and lighting — one coordination drawing can cover all of these items instead of several separate trades each working from their own dimension sheet. That is the practical value of a turnkey interior project solution: fewer handovers, and one party responsible for matching finishes across rooms.

Sequence The Order So Nothing Waits At Site

Mirror sliding wardrobes are made to measure, so the lead time starts when dimensions are signed off, not when the purchase order is raised. A practical sequence:

  • Freeze openings. Release final dimensions only after flooring levels and ceiling lines are fixed on site.
  • Approve one sample set. One wardrobe leaf and one interior fit-out section, checked for mirror tint, frame colour and hardware finish before the full run is produced.
  • Release in room groups. Master suite first if it is on the critical path, guest rooms next. This keeps a delay in one area from stopping the whole joinery package.
  • Pack by room. Bodies, leaves and hardware labelled per room number rather than per product line, so installers are not sorting crates in a corridor.
  • Inspect on arrival. Check mirror edges and leaf corners before the crates leave the loading area; damage reported after unpacking is much harder to resolve.

Spare quantities matter more here than for most items. Order one spare mirror leaf per bedroom group, plus an extra hardware set per ten openings. That small buffer turns a site stoppage into an afternoon's work.

A Simple Checklist Before You Release The Order

  • Every opening has three heights and two widths recorded, with the smallest used for the carcass.
  • Bodies, leaves, hardware sets and interior fit-out are counted separately.
  • Mirror type, frame colour and hardware finish are named once per room group.
  • Corner returns and non-sliding mirrored items sit on their own schedule page.
  • Flooring build-up, soffit detail and electrical positions are shown on the same drawing as the wardrobe setting-out.
  • Spare leaves and spare hardware are in the same consignment.

If you are pricing a villa or apartment package and want the wardrobe quantities checked against your drawings, send us the room schedule with opening dimensions and finish preferences. We will return a body-by-body breakdown for the sliding wardrobe range, with the interior fit-out listed separately so you can see exactly what each opening includes.