Sliding storage panels look simple on a drawing — a set of panels, two tracks, done. On site they are one of the easiest built-in items to get wrong, because the panel size, the track layout and the cabinet behind them are decided by three different suppliers at three different times. This guide walks through how we quantity-take and coordinate Santerson Sliding Storage Panels on villa and apartment projects, so the order you release is the order that fits.

What actually makes up a sliding storage panel wall

Before counting anything, agree what is included. A sliding storage wall in our built-in furniture range is made to measure: the panels, carcasses, shelves and finishes are all specified per project rather than picked from fixed sizes. In practice one installation breaks down into:

  • Sliding panels — the moving fronts, including their core, face material and edge detail.
  • Track and hardware — top and bottom tracks, hangers, buffers, handles or recessed pulls, plus any flush or overlap detail between panels.
  • Carcass and internal fit-out — the storage behind the panels: shelving, drawers, hanging rails, display niches or hidden cabinets.
  • Fixed frames and infill — reveals, end panels, scribes to wall and ceiling, and any matching panelling that makes the wall read as one surface.
  • Openings and services — skirting breaks, architrave stops, sockets, switches, cabling and integrated lighting.

Where a wall also carries a television or display, we usually split it between the storage-wall scope and the media-wall scope. Santerson Sliding Panel TV Systems covers the panel-and-screen combination; a plain closed wall is quoted as sliding storage panels. Say which one you need in the enquiry, because the two carry different clearances.

Step 1: take quantities from the opening, not from the panels

Count in this order, and record each figure on the drawing:

Item to measureWhat to recordWhy it matters for ordering
Clear opening widthFinished-wall-to-finished-wall width, at floor level and at head heightSets the number of panels and their individual width; walls are rarely square over a long run
Clear opening heightFinished floor to finished ceiling, checked at both ends of the runDetermines panel height and whether a top scribe or full-height frame is needed
Reveal depthDepth available for track plus carcass, at the shallowest pointDecides track type, sliding vs. pocket detail and door overlap
Panel count and coverageHow much of the opening must be open at once, and how much closedDrives panel widths, stacking side and whether panels need to pass each other
Adjacent finishesFlooring, skirting, plaster or cladding meeting the wallDetermines where tracks sit and who stops each finish

A common mistake is to quantity from a plan dimension that was drawn before the flooring and plaster were added. Take dimensions off the finished construction lines, or state on the enquiry which finishes are not yet included.

Step 2: turn elevations into a panel schedule

Once the openings are known, produce a one-line-per-panel schedule. We ask project buyers for this before we quote, and it is what prevents the "nine panels ordered, seven fit" problem. Each line should show:

  • Room and wall reference from the drawing set;
  • Panel width and height, plus the stack direction;
  • Face material and finish code, so matching panels in other rooms are not re-specified separately;
  • Hardware line — track type, hanger capacity, handle style;
  • Internal configuration behind that panel (shelves, drawers, hanging, niche).

If the same finish has to continue into wardrobes or cabinetry elsewhere in the property, list those rooms on the same schedule. Panels, closet sliding panels and wardrobe fronts ordered together come from one production batch, which is what keeps grain direction and colour consistent across the storey.

Step 3: coordinate the interfaces before releasing production

Quantity work is only half of it. The items below are the ones that cause variation orders later, so we settle them at the design stage:

Floor and track interface

Decide whether the bottom track sits in the finished floor or on top of it. Recessed tracks need to be set before the flooring goes down, which means the track drawing has to come out ahead of the floor order. Surface-mounted tracks are simpler but change the threshold detail at doorways.

Ceiling and head restraint

Top tracks hang from a structural fixing or a built-up frame. Confirm what is above the ceiling line, and whether the framing is ours, the main contractor's or the joiner's. On site this is the single most common coordination gap.

Storage behind the panels

The internal layout changes the carcass depth and therefore the panel overlap. A wall mixing open shelving with closed storage — see Santerson Mixed Open & Closed Storage — needs the niche positions fixed early, because lighting and sockets follow them.

Matching adjacent products

Where a storage wall meets Santerson Full Height Storage Walls or a media wall, note the junction detail and who supplies the transition trim. Two systems ordered separately often arrive with slightly different panel thicknesses.

Sliding doors vs. storage panels

If part of the run is an actual room divider or doorway rather than a storage front, quote it as a sliding door — Santerson Wooden Sliding Doors and Partition Sliding Systems carry different hardware and different safety details from a storage panel.

Step 4: order in packages that match the site programme

Because these are made-to-measure items, split the order so it lands when the trades need it rather than all at once:

  • Package A — tracks and frames: released as soon as openings are fixed, so the builder can set recesses and structural fixings.
  • Package B — carcasses and internals: after the wet trades and floor finishes are complete and levels have been re-checked.
  • Package C — panels and hardware: last, once paint and flooring are protected, to avoid damage during other works.

We handle this through our logistics and door-to-door delivery service, packing each room's panels as a labelled set so the fitter is not sorting a mixed container on site.

A practical quantity checklist

  • Opening width and height taken off finished construction lines, at both ends of the run
  • Panel schedule issued — one line per panel, with finish code and hardware line
  • Internal configuration fixed per panel before carcass depth is set
  • Track fixing method agreed and drawn, with the responsible trade named
  • Floor threshold detail resolved: recessed or surface-mounted bottom track
  • Matching finishes grouped into one order batch across rooms
  • Junction details to adjacent storage, media and wall panelling recorded
  • Delivery split by package against the site programme

Getting a quotation that comes back complete

Send the panel schedule, the marked-up elevations and the interface notes together. With those three documents we can confirm panel sizes, hardware and internal fit-out in one pass, and flag anything that needs site verification — such as out-of-plumb walls or a shallow reveal — before production rather than after. As part of our turnkey solutions for villa and hospitality projects, the same team coordinates the storage wall against flooring, wall finishes and lighting, so the schedule stays one document instead of four.

Panel sizes, material options, hardware selections and track details are confirmed for each project; the figures on your drawings govern the order.