A swim spa is easy to leave out of a materials schedule until the wet trades are already moving. Then it becomes a problem nobody priced: an item that needs power, a base, access for delivery and a plant room plan. This article uses one specific unit in our range, Outdoor Swim Spa WS-115AⅢ-U, to show how a single pool item can be carried through a whole-project materials schedule alongside furniture, joinery and finishes — from first specification to handover.
Why swim spas fall out of the schedule
On most villa and resort packages the schedule is built around rooms: cabinetry here, flooring there, lighting and sanitaryware listed against each space. A swim spa does not sit in a room. It sits on an external slab or deck, next to paving, screening, outdoor furniture and sometimes a pergola. Because it crosses several trade packages at once, it is often recorded as "to be confirmed by others" and stays that way until someone asks who is supplying it, who is wiring it and who is protecting it on site.
The fix is procedural rather than technical: give the swim spa its own line in the schedule, with the same fields every other long-lead item carries — supplier, model, dimensions, power requirement, delivery lead time, storage location on site and the trade responsible for the base, the electrical connection and the commissioning witness.
What the WS-115AⅢ-U record should carry
The values below are the catalogue entries we publish for this model. Put them in the schedule as a starting point, then have the selected configuration confirmed before any electrical or civil work is priced.
| Schedule field | Catalogue entry for WS-115AⅢ-U |
|---|---|
| Model | WS-115AⅢ-U |
| Overall dimensions | 3880 × 2200 × 1250 mm |
| Jet total | 23 pcs |
| Water pump / filter pump | 4 pcs / 1 pc |
| Control system | 1 set |
| LED lights | 1 pc |
| Total power | 11.85 kW |
| Features shown | Water jets, LED lighting, Ozone |
| Swim training system | Not listed for this model — confirm before specifying swim training use |
Two of these lines change how the rest of the schedule behaves. The footprint, 3880 × 2200 × 1250 mm, determines the slab or pedestal, the surrounding paving setout and the delivery route to the site. The total power figure of 11.85 kW determines the circuit, the distribution board position and whether the electrical package needs a dedicated run from the main switchboard. Neither should be added late.
Working backwards from the wet trades
Once the swim spa has a line in the schedule, sequence it the way you would sequence joinery: fix the specification, then let the dependent trades work backwards from it.
- Structure and paving. The unit's footprint and access route are set before the surrounding deck is detailed. Paving levels, drainage falls and any inspection chamber are coordinated against the shell dimensions rather than drawn independently.
- Electrical. Power requirement, cable route and isolator position follow from the confirmed configuration. Where a heat pump or extra pumps are added later, the electrical package has to be re-priced — which is exactly why the option list should be settled before tender.
- Water treatment and drainage. Ozone is shown as a feature on this model; sand filtration is an option on the range. Backwash and overflow routes need to exist before the hardscape is laid.
- Adjacent product packages. Poolside loungers, pergolas, screens and outdoor dining from our outdoor furniture range are set out around the shell, not after it.
- Site protection. A delivered spa shell sitting on an active site for weeks needs storage and protection agreed in advance, with a named responsible party.
Where it belongs in a one-stop package
Projects that buy furniture and finishes from several suppliers usually handle the swim spa badly: no single party owns the interface between the shell, the plant and the surrounding works. We work as a one-stop furniture and building materials supplier, so the same procurement file covers the spa, the outdoor furniture around it, the pergola, the wall cladding behind it and the interior fit-out beyond the glass. That is what keeps one person accountable for the interface dates.
For turnkey villa and hospitality projects, we run the swim spa through the same workflow as the rest of the package — design and specification, production, logistics, installation support and after-sales. The logistics and door-to-door delivery arrangements cover freight by sea, air or rail with the associated paperwork; for a spa shell, the practical question on that stage is whether the delivery vehicle can reach the prepared position, so access is confirmed at the same time as the order rather than at delivery week.
A short checklist for the scheduler
- Record the model number in the schedule, not "swim spa TBC" — the model carries the dimensions and power figure everything else depends on.
- List optional equipment as priced alternatives with a decision date, so the electrical and civil packages are not re-tendered mid-build.
- Name the trade responsible for the base, the electrical connection, the commissioning witness and site protection between delivery and handover.
- Coordinate poolside furniture, screening and paving setout against the shell dimensions in the same drawing package.
- Keep the manufacturer's configuration confirmation on file with the schedule revision; specification changes should be visible as revisions, not emails.
Before you lock the line item
Send us the drawing package and the intended location for the unit. We will confirm which configuration applies to your project — including pumps, treatment options, insulation and steps — so the dimensions and power load in your materials schedule match what actually arrives on site. The full swimming pools and swim spas range is published on the site if you are comparing footprints across models.
Specifications shown are catalogue entries for WS-115AⅢ-U and apply to that configuration. Included equipment, electrical requirements and options vary by selection and must be confirmed before ordering or pricing dependent works.