A 7.5-metre outdoor swim spa does not arrive as one crate and leave the site ready to swim. Delivery, site preparation, power, lifting and commissioning all have to line up with each other, and the party that pays for a mismatch is usually the buyer. This guide walks through how we sequence those steps at SANTERSON for the Outdoor Swim Spa WS-PC07ST-L, and what your side of the project needs to decide before the spa leaves the factory.
Why this model needs a delivery plan, not just a shipping quote
The catalogue lists the WS-PC07ST-L at 7490 × 2400 × 1470 mm, and we work to the confirmed configuration sheet rather than that figure alone when planning the route. That footprint moves it out of ordinary parcel freight and into containerised cargo with lifting equipment on both ends, and the length matters most: it drives the container type, the route from the port to the site, the turning radius on a driveway, and whether the unit can pass a gate or has to be craned over it.
The configuration also carries permanent equipment — control system, swim training unit, filter pump, jets and lighting. Once those are fitted, the spa is not something you can tip on its side to get round a corner. So we treat the delivery route as part of the product specification, and we confirm it before production closes.
Step 1: Lock the configuration before the freight is booked
Options change both the weight and the services the site has to provide. Before we quote freight, we need the final option list agreed on the purchase order.
- Heating choice. Heat pumps and water heaters draw current very differently, so the electrical service you install depends on which one is on the order. Confirm the heating equipment for your configuration before your electrician prices the supply.
- Filtration route. The filter pump is fitted to the unit; a sand filtration option adds a separate vessel, its own position on the plant pad and its own pipework run.
- Insulation package. Insulation affects how the spa is crated and how it behaves between delivery and commissioning in a cold season.
- Steps. Steps are an option rather than part of the shell, so they need to be on the order before the packing plan is drawn up.
We list these options — control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps — on the product page, but availability differs by model. Confirm the exact set for your configuration with our project team rather than assuming a bundle carries over from another size.
Step 2: Confirm the site can carry it and serve it
Two questions decide whether the spa works on the day it arrives:
- Can it get there? Measure the route, not just the plot: container access to the street, truck turning space, gate widths, overhead cables, and the final carry or lift onto the slab.
- Can the slab take it? A full shell of this size is a heavy load. Your structural engineer signs off the pad, the perimeter support and any buried plant pit — that is local work we do not design for you, and it needs to be cured before the spa lands.
Electrical work follows the same rule. The site electrician provides the supply, protection and bonding to their own national and local requirements. We send the equipment schedule for the agreed configuration so they are wiring to real data, not a catalogue average.
Step 3: Choose the freight leg that fits the site
Our logistics and door-to-door delivery service covers sea, air and rail freight forwarding, customs paperwork such as commercial invoices, packing lists and certificates of origin, packaging and container loading plans, shipment tracking and delivery to the site address. For a swim spa of this size the practical choice is almost always a sea container, with inland transport arranged to the project address.
Three things have to come from your side before we can book that leg:
- The exact delivery address and whether large vehicles can reach it;
- Who provides the crane or forklift on site, and its safe working load;
- Your import arrangements — duties, clearance agent and any permits required locally.
Import terms, Incoterms, transit time and insurance scope are agreed case by case for each project. We will not commit to a landed cost or a delivery date until the route is confirmed, because both change with the port and the final address.
Step 4: Plan the set-down as a scheduled operation
The day the container arrives, four things have to be present at once: the lifting equipment, the prepared base, the electrical rough-in complete, and someone from your side to sign the goods in. We schedule the delivery window against that checklist instead of shipping on production completion alone.
| Item to confirm | Who owns it |
|---|---|
| Container route, port and inland transport | SANTERSON logistics team, with your clearance agent |
| Crane / forklift hire and lift plan | Buyer's local contractor |
| Concrete pad, drainage and plant position | Buyer's civil contractor, engineer-signed |
| Supply, protection, bonding and earthing | Buyer's licensed electrician |
| Equipment schedule for the agreed configuration | SANTERSON |
| Water fill and drainage connection | Buyer's plumber |
Step 5: Commissioning, inspection and handover
Setting the shell is only the start of installation. Our installation and after-sales support service covers on-site installation, inspection and snag lists, warranty coverage, spare parts and replacement, and ongoing maintenance.
Before our team or your contractors energise anything, the site side has to be finished: supply, protection, bonding and earthing installed by a licensed electrician; water fill and drainage connected; the filter pump, jets, swim training unit and lighting positioned and accessible for testing. The handover itself is then a check of each item on the equipment schedule against what was actually supplied, followed by a snag list signed off in writing.
Response times and warranty terms are set out per project. Ask for them in writing on the purchase order rather than relying on website copy, so the scope of after-sales support is unambiguous when you need it.
A sequence you can put straight into your programme
Before production: agree the option list; receive the configuration sheet; engineer signs the pad; electrician prices the supply.
Before shipping: confirm crated dimensions and weight; book the container and inland route; identify who lifts on site; settle import paperwork.
Before the truck arrives: pad cured; electrical rough-in, bonding and drainage complete; lifting gear booked; a receiver present.
After set-down: complete the electrical connection and water fill; check every item against the equipment schedule; sign off the snag list.
Where this product sits in our range
The WS-PC07ST-L is one variant in our swimming pools and swim spas category, which also covers shorter shells in the same PC series for sites with a tighter approach. As a China-based furniture and building materials manufacturer working on villas, resorts and hospitality projects, we supply the spa as part of a wider package — outdoor furniture for villas and resorts, pergolas and loungers, wall panels and ceiling finishes, bathroom fixtures and lighting — which is why one coordination plan usually covers more than the spa itself.
If you are comparing shell sizes against a real site, send us the plan drawing and we will tell you which variant the access route actually supports.
Send us your site plan and delivery address. Our project team returns the feasible model options, the configuration sheet for electrical pricing, and a door-to-door freight plan. Contact PHILLIP on WhatsApp +86-13928214007 or santerson@qq.com, or use our contact page.