A two tone melamine wardrobe looks effortless once it is in place: a lighter field, a darker accent, clean lines that carry through the whole bedroom wall. Getting there is what separates a smooth site programme from a joinery package that stalls on site. An installation plan is where that work happens — before the first panel is cut, and long before the delivery container is booked.

For villa and apartment projects, we see the same avoidable problems repeat: doors ordered to a swing clearance that was never checked, carcass depths set before the skirting and cornice were surveyed, and accent colours approved from a sample off a different board run. Below is the plan structure we ask our project clients to sign off on two tone melamine wardrobes packages, written so a site team, an interior designer and a procurement manager can all work from the same document.

1. Scope, room schedule and who signs what

Start with a room-by-room schedule rather than a single wardrobe count. For each wardrobe record the room or apartment reference, the run length, the height available at the ceiling line, and whether the unit is built into a recess, boxed out to the slab, or free-standing. Built-in joinery in particular is measured against what the building actually gives you — floor levels, wall straightness, cornices and skirting boards all change the finished set-out.

Then name the decision-makers on one page: who approves the elevation drawings, who signs off the finish samples, who accepts delivery on site, and who is responsible for the setting-out builder's work. Half of the disputes we see in cabinetry packages are not technical — they are about nobody having owned a decision at the right time.

2. Survey data and dimensional sign-off

Two tone wardrobes are unforgiving of rough dimensions, because the contrast between the two finishes draws the eye along every horizontal line. The survey section should record:

  • Length, height and depth at multiple points along the run, not one average figure — walls out of plumb are normal in older villas and need to be built into the set-out.
  • Ceiling and floor levels across the run, plus the position of cornices, skirting, architraves and any bulkheads.
  • Obstructions: power points, switch plates, air-conditioning returns, downlights, door openings and their swing arcs.
  • Floor covering build-up and its final thickness, which decides whether the carcass sits on adjustable levelling feet or a plinth.
  • Clearance in front of the wardrobe, and the traffic route the assembled panels will travel along on delivery day.

Because our wardrobes are made to measure with layout tailored to each project, these dimensions become production data once they are signed. Anything changed after sign-off is a variation, so it is worth spending an extra hour on the survey rather than several weeks on rework.

3. Door system and clearance logic

The door system should be decided before elevations are drawn, not after. It drives the set-out, the internal configuration and the room's usable floor area.

Door systemWhat to confirm in the plan
Hinged doorsFull swing arc against beds, side tables and the room door; handle projection into the room; whether an adjacent door leaf fouls a wall or reveal.
Sliding doorsTrack depth at the head and sill, overlap between leaves, wall strength to carry the head track, and clear floor space for the panel travel. A two tone sliding door wardrobe suits narrow walk-in robes and bedroom walls where a swing arc cannot be accommodated.
Walk-in / open layoutPassage width between runs, lighting positions, and whether the opening is dressed with a frame or left as an architectural reveal.

4. Internal configuration and storage zoning

The two tone look sits on the outside; the plan has to be right on the inside. Split each run into hanging, drawer and shelf zones by how the space will actually be used, and record heights for each:

  • Single-hanging and double-hanging runs with their rail heights.
  • Trousers pull-outs, tie and jewellery trays, and shoe storage depth.
  • Open shelves for folded stacks, with a note on which bays stay open and which close behind doors.
  • Lighting provision — door-triggered, motion-sensor or always-on — with the wiring route, transformer location and access point for maintenance.

Where a project needs something beyond the standard catalogue layout, that is exactly what custom furniture design and prototyping covers: bespoke layouts, material and finish choices, and 3D modelling before production starts.

5. Finish schedule and sample approval for the two tone combination

This is the section most often left vague, and it is where a two tone scheme either reads as deliberate or falls apart. Record for each wardrobe:

  • The field colour and the accent colour, and which surfaces carry which — door fronts versus carcass, tall bays versus base run, interior versus exterior.
  • Surface texture: matte, gloss or woodgrain. Within the same melamine range you can specify matte finish melamine wardrobes, glossy fronts, or wood grain melamine wardrobes paired with a solid accent.
  • Edge banding colour and thickness, and whether edges match the face exactly or are intentionally contrasted.
  • Hardware: handle profile, hinge and slide brand as specified on the order, plus integrated handleless profiles where the design calls for them.
  • Who receives physical samples, from which board batch, and by what date approval must return.

A practical rule: approve the two tone combination on a sample that shows both finishes side by side under the room's actual lighting, not as two separate swatches. A pairing that looks balanced in a showroom can read as mismatched against warm bedroom downlights.

Coordination tip: keep the wardrobe finish schedule and the kitchen finish schedule in one document when both are supplied on the same project. The two tone melamine cabinets in the kitchen usually need to echo the wardrobe palette, and matching them at specification stage avoids two separate sampling rounds.

6. Site preparation and readiness dates

Wardrobe installation is a follow-on trade, so the plan needs a site-readiness date as well as a delivery date. Confirm in writing:

  • Floors level and finished, walls rendered and set out to the agreed datum line.
  • Electrical first fix complete for internal lighting, with wiring tested before boxing-in.
  • Silicones, paint touch-up and skirting replaced or noted as to be cut in after installation.
  • Storage area on site that is dry, secure and large enough for the panel delivery — built-in joinery cannot be left in a corridor overnight.
  • Access: lift dimensions, stair widths, door thresholds, and whether panels need to be brought in flat and assembled in room.

7. Packaging, delivery sequence and unloading

For international projects the plan should mirror the logistics reality rather than an ideal schedule. Record the container or shipment reference, the door-to-door delivery arrangement, expected arrival window, who clears customs, and who signs the packing list on site. Panel packages arrive numbered against the room schedule, so a mismatch between the site document and the crate labels costs hours at the loading dock.

Sequence deliveries by zone: install one complete run before moving to the next rather than unloading an entire apartment floor at once. It keeps the working area clear, protects finished panels, and lets defects be caught while there is still time to correct them in production.

8. Installation method, tolerances and snagging

Set out the installation sequence explicitly so the on-site team and the client agree on what "complete" means:

  • Setting-out line marked on walls and floor; carcasses levelled and fixed to suitable substrate, with fixings suited to the wall build-up.
  • Doors hung and adjusted for parallel gaps, then re-checked after the room has been used for a few days.
  • Silicone and trim lines matched to the finish schedule; no visible fasteners on show faces.
  • Drawers, slides and lighting operated through a full cycle before handover.
  • A snag list signed off with photographs, plus the process for spares and replacement parts if anything was damaged in transit or on site.

Where we support installation and after-sales on a project, this snag list is the reference document — which is why it should be produced jointly on the day, not emailed a week later.

9. Programme, variations and handover records

Close the plan with dates in one table: survey complete, drawings issued for approval, finish samples approved, production released, shipment booked, site ready, installation start, snag close-out, handover. Attach the drawing register and state how late changes are handled — a colour swap after sample sign-off is cheap; a depth change after production release is not.

Handover records worth keeping: signed elevations as built, the finish schedule with sample references, the packing list, and the snag close-out sheet. For a rental or resale villa these documents make life easy for whoever maintains the joinery next.

Common gaps we see in wardrobe installation plans

  • No door swing check. The design is approved, then a hinged leaf fouls the bed or the room door on site.
  • One dimension for a whole run. Out-of-plumb walls turn a single average measurement into gaps at the ceiling line.
  • Finishes approved flat, not paired. The two tones are signed off separately and only meet for the first time on the finished wall.
  • Electrical work scheduled after boxing-in. Lighting provision has to be in before the carcass is closed up.
  • No site-readiness date. Panels arrive to a floor that is still being tiled.

Planning a joinery package for a villa or apartment project?

SANTERSON supplies made-to-measure wardrobes, cabinetry and the rest of the interior fit-out from one programme — design coordination, production, quality control and door-to-door delivery. Send us your room schedule and elevations and we will return a wardrobe package with the finish schedule and installation sequence built in.

Phone / WhatsApp: +86-13928214007 (PHILLIP)  ·  Email: santerson@qq.com  ·  Contact page