A swim spa shell arrives on a pallet, gets craned onto a slab and is plugged in the same afternoon — that is the fantasy. The Outdoor Swim Spa WS-115FⅢ is a 5000 × 2200 × 1250 mm vessel carrying a control system, a swim training unit, a water pump, a filter pump, twenty-four jets and four LED lights. Treating it as a drop-in product is how projects end up with an underpowered circuit, no drainage route and a shell that cannot be reached again after the paving goes in. Below is the checklist we ask buyers and contractors to complete before the spa ships.

1. Confirm the configuration before you plan anything else

The catalog listing for WS-115FⅢ shows a total power figure of 8.05 kW, but options such as a heat pump, UV sterilisation, sand filtration and extra insulation change both the electrical load and the physical footprint. Two identical model numbers ordered by two different villas can arrive with different equipment sets. Get the final bill of materials in writing first, because the electrical schedule, the equipment-room location and the crane plan all depend on it.

  • Included versus optional items: control system, swim training system, water pump, filter pump, jets, LED lighting, ozone, heat pump, UV sterilisation, sand filtration, insulation, steps.
  • Total connected load for the confirmed specification, not the catalog baseline.
  • Shell dimensions plus clearance needed for the filter pump and control panel access.

2. Site, foundation and drainage

A spa of this size holds a large volume of water, so the ground under it matters far more than the ground under a patio set. The installation drawing should record the finished slab level, the slab reinforcement as specified by the local structural engineer, and how the shell will be reached — over a wall, through a gate, or by crane before the roof structure closes in.

  • Slab design signed off locally against the shipped operating weight; we supply dimensions and weights, the engineer sizes the slab.
  • Access route surveyed with the actual delivery vehicle and lifting equipment in mind.
  • Drainage for a full drain-down, plus an overflow path that does not run across a neighbour's boundary or a pool deck.
  • A service zone left clear around the pumps and control system — removable paving sections are usually cheaper than a second visit.

3. Electrical work: the part most plans get wrong

The 8.05 kW baseline in the catalog is an indicator, not a design value. Your electrician needs the nameplate data of the confirmed configuration and must design to local wiring rules, including the correct circuit rating, protective earthing, residual-current protection and isolation for a wet installation. We confirm equipment ratings; we do not certify compliance with another country's electrical code.

  • Dedicated circuit sized from the confirmed configuration's nameplate data.
  • Isolator placed within reach of the control system but outside the spa splash zone.
  • Cable route, conduit and containment shown on the drawing before tiling or paving is laid.
  • Supply capacity checked against the rest of the building load, especially where a heat pump is added.

4. Water supply, filtration and water treatment

WS-115FⅢ is listed with one filter pump, ozone treatment and optional UV sterilisation and sand filtration. The plan should show where cold water enters for filling and top-up, where the drain line goes, and how chemicals are stored and dosed. If the site runs on bore water or hard mains supply, raise it early — scaling changes both maintenance frequency and element life.

5. Logistics, customs and the delivery window

For an overseas project, the installation plan starts at the port. Our logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, commercial invoices, packing lists, certificates of origin and shipment tracking. Confirm the Incoterms, who handles customs clearance, and whether the quoted delivery includes lifting gear on site — a spa shell is not a parcel.

6. Commissioning, handover and after-sales

Handover should be documented: jet and swim-training operation tested, control system settings recorded, filtration cycle agreed, and the maintenance routine explained to whoever will actually run it. Our installation and after-sales support covers on-site installation, inspection and snags, warranty coverage, spare parts and ongoing maintenance; the specific terms are set per project, so read them against your own schedule rather than assuming standard conditions.

Buyers comparing several units should review the full Swimming Pools and Swim Spas range, since a longer spa with a separate relaxation pool may suit a resort deck better than a single-vessel unit.

Quick pre-shipment checklist
Confirmed equipment list and nameplate load · slab engineered for operating weight · access and crane route surveyed · drainage and overflow designed · electrical schedule with isolator location · water supply and top-up point · chemical storage location · delivery terms and lifting arrangements · commissioning record and maintenance routine.
Send us the site drawing. Share the plan, the confirmed configuration and the delivery destination, and our project team will return the equipment schedule, dimensional drawings and a quotation that matches what actually ships. Contact SANTERSON — phone / WhatsApp +86-13928214007 (PHILLIP), email santerson@qq.com.