A wall mounted bar unit looks like a small item on a villa or apartment fit-out schedule, and that is exactly the problem. Because it reads as minor, it tends to be scheduled late, specified loosely, then discovered on site when the wall finish is already complete and the fixing substrate is wrong. This guide walks through how we place Santerson Wall Mounted Bar Units in a materials schedule that covers the whole project, so the unit arrives with the rest of the joinery, on the same submittal cycle, and is fixed into a wall that was prepared for it.

Why the bar unit belongs in the master schedule, not a late add-on

A suspended cabinet carries bottles, glassware and often a small appliance tray. Its load path goes through the wall, not the floor, so the wall build-up has to be decided before the wall is closed. If the bar unit appears on a purchase list after partitions are set out, one of two things happens: the fixing detail gets re-engineered around whatever is already there, or the unit sits proud of a finished surface and the reveal has to be trimmed on site.

There is a second reason to schedule it early. In our range, these units are made-to-measure — size, layout, material and finish are set per project rather than picked from a fixed catalogue width. That means the bar unit runs through the same shop-drawing and approval cycle as kitchen cabinetry and wardrobes. Scheduling it with those trades keeps one drawing review, one approval signature, one production slot.

The practical rule we work to: if an item needs shop drawings, it belongs in the same submittal register as the rest of the built-in joinery. Wall mounted bar units clear that bar, so they are opened with cabinetry and not after it.

The five columns we fill in before anything is ordered

A materials schedule entry for a suspended unit needs enough detail that the site team, the wall contractor and the factory are all reading the same instruction. In our submittals we complete these fields:

  1. Location and room reference. The room code from the drawings, plus the wall elevation number. A bar unit on a living-room party wall and one on a lightweight partition are different fixing problems.
  2. Set-out dimensions. Finished width and height, projection from the finished face of the wall, and the level of the underside above finished floor. Projection matters because it governs circulation past the unit and whether it reads as flush with adjacent cabinetry.
  3. Substrate note. Who provides the reinforcing or blocking behind the finish, and at what stage. This column is where most schedules fail; leaving it blank pushes the problem onto the installer.
  4. Finish and material reference. The board, veneer, lacquer or laminate reference used elsewhere on the project, so the unit matches adjacent tall cabinets and media walls rather than being matched by eye later.
  5. Interfaces. Lighting feed, socket position for any appliance tray, and whether glass-fronted doors sit against a lit niche. Interfaces are listed even when another trade executes them.

Reading the Bar Cabinets family as one schedule group

Santerson's bar cabinets are catalogued as a set of configurable types rather than fixed models, which makes it easier to give each project position a matching format and keep them all on one line of the register:

TypeWhere it normally lands in a projectSchedule note that saves time
Wall Mounted Bar UnitsLiving rooms, media walls, entertainment zones, study and office pantries where floor space is better left clearAdd the substrate column now; blocking must be set before wall closure
Island Bar UnitsOpen-plan kitchens and entertaining islandsCoordinate with the island carcass so one drawing covers both
Tall Bar CabinetsPantry runs, scullery walls, guest-suite storageConfirm the tall unit's finished depth so returns align
Compact Bar CabinetsGuest bathrooms, small studies, short corridor runsUseful where a full-height unit would crowd the room
Glass Front Bar CabinetsDisplay positions, lounge and dining wallsList interior lighting feed in the interfaces column
Integrated Bar SystemsFull entertainment or media walls combining bar, storage and displaySpecify as part of the wall system so one trade carries it

Grouping them this way has a procurement benefit beyond tidiness. When a project uses a wall mounted unit in the lounge and a tall cabinet in the pantry, both can be produced from the same material and finish batch, which is the only reliable way to avoid a visible tone difference between two cabinets on the same wall.

Coordinating the wall before the unit arrives

Substrate and fixing

For a suspended unit we ask for solid blocking or a reinforced zone at the fixing line, set out from the shop drawing and confirmed on site before the wall finish is closed. On masonry this usually means an anchor detail agreed with the wall contractor; on stud partitions it means timber or steel noggin at the exact heights shown on the drawing. Either way, the note travels with the schedule entry, so the wall crew treats it as part of their scope instead of discovering it.

Services and lighting

Bar positions usually carry at least one socket — a wine fridge, a blender, a coffee machine — and often concealed interior lighting. We record the feed position on the shop drawing and hand that drawing to the electrical contractor during coordination, rather than sending a separate note after first fix. Where the unit sits inside a wider lit composition, it can be scheduled alongside integrated cabinet lighting so one detail covers driver location and access.

Adjacent finishes

A wall mounted unit usually reads best when it aligns with something: the head of adjacent cabinetry, a reveal in wall panel systems, or the shadow line of a media wall. Those alignment dimensions come from the joinery drawing, so the panel and panelling trades receive it at the same time as the cabinet maker.

Where this fits in a one-stop procurement flow

For projects sourcing furniture and building materials together, the bar unit is normally specified during the material selection and product specification stage, then confirmed through detail drawings before production. As a furniture and building materials manufacturer handling design, production and delivery under one contract, we can hold the wall mounted unit in the same production release as kitchen cabinetry and wardrobes, which removes the separate purchase order that so often arrives too late to influence the wall build-up.

For villa and apartment work in Australia, this grouping also simplifies freight: the suspended unit ships with the joinery consignment under one packing list rather than as a later part shipment. Import terms, duties and delivery scope are confirmed project by project, so we treat them as schedule items to be agreed, not assumptions.

A pre-order checklist

  • Room reference and wall elevation number recorded against the schedule line.
  • Finished width, height, projection and underside level confirmed on a drawing, not estimated.
  • Substrate or blocking responsibility named, with the stage it happens at.
  • Finish reference matched to the adjacent cabinetry batch.
  • Electrical feed and lighting driver access shown on the same shop drawing.
  • Unit included in the joinery production release, not ordered separately later.

Confirming your configuration

Dimensions, materials, finish and storage layout for a wall mounted bar unit are set per project, so we confirm them against your drawings before quoting. Send us the room elevation and the adjacent cabinetry specification, and we will return a shop drawing with the fixing zone marked, ready to hand to your wall contractor.

Start with the Wall Mounted Bar Units product page and the wider product range, then send drawings through our contact page.