A solid colour acrylic door panel looks simple on a rendering: one flat, saturated surface with no grain and no pattern to hide behind. That is exactly why the finished kitchen either matches the drawing or exposes every deviation. Before any panel is cut, the following decisions need to be closed out in writing, not left for the production floor to interpret.

1. The colour itself, not just the colour name

A written shade name is not a specification. Acrylic sheet from different batches can sit slightly apart in tone, and the same reference reads differently under warm 2700K downlights than under cool daylight from a north-facing window.

  • Fix the reference: RAL, Pantone or a physical acrylic swatch from the actual sheet supplier.
  • Ask which side of the panel is glossy and whether the reverse matches — relevant when a cabinet returns into an open-plan view.
  • Order one physical sample panel in the chosen shade and view it on site, next to the worktop, splashback and wall paint, before signing off.

Our Solid Color Acrylic Cabinets are made to measure with the finish selected per project, so the shade reference belongs on the drawing pack rather than in an email subject line.

2. Gloss or matte, and how edges are handled

Two different products often sit under one name. A high gloss acrylic front behaves very differently from a Matte Acrylic Cabinet front in a busy kitchen: gloss reflects light and fingerprints, matte absorbs both but shows scuffing along an unprotected edge.

  • Confirm the wrap method on all four edges, and what the corner radius is. Sharp mitred corners chip in transit; large radii read as a rounded, softer profile.
  • Decide where the anti-fingerprint or protective film stays during installation and who removes it.
  • Agree how a damaged door is remade later — same batch reference, same edge detail, same hardware hole pattern.

3. Substrate, door thickness and hardware interface

The acrylic is a facing; the board behind it carries the load. Door thickness and substrate decide hinge cup depth, handle drilling and how the front sits against an appliance.

  • Confirm substrate type and door thickness in millimetres on the shop drawing.
  • State the hinge brand and model, soft-close or standard, and whether handles are routed, integrated or omitted for a handleless run.
  • Give appliance models early so cut-outs, ventilation gaps and door overlaps are dimensioned once instead of corrected twice.

Where a project mixes finishes — for example gloss uppers with matte lowers — the same rules apply to each run. Our High Gloss Acrylic Cabinets and matching ranges are specified by project, so mixed-finish sets should be shown as separate schedules on one drawing pack.

4. Site dimensions, tolerances and the interface trades

Custom sizing only works when the measurement is taken at the right moment. Confirm who measures, when, and what has already been finished: plaster, tiling, screed and the electrical first-fix all change a critical dimension by centimetres.

Item to confirmWhy it matters before production
Floor finish level and skirting treatmentSets carcass height, plinth detail and whether toe-kicks are scribed on site
Wall flatness and out-of-plumb readingsDetermines scribing allowance and filler panel widths beside the run
Window reveals, radiators, switches and socketsPrevents doors fouling a handle or a socket plate on opening
Worktop thickness and splashback materialFixes the height of wall units and the shadow gap under them
Access route to the propertyLargest assembled unit must fit lifts, stair turns and doorways

Send the drawing pack back with those dimensions initialled by the site contact. A correction made on paper costs minutes; the same correction after pressing costs a replacement panel.

5. Packaging, sequence and what arrives together

Cabinetry for a whole kitchen rarely travels as one pallet. Confirm the packing list by unit number, matching the drawing numbers, so the installer can follow the same sequence on site. Gloss fronts need edge protection and separation between panels, and glass or appliance deliveries should be scheduled so they do not sit in the same room while carcasses are being levelled.

Practical rule: if a decision would change the appearance of the finished kitchen or the cost of remaking it, it belongs in the pre-production confirmation sheet. Anything verbal gets restated in writing and returned before the order is released.

Before you release the order — a short checklist

  • Shade reference and physical sample approved on site, in the actual lighting
  • Gloss or matte confirmed per run, with edge and corner detail agreed
  • Substrate, door thickness, hinges and handle method stated on the drawing
  • Appliance models, worktop thickness and splashback fixed
  • Site dimensions re-measured after first-fix, and signed off
  • Packing list keyed to drawing numbers, with access route checked

SANTERSON manufactures made-to-measure cabinetry for residential and project kitchens, from the finish sample through production, packing and delivery. Send us your layout or drawing pack and we will return a specification sheet listing every item above, so the version you approve is the version that ships.