A hanging modular wardrobe looks deceptively simple on a drawing: carcass panels, rails, drawers, one clean front. On site it is the joinery item that exposes planning gaps fastest, because the wall has to carry what a floor-standing cabinet would normally take for itself. When the installation plan is thin, the problems surface late — after boards have shipped, after the bedroom floor is finished, after the trade sequence is locked in.

Our Hanging Modular Wardrobes are made to measure for each project, with the layout, finish and dimensions specified room by room. That flexibility is exactly why a written installation plan matters: it fixes the decisions before production starts, so what arrives on site matches what the wall and the trade programme can actually support. Below is the checklist we work through with buyers, contractors and designers.

1. A measured survey, not a drawn elevation

Take dimensions from a site survey of the completed shell rather than an architectural elevation. That usually means measuring each wall at several heights and widths instead of trusting two numbers off a drawing. The plan records:

  • Wall condition and construction. Substrate type, whether studs or framing are present, where they sit, and whether any wall is plasterboard over battens, masonry, or a lightweight partition. This determines the fixing method and whether a support frame is required.
  • Level and plumb, in both directions. Note the actual deviation across the run. A hung run amplifies out-of-level walls into visible scribe lines and misaligned door gaps.
  • Floor finish level. Record the finished floor height against the proposed bottom of the lowest unit, plus clearance for skirting, thresholds and door swings.
  • Obstructions. Sockets, switches, light points, radiators, downpipes, ceiling cornices, bulkheads, HVAC grilles and any service run that must be avoided or boxed in.
  • Access route to the room. Door widths, lift sizes, stair turns and corridor clearances for the largest panel. A panel that cannot reach the bedroom becomes a site-assembled problem nobody budgeted for.

Where rooms repeat across a villa or apartment project, the plan should still show per-room variations rather than assume one detail fits every bay.

2. Load path and fixing method, agreed before production

For a wall-mounted wardrobe run, the wall becomes part of the structure. The installation plan should state who confirms that capacity and how the load is transferred:

  • The intended total load: carcass weight plus contents, including dense hanging garments, boxes and any drawer stacks pulled out.
  • The fixing route — through fixings into framing or masonry, a concealed support rail or batten frame, or a floor-receiving plinth combined with wall restraint.
  • Fixing centres and the position of every bracket, so the fabrication drawing shows them rather than leaving it to the installer on the day.
  • Whether any reinforcement, blocking or a new substrate is needed — and which trade carries that work.
  • Sign-off responsibility: who confirms wall suitability in writing before panels are released for manufacture.

On older buildings and refurbished villas this is the point most often skipped. If the substrate turns out to be unsuitable after production, the fix is either a costly site-built frame or a change of wardrobe type.

If the wall cannot be verified before production, specify a supported configuration at the design stage instead of resolving it on site. Our team confirms dimensions and selected specifications for each project before manufacture begins.

3. Internal layout mapped to daily use

A hanging modular wardrobe only works if the internal zoning matches daily habits. In the plan, set out the split between hanging, drawer and shelf storage for each unit, and note the reasoning so the client can sign off against something concrete:

  • Hanging zones. Short-hang sections for shirts and jackets, long-hang sections for coats and dresses, plus any pull-down rail where the ceiling height makes a high rail awkward to reach.
  • Drawer zones. Our Drawer Focused Modular Wardrobes suit occupants who store most of their wardrobe flat — underwear, knitwear, accessories. Drawers sit best within easy reach and need clear front access, so they should not be buried behind a door hinge line.
  • Shelf zones. Our Shelf Focused Modular Wardrobes work for folded stacks, linens and display. Fixed shelves are cheaper; adjustable shelving costs more but survives changes in use.
  • Combination runs. Where one wall has to do all three jobs, our Combination Modular Wardrobes let you set the sequence module by module, keeping heavy drawer modules low and light shelf modules high.
  • Open and glass fronts. Where a display element is wanted, our Open Modular Wardrobes and Glass Modular Wardrobes change both the look and the dust-protection expectation, so note which sections are exposed.

For walk-in rooms on the same project, our Boutique Style Walk in Wardrobes follow the same planning discipline with circulation space added to the equation.

4. Door type and clearance study

Doors decide whether a hung wardrobe feels generous or cramped, and they interact with the rest of the room. The plan should answer:

  • Hinged, sliding or open. Sliding fronts need parallel clearance for the track; hinged fronts need swing room past the bed, the vanity and any opposite furniture.
  • The exact opening envelope for each door in its fully open position, checked against fixed furniture and architraves.
  • Track and hardware access. Sliding systems need service access to the running gear; the plan should not seal it behind a fixed lining.
  • Handle or handleless front, since an integrated handle profile changes the reveal at returns and at the ceiling line.

5. Interfaces with flooring, ceilings and electrical work

A hung wardrobe meets the floor, the ceiling and the electrical package, and it sits on a wall finish another trade applies. Write those junctions into the plan as details, not assumptions:

InterfaceWhat the plan must fix
FloorWhether the run stops above the finished floor or sits over a plinth; skirting treatment; protection of the completed floor during installation.
CeilingFull-height or scribed to an uneven soffit; cornice removal; access panel position if services run behind the top of the carcass.
Electrical and lightingInternal lighting points, driver location and how drivers remain reachable; switch position; any socket that must be relocated before panels go up.
Wall finishesPaint or wallpaper sequence relative to installation, so no visible touch-up line runs behind a carcass edge.

Integrated interior lighting is worth deciding early. Once the carcass is on the wall, chasing a new cable run is disruptive and often visible.

6. A sequence that matches the site programme

The plan should place wardrobe installation in the trade order rather than leaving it to whoever is free. A typical safe sequence:

  1. Survey of the completed shell, with wall suitability confirmed.
  2. Approval of shop drawings, including fixing positions and internal layout.
  3. Any blocking or reinforcement carried out and inspected.
  4. Wall finishes complete to the line agreed in the details.
  5. Delivery, inspection for transit damage, and staged storage near the room.
  6. Installation, alignment, door adjustment, snag list, handover.

Where a project is being supplied from overseas, this sequence has to be built around the shipping window as well. Our logistics service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery, so the plan can state when goods land rather than assume it. Installation support, snagging and after-sales handling are coordinated separately through our Installation & After-sales Support service.

7. Finish schedule and specification sign-off

Every module needs a finish reference in the plan — board material, surface finish, edge treatment, hardware finish, and door style — with one approved sample held on site for comparison at handover. Our Custom Minimalist Bedroom Wardrobe page shows how a flat-panel, handleless front is described in enough detail that a contractor can check the delivered work against it.

Close the plan with three signatures: the buyer or project manager, the designer, and the installer. That document is what you refer back to when a dimension is queried or a finish is disputed.

Common gaps we see in thin installation plans

  • No confirmation of wall substrate before production release.
  • Internal layout copied from a previous room instead of the actual occupant's storage habits.
  • Sliding door track sealed behind fixed linings with no service access.
  • Lighting drivers placed where no one can reach them.
  • Delivery route never measured, so large panels have to be cut or assembled on site.
  • No snag list at handover, which leaves adjustment work unclosed.

Frequently asked questions

Can a hanging modular wardrobe go on any wall?

No. Capacity depends on the substrate and framing behind the finish. Solid masonry and correctly spaced timber framing behave very differently from a lightweight partition. Verify the wall before committing to a fully suspended run, or specify a supported configuration.

Should the wardrobe be installed before or after the floor is laid?

It depends on the detail. A run that stops above the finished floor needs the flooring complete and protected; a plinth-based build can sit to a set-out before some floor works. Whichever you choose, record it in the plan so both trades work to the same line.

How are made-to-measure dimensions confirmed for several identical bedrooms?

Each room is surveyed individually. Nominally identical rooms vary enough in level, plumb and service positions that a single detail drawing applied to all of them usually produces visible gaps somewhere.

Next step

Send us the room drawings, the intended internal split, and any information you already have about wall construction. We will confirm dimensions and selected specifications for your project before production, which is far cheaper than resolving the same question on site with panels already delivered.