A set of white shaker cabinets looks simple on a drawing. Five-piece door, square profile, clean colour. That simplicity is exactly why the installation stage punishes poor preparation: with flat fronts and a light finish, every uneven wall, every out-of-level run and every mismatched worktop edge shows up immediately. An installation plan is what stands between a measured design and a kitchen that goes together in the sequence you expected.

Below is the working checklist we use when white shaker cabinetry is being supplied for a villa, apartment or hospitality unit — from the survey data you need before production to the handover record at the end.

1. Survey data that fixes the cabinet sizes

Made-to-measure cabinetry is only as accurate as the survey that defines it. Before any panel is cut, the plan should carry a dimensioned drawing of the room with:

  • Floor level and wall plumbness. Record high and low points along the whole run, not one corner. Shim allowance under toe kicks depends on this.
  • Finished floor levels. State whether the stated height includes tiles, screed or vinyl that have not been laid yet.
  • Obstructions. Downpipes, skirting, radiators, switch plates, air returns and existing architraves that must be cut around or removed.
  • Service positions. Water in and out, waste, gas, power outlets, hob extraction and the flue route, each with a measured height and set-out from a fixed corner.
  • Door and circulation clearances. Confirm that full-height carcasses and drawer fronts can be carried to the room intact, especially in apartments and upper floors.

Practical rule: any dimension you intend to build to should be measured twice from two different reference points. A single reading taken from a tile line that is itself out of square will transfer the error into every unit on the run.

2. A written specification, not a colour name

"White" covers warm white, cool white, off-white and grey-white, and shaker doors in different materials take that colour differently. The plan needs the actual specification agreed with the supplier, because cabinet fronts are usually the last element ordered and the hardest to replace.

ItemWhat to record in the plan
Finish and materialThe door construction and surface — painted, lacquered, PVC-wrapped or acrylic. Our shaker range includes painted shaker cabinets and plywood shaker style cabinets, each with its own edge detail and cleaning regime.
Colour referenceThe supplier's sample code, the sheen level, and a signed physical sample held on site. Screen-rendered whites are not reliable for matching.
Door profileCentre panel rebate depth, frame width and whether the shaker profile is applied or machined — this determines how the door meets hinges and handles.
CarcassBoard type, thickness, edge banding colour, back-panel fixing method and whether the carcass is fully enclosed.
IronmongeryHinge brand and closing action, drawer runner load rating, handle holes (drilled, undrilled or integrated profile), and door/drawer gap standard.
Integrated itemsAppliance recess dimensions, ventilation gaps, and any glass front shaker cabinets with their glazing type and shelf loading.

3. Interface decisions taken before the units arrive

Most installation arguments are interface arguments. Settling them on paper in advance keeps the site team from improvising on the day.

  • Worktop and splashback. Confirm who supplies and fits the worktop, its thickness, the edge profile, and how the front scribe and rear upstand are detailed. Note the cut-out positions for sink and hob before the tops are templated.
  • Tiling sequence. Decide whether wall units sit on tiled walls or on a marked set-out line, and where the splashback terminates relative to the cabinet fronts.
  • Cornice, scribe and filler panels. State the width of scribes at each end of the run, and whether a cornice or a shadow gap closes the top of the wall units.
  • Flooring transition. Record whether the toe kick is faced and recessed, and how the floor covering meets it.
  • Lighting and electrics. Internal cabinet lighting needs cable routes, transformer positions and a switch location agreed with the electrician before carcasses are fixed.
  • Adjoining joinery. Where the kitchen meets shaker panel wardrobes, tall storage or a utility room fit-out, fix the reveal between materials and who is responsible for the junction.

4. Sequencing, access and site readiness

The plan should name a readiness date and what has to be complete by it: first fix signed off, screed and tiles laid and dry, plaster finished and painted on the walls behind the units, and a clean, dry, lockable room for storage. Delivering cabinetry into an active wet trade is how white fronts get damaged.

Then set out the order of work:

  • Tall and appliance carcasses first — they set the vertical reference for everything else.
  • Base units along the primary run, levelled and linked, before any wall units go up.
  • Wall units hung on the confirmed set-out line, checked for level across the full run, not unit by unit.
  • Worktops templated or installed, then cut-outs made on site with the appliance dimensions in hand.
  • Doors and drawer fronts fitted last, then adjusted as a group so gaps are consistent along the whole kitchen.
  • Appliances connected, seals and trims completed, and all protective film removed.

5. Tolerance rules to write into the plan

White shaker fronts are unforgiving of small errors, so state the acceptable tolerances rather than leaving them to the fitter's judgement:

  • Runs level and plumb within a few millimetres across their full length, checked with a long straight edge.
  • Consistent door and drawer gaps throughout, with adjacent fronts flush at the face line.
  • Doors that swing freely without touching neighbouring fronts or handles when opened.
  • Drawer runners operating without binding at every pull position, including when loaded.
  • No visible fasteners, no scribe joints wider than the agreed detail, and no filler strips left proud of the carcass line.

6. Inspection, snags and handover

Close the job with a documented check rather than a verbal one. A practical snag sheet covers:

  • Every door and drawer opened, closed and adjusted; hinges re-checked after the building has been in use.
  • All surfaces inspected under daylight as well as artificial light — pale finishes reveal adhesive residue and handling marks late in the day.
  • Sealant lines at worktop and splashback junctions, clean and continuous.
  • Appliance fit, ventilation gaps met, and all cut edges sealed.
  • Care instructions issued for the specific finish, with spare doors, panels and ironmongery listed against the order so replacements can be matched later.

Specification details — materials, dimensions, finishes and load ratings — are confirmed per project at order stage. Confirm them against your own drawings and local requirements before installation begins.

How a supplier's coordination changes the plan

When cabinetry is ordered as made-to-measure work, the survey drawing, the specification sheet and the delivery schedule should come from one source rather than being reconciled on site. Where a project also needs flooring, wall panels, wardrobes and bathroom fixtures, coordinating them with the same supplier keeps the junction details consistent — which is where most of the rework happens.

SANTERSON manufactures cabinetry and interior products for villa, apartment and hospitality projects in Australia and elsewhere, covering custom built-in kitchen cabinets through the wider fit-out package, with production coordination, door-to-door delivery and on-site installation support listed as part of the service. Send us the room drawing and the finish you are working to, and we will return a specification for review before anything goes into production.