A swim spa is one of the few products on a villa or hospitality project that touches four disciplines at once: structure, waterproofing, mechanical plant and electrical supply. That is exactly why specifiers ask for a submittal before they release an order. A brochure page tells you what the shell looks like; a submittal package tells the architect, the M&E consultant, the main contractor and the local authority whether the unit can actually be installed on this site, in this country, at this level. Below is the package we would expect to assemble for Outdoor Swim Spa WS-PC07A-T, and what each part has to prove.
1. Identification: model, configuration and the drawing set
Start with a cover sheet that names the project, the supplier, the date, the revision number and the exact model as ordered. For this unit the catalog lists overall dimensions of 7000 × 3000 × 1470 mm, but a submittal cannot stop at three numbers. The reviewer needs dimensioned plans, sections and elevations that show where the shell sits relative to the finished deck level, how deep the pit or plinth has to be, where the access hatch falls, and which side carries the control system and equipment compartment.
Ask for these drawings at a legible scale with dimensions in millimetres, and check that the model code on every drawing matches the purchase order. A submittal that shows a generic shell drawing while the order references a "-T" variant is the most common reason packages come back for resubmission.
2. Equipment schedule: what is included and what is optional
The catalog specification for WS-PC07A-T records one control system, one swim training system, one water pump, one filter pump, a jet total of 56 pieces, four LED lights and a total power figure of 11.55 kW, with water jets, LED lighting, ozone and the swim training system shown as fitted features. Put every one of those lines into a schedule with make, model code, quantity and whether the item is standard or optional.
That last column matters more than it looks. The same catalog lists control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps as options, and availability varies by model. Two units can carry the same shell size and completely different plant rooms. Compare the schedule line by line against your own requirement list rather than accepting a single "standard specification" paragraph.
| Item to fix in the submittal | Why the reviewer needs it |
|---|---|
| Total connected power and supply arrangement | Drives cable sizing, breaker rating, protection device and whether a dedicated circuit is required from the distribution board. |
| Pump, filter and jet quantities with duty data | Confirms flow rate, filtration cycle and whether the seating or therapy layout matches the design intent. |
| Ozone and any UV sterilisation line | Chemical dosing strategy for the operator's maintenance plan depends on which sanitation option is fitted. |
| Insulation and steps as separate line items | Affects running energy cost, deck detailing around the entry and the access arrangement for users. |
3. Electrical documentation
This is where most swim spa submittals fail review. Request the wiring diagram, the control panel layout, the declared supply voltage and phase arrangement, the total connected load, the recommended protective device rating and the residual-current protection requirement. Confirm earthing and bonding provisions for a wet environment, and confirm who supplies the isolator and where it must be located relative to the water's edge.
Electrical acceptance is governed by the installation country, not by the factory. The submittal should therefore carry the supplier's declaration of what they deliver and a clear statement that final compliance with local wiring rules is confirmed by the local electrical contractor and inspector. We do not present foreign certification as proof of local approval.
4. Site, foundation and access data
The submittal needs the operating weight when full, the point or line load on the surrounding deck, the slab or plinth requirement, drainage provisions for the equipment compartment, and the clearance needed for service access to the pumps and filter. Also state the delivery route: a seven-metre shell has to reach the plot, pass through or over whatever is in the way, and be set down by crane or forklift.
Include a lifting and setting note with the suggested pick points and the equipment needed. Contractors plan the crane before they plan the plant room, and a submittal that ignores the delivery route reads as though nobody has thought past the factory gate.
5. Materials, finishes and durability evidence
List the shell material and laminate build-up, the frame and hardware materials, the finish options selected for this project, and the colour or trim codes as ordered. For an outdoor unit on a resort or villa terrace, also state what is exposed to sunlight, chlorine or salt air, and how each component is meant to be cleaned. Where a claim about material performance matters to the specifier, ask for the test report or the manufacturer's data sheet behind it rather than a marketing sentence.
6. Water treatment, commissioning and maintenance
Attach the filtration and sanitation description for the chosen configuration, the filling and draining arrangement, the commissioning checklist, and the recommended maintenance schedule with consumable and spare-part references. Hotel operators and facilities managers read this section first: they want to know what their team does weekly, which parts wear out, and how to order replacements years later.
7. Commercial terms and after-sales scope
Close the package with the warranty terms as written for this configuration, the spare-parts availability statement, the lead time from confirmed order to shipment, the packing and container loading plan, and the installation support actually provided. Our service pages describe door-to-door freight with customs paperwork, on-site installation support, snag inspection and after-sales assistance — but each project should receive those terms in writing for its own scope rather than reading them off a marketing page.
A quick pre-submission check
- Model code on drawings, specification sheet and purchase order all identical.
- Every optional item either priced in or explicitly excluded — no silent assumptions.
- Electrical data complete enough for the local engineer to size the circuit.
- Weights, foundation note and lifting plan attached for the structural reviewer.
- Warranty, spares and installation scope stated in writing for this project.
Note on figures: the dimensions, jet counts and power values quoted above are transcribed from the catalog entry for WS-PC07A-T. Options change the plant and therefore the electrical data, so treat the submittal drawings and specification sheet issued for your configuration as controlling.
Santerson has been manufacturing furniture and building materials in China since 2008 and supplies one-stop furniture and building materials packages for villa, hotel and office projects worldwide. If you are assembling a submittal for a swim spa package that also has to coordinate with luxury outdoor swim spas, poolside furniture or an outdoor kitchen, send us the model code and the project location and we will return the drawing set, equipment schedule and electrical data for that exact configuration.
Send your enquiry to Contact Us — Phone / WhatsApp +86-13928214007, email santerson@qq.com. Enquiries are answered within 24 hours during business hours, Monday to Saturday, 8:00 AM – 6:00 PM (GMT+8).