A request for quote that only says "L shaped corner cabinets, 6 metres" will come back with six different prices from six suppliers, and none of them will be comparable. What separates a usable quotation from an unusable one is the detail you hand over before the first number is calculated. Below is the information set we need at SANTERSON to quote L Shaped Corner Cabinets accurately, and what you should expect to see returned.

Start With the Two Numbers That Drive Everything Else

Corner cabinetry is priced from linear run and from the geometry of the return leg, not from a catalogue unit count. Before anything else, your RFQ should state:

  • The two wall runs meeting at the corner, measured in millimetres from a fixed reference point such as a completed structural wall face, plus the finished floor level.
  • The clear dimension at the corner itself — including any return that stops short of the wall because of a window, radiator, flue, piped shaft or appliance.
  • Base unit depth and wall unit depth you are working to, since an L configuration changes circulation width and door swing clearance in ways a straight run does not.

Send the drawings you actually have — even a dimensioned sketch photographed from site is better than nothing. Where a plan exists, mark which corner is being fitted and which leg carries the sink, hob or tall appliance housing, because those three items set the carcass specification more than any other decision.

State the Corner Mechanism You Want, or Ask to Be Quoted Options

This is where most RFQs go wrong. "Corner cabinet" describes a position, not a product. Two buyers with identical dimensions can end up with completely different hardware and therefore completely different prices. Specify the access solution, or ask the supplier to price alternatives side by side:

Access solutionWhat it doesWhat to state in the RFQ
Rotating carousel shelvingShelves rotate to bring contents to the front of the opening; suits deep, blind corners used for pots and bulk storage.Required shelf diameter range, load type, door opening angle.
Pull-out carousels and basket towersBaskets or tiers slide out on rails past the door line, so the full depth is reachable without crouching.Number of tiers, basket material, rail load rating, left- or right-hand approach.
Open shelf corner unitsNo doors and no mechanism; used for display, cookbooks or in open-plan layouts where the corner is a visual feature.Shelf spans, whether dust protection matters, adjacency to hob.
Glass front corner unitsDisplay glazing on an otherwise standard carcass; commonly used for china, glassware or lit niches.Glass type and tint, internal lighting, shelf material.
Diagonal (blind-corner) cabinet with shelvesThe simplest construction and usually the lowest cost, but the least usable storage.Whether usability or budget is the priority — say so plainly.

If you are undecided, write "please quote both carousel and pull-out options for this corner" in the RFQ. A supplier who quotes only one mechanism leaves you unable to compare against competitors, and a revision round later costs time you may not have.

Specify Materials, Finish and Edge Treatment

Carcass and door are separate specifications and should be quoted as such. In your RFQ, name:

  • Carcass board — moisture-resistant board where the corner sits beside a sink or dishwasher, standard board elsewhere.
  • Door material and surface — lacquer, laminate, veneer or solid timber, with matte, gloss or textured finish. Where a project already has a finish schedule, give the reference code rather than an adjective.
  • Edge treatment — edge banding colour match, ABS versus PVC versus painted edge, and whether 2 mm rounded edges are required for high-traffic or child-facing settings.
  • Colour source of truth — RAL code, Pantone reference, a physical sample you can post, or an existing installed run to match. "Grey" is not a specification.
  • Worktop interface — whether the corner unit must support a mitred worktop joint, a cut-out for a sink, or an angled splashback.

List Hardware and Tolerances Explicitly

Hardware is frequently excluded from the headline price and then added as extras. Put it in the RFQ so it appears in the comparison:

  • Hinges with or without soft close, and the opening angle needed where a corner door crosses an adjacent unit.
  • Drawer slides — full extension, load rating, integrated or push-to-open.
  • The carousel or pull-out mechanism brand and model if you have a preference; otherwise request the supplier's standard and its load rating.
  • Handles or handleless profile, including the profile radius where doors meet at an internal corner.
  • Plinth and scribe treatment: whether the corner runs continuous skirting or is scribed to an uneven wall.
  • Integrated lighting, including transformer location, which is easy to forget until the ceiling is closed.

Also state what the walls are like. Older residential and renovated villa projects rarely have square corners; if you know the corner is out of square, say so and ask for scribed panels rather than assuming a 90° carcass will fit.

Set Out Quantity, Site Context and Delivery Terms

A quotation for one kitchen and a quotation for forty identical apartment kitchens are prepared differently. Your RFQ should include:

  • Total corner units by type, plus how many repeated layouts exist across the project.
  • Whether the project is residential, serviced apartment, hotel or villa — this changes wear expectations and fire-performance discussion.
  • Destination city, port of entry, and whether you want delivery to a terminal or door-to-door to site.
  • Incoterms you intend to trade on, and who is handling import clearance.
  • Required site date for the first units, and whether staged delivery across phases is acceptable.
  • Whether installation support is in scope, or whether local fitters will install from supplier drawings.

A practical note on made-to-measure work. Corner cabinetry from a factory such as ours is produced to project-specific dimensions, so the numbers you send become the numbers we cut. Where an RFQ is issued before site survey, ask for the quotation to be marked "subject to site verification", and confirm final dimensions after screed, plaster and services are in place. That single line protects both sides from avoidable rework.

What a Complete Quotation Should Return

Before you compare suppliers, check that each quotation contains the same bones:

  • Itemised units with dimensions and mechanism named, not "1 set corner cabinet".
  • Carcass, door, edge and hardware specified separately.
  • Mechanism brand or grade, with load rating.
  • Packaging description and total package count, so you can plan site storage and lifts.
  • Pack list per unit, and whether units arrive assembled or flat-packed.
  • Lead time stated as production plus transit, not one blended figure.
  • Validity period of the price, and what triggers a revision.
  • Whether spares — extra hinges, rails, shelf pins — are included or priced separately.

How We Handle Corner Cabinetry Enquiries

SANTERSON is a China-based furniture and building materials manufacturer supplying custom built-in kitchen cabinets for hotel, apartment and residential projects, with made-to-measure sizing, material and finish options and layout tailored to the space. Our corner range covers several access solutions, including Pull Out Corner Cabinets for full-depth reach and Lazy Susan Corner Cabinets for blind corners used for heavier items. Because cabinetry is one part of a wider fit-out, buyers often quote corner units alongside wardrobes, vanities, wall panelling and flooring in the same package, which reduces the number of separate deliveries landing on site.

Send drawings, the two wall runs, your mechanism preference and your finish reference, and you will receive an itemised quotation rather than an estimate. If your project needs more than cabinetry — joinery, doors, panelling or lighting from one production source — say so at RFQ stage; scope agreed early is usually cheaper than scope added later.

All dimensions, mechanisms and finishes in a quotation are confirmed against approved shop drawings before production. Please verify final site dimensions before releasing an order.